2023/05/17 Southern California Edison Distribution Line Service Extension AgreementDescription Amount
Service Request Number: 3478588 Project:
LINE EXT FOR NEW FIRE STATION
29745 GOETZ RD MENIFEE CA 92587
Install - Billing Option:SCE INSTALL - DISCOUNT
29714 HAUN RD
MENIFEE CA 92586
Telephone:
MENIFEE, CITY OF
SCE Contact:Nicholas Ryan Lopez
Invoice Date:03/29/2023
26100 MENIFEE ROAD
MENIFEE CA 92585
Southern California Edison Company
Document #7590487042
Invoice # 501301
Item #529950
Design #: 1598674
2097543 - LINE EXTENSION
Product:$46,440.37
Previous Payment $0.00
* Enclosed are two copies of your invoice. Please return one copy of the invoice with your payment to Accounts
Receivable in the enclosed return-addressed envelope. The other copy of the invoice is for your records.
* ALL PRICES ARE APPLICABLE FOR A PERIOD OF 90 DAYS FROM THIS DATE AND ARE SUBJECT TO
CHANGE THEREAFTER.
* All payments must be delivered by mail, an alternate postal method, or one of our electronic payment options.
Walk-in payments are no longer accepted at any SCE location, including Accounts Receivable.
* Please complete all applications and/or contracts and return to your planning office, using the enclosed
return-addressed envelope.
* For the Refundable and Discount Option appendices, choose only one option. Sign "Has Chosen" on the appropriate
option and sign "Has Not Chosen" on the other option. Only sign each form once. Return both forms in the enclosed
self-addressed envelope.
* If a street light work order is associated with this project, contracts for that project will be enclosed.
* Easement documents will be mailed directly to you from our Right of Way department. Please complete and return
them as soon as possible, as we will not be able to proceed with the project without clearance
* Call the Edison company at 1-800-655-4555 to make application for electrical service.
* An Edison Inspector must approve all underground systems. Please call your designated inspector 48 hours prior to
construction to schedule an inspection.
* Final electrical inspection from the local governmental building and safety department must be received before we can
energize your service.
* By paying this invoice, customer acknowledges and agrees that if this project is canceled by customer for any reason
or customer does not proceed with the project completion.
* Any expense incurred by SCE, including, but not limited to, expenses related to engineering, inspection and
construction, prior to the project cancellation or completion will be deducted from any applicable refund due to the
customer.
* To ensure worker and public safety, please maintain the appropriate clearance distance from utility infrastructure
during your construction project to avoid encroachments that may result in serious injury or damage.
* If relocation of existing utility infrastructure is pending, please adjust your work around the proposed relocation
schedule as appropriate. If you have any questions, please contact the designated SCE representative assigned to your
project.
.
$ 46,440.37
COMMENTS:
TOTAL PROJECT INVOICE AMOUNT:
DocuSign Envelope ID: 9A68AA9B-67CC-4C3A-88C4-C1143D7F85E8
Description Amount
Service Request Number: 3478588 Project:
LINE EXT FOR NEW FIRE STATION
29745 GOETZ RD MENIFEE CA 92587
Install - Billing Option:SCE INSTALL - DISCOUNT
29714 HAUN RD
MENIFEE CA 92586
Telephone:
MENIFEE, CITY OF
SCE Contact:Nicholas Ryan Lopez
Invoice Date:03/29/2023
26100 MENIFEE ROAD
MENIFEE CA 92585
Southern California Edison Company
Document #7590487042
Invoice # 501301
Please detach and return payment stub with payment
Payment
Stub
MENIFEE, CITY OF
29714 HAUN RD
MENIFEE CA 92586
Please pay total amount now due:$ 46,440.37
Thank you for paying promptly
Make check payable to Southern California EdisonDocument #7590487042
ATTN: Accounts Receivable
PO Box 800
Rosemead, CA 91771-001
ADDITIONAL PAYMENT INSTRUCTIONS:
If paying by check, please follow instructions on payment stub
JP Morgan Chase Bank
New York, NY
ABA#: 021000021 - Acct#: 323-394434
SCE Taxpayer ID No. 95-1240335
Document #:7590487042
SCE Contact:
Southern California Edison
Attn: Accounts Receivable
8631 Rush Street G-53
Rosemead, CA 91770
Nicholas Ryan Lopez
Instructions for wire or ACH payments:
*** Failure to properly identify your document number and SCE contact may delay the application
of funds and initiation of your project
Special Instructions for overnight delivery methods:
DocuSign Envelope ID: 9A68AA9B-67CC-4C3A-88C4-C1143D7F85E8
LOC.W.O.A.I.JOB #
APPENDIX A - DISCOUNT OPTION
ELECTRIC LINE EXTENSION AGREEMENT
4/20/2023 12:00:00AM
LINE EXTENSION 2097543
1. SCE RULE 16 COST TO SERVE
(A) SCE RULE 16 COST TO SERVE
(B) LESS APPLICANT ALLOWANCES
(C) EXCESS RULE 16 COST TO SERVE (LINE 5. (A))
(D) EXCESS ALLOWANCES TO (LINE 2.)
SCE COST TO SERVE RULE 15
(E) OVERHEAD 0 FEET X $.00 UNIT COST $.00
(F) UNDERGROUND 0 FEET X $.00 UNIT COST $.00
(G) PROJECT SPECIFIC (IF 2X UNIT COST OR COMPETITIVE BID)
(H) TOTAL SCE RULE 15 COST TO SERVE
2. APPLICANT ALLOWANCES (FROM LINE 1. (D)
3. REFUNDABLE:
(A) SCE RULE 15 COST TO SERVE (LINE 1. (H))
(B) PLUS ESTIMATED VALUE OF STRUCTURES
(C) SUBTOTAL (LINE 3. (A) + 3. (B))
(D) LESS ALLOWANCE (LINE 2)
(E) REFUNDABLE AMOUNT (LINE 3. (C) - 3. (D))
(F) PLUS REFUNDABLE ITCC* ON LINE 3. (E)
4. PAYMENT OPTION SELECTED: DISCOUNT HAS CHOSEN: SIGN
(A) NON-REFUNDABLE DISCOUNT OPTION: 50 %
50 % OF LINE 3G:1)
2)VALUE OF STRUCTURES:
3)
4)
NON -REFUNDABLE PAYMENT:
AMOUNT DUE APPLICANT:
5. OTHER NON-REFUNDABLE ADVANCE & CREDITS
(A) OTHER NON-REFUNDABLE CHARGES
(RULE 16, FLAT RATE, INSPECTION, R/W, ETC.)
(B) ITCC* ON OTHER NON-REFUNDABLE
(C) ITCC* ON APPLICANT FURNISHED FACILITIES.
(D) INSTALLED COST OF SUBSTRUCTURES BY SCE
(E) LESS APPLICANT DESIGN OR REIMBURSABLE CREDITS
(F) TOTAL NON-REFUNDABLE (LINE 5. (A) THRU 5. (D) - 5. (E))
(G) TOTAL CREDITS (LINE 5. (E) - 5. (A) THRU 5. (D))
6. AMOUNT TO BE PAID BY APPLICANT TO SCE
7. AMOUNT TO BE REFUNDED TO APPLICANT UPON FULFILLMENT OF ALL
CONTRACTUAL OBLIGATIONS
HAS NOT CHOSEN: SIGN
* INCOME TAX COMPONENT OF CONTRIBUTION
(G) TOTAL AMOUNT (LINE 3. (E) + 3. (F))
$29,629.44
$5,718.00
$23,911.44
$0.00
$23,794.92
$23,794.92
$0.00
$23,794.92
$0.00
$23,794.92
$0.00
$23,794.92
$5,710.79
$29,505.71
$14,752.86
$0.00
$14,752.86
$0.00
$25,554.44
$6,133.07
$0.00
$0.00
$0.00
$31,687.51
$0.00
$46,440.37
$0.00
DocuSign Envelope ID: 9A68AA9B-67CC-4C3A-88C4-C1143D7F85E8
I Choose Discount Payment Option
Description Amount
Service Request Number: 3478588 Project:
LINE EXT FOR NEW FIRE STATION
29745 GOETZ RD MENIFEE CA 92587
Install - Billing Option:SCE INSTALL - REFUNDABLE
29714 HAUN RD
MENIFEE CA 92586
Telephone:
MENIFEE, CITY OF
SCE Contact:Nicholas Ryan Lopez
Invoice Date:03/29/2023
26100 MENIFEE ROAD
MENIFEE CA 92585
Southern California Edison Company
Document #7590487044
Invoice # 501301
Item #529950
Design #: 1598674
2097543 - LINE EXTENSION
Product:$61,193.22
Previous Payment $0.00
* Enclosed are two copies of your invoice. Please return one copy of the invoice with your payment to Accounts
Receivable in the enclosed return-addressed envelope. The other copy of the invoice is for your records.
* ALL PRICES ARE APPLICABLE FOR A PERIOD OF 90 DAYS FROM THIS DATE AND ARE SUBJECT TO
CHANGE THEREAFTER.
* All payments must be delivered by mail, an alternate postal method, or one of our electronic payment options.
Walk-in payments are no longer accepted at any SCE location, including Accounts Receivable.
* Please complete all applications and/or contracts and return to your planning office, using the enclosed
return-addressed envelope.
* For the Refundable and Discount Option appendices, choose only one option. Sign "Has Chosen" on the appropriate
option and sign "Has Not Chosen" on the other option. Only sign each form once. Return both forms in the enclosed
self-addressed envelope.
* If a street light work order is associated with this project, contracts for that project will be enclosed.
* Easement documents will be mailed directly to you from our Right of Way department. Please complete and return
them as soon as possible, as we will not be able to proceed with the project without clearance
* Call the Edison company at 1-800-655-4555 to make application for electrical service.
* An Edison Inspector must approve all underground systems. Please call your designated inspector 48 hours prior to
construction to schedule an inspection.
* Final electrical inspection from the local governmental building and safety department must be received before we can
energize your service.
* By paying this invoice, customer acknowledges and agrees that if this project is canceled by customer for any reason
or customer does not proceed with the project completion.
* Any expense incurred by SCE, including, but not limited to, expenses related to engineering, inspection and
construction, prior to the project cancellation or completion will be deducted from any applicable refund due to the
customer.
* To ensure worker and public safety, please maintain the appropriate clearance distance from utility infrastructure
during your construction project to avoid encroachments that may result in serious injury or damage.
* If relocation of existing utility infrastructure is pending, please adjust your work around the proposed relocation
schedule as appropriate. If you have any questions, please contact the designated SCE representative assigned to your
project.
.
$ 61,193.22
COMMENTS:
TOTAL PROJECT INVOICE AMOUNT:
DocuSign Envelope ID: 9A68AA9B-67CC-4C3A-88C4-C1143D7F85E8
Description Amount
Service Request Number: 3478588 Project:
LINE EXT FOR NEW FIRE STATION
29745 GOETZ RD MENIFEE CA 92587
Install - Billing Option:SCE INSTALL - REFUNDABLE
29714 HAUN RD
MENIFEE CA 92586
Telephone:
MENIFEE, CITY OF
SCE Contact:Nicholas Ryan Lopez
Invoice Date:03/29/2023
26100 MENIFEE ROAD
MENIFEE CA 92585
Southern California Edison Company
Document #7590487044
Invoice # 501301
Please detach and return payment stub with payment
Payment
Stub
MENIFEE, CITY OF
29714 HAUN RD
MENIFEE CA 92586
Please pay total amount now due:$ 61,193.22
Thank you for paying promptly
Make check payable to Southern California EdisonDocument #7590487044
ATTN: Accounts Receivable
PO Box 800
Rosemead, CA 91771-001
ADDITIONAL PAYMENT INSTRUCTIONS:
If paying by check, please follow instructions on payment stub
JP Morgan Chase Bank
New York, NY
ABA#: 021000021 - Acct#: 323-394434
SCE Taxpayer ID No. 95-1240335
Document #:7590487044
SCE Contact:
Southern California Edison
Attn: Accounts Receivable
8631 Rush Street G-53
Rosemead, CA 91770
Nicholas Ryan Lopez
Instructions for wire or ACH payments:
*** Failure to properly identify your document number and SCE contact may delay the application
of funds and initiation of your project
Special Instructions for overnight delivery methods:
DocuSign Envelope ID: 9A68AA9B-67CC-4C3A-88C4-C1143D7F85E8
LOC.W.O.A.I.
APPENDIX A - REFUNDABLE OPTION
ELECTRIC LINE EXTENSION AGREEMENT
JOB #
04/20/2023
LINE EXTENSION 2097543
1. SCE RULE 16 COST TO SERVE
(A) SCE RULE 16 COST TO SERVE
(B) LESS APPLICANT ALLOWANCES
(C) EXCESS RULE 16 COST TO (LINE 5. (A))
(D) EXCESS ALLOWANCES TO (LINE 2.)
SCE COST TO SERVE RULE 15
(E) OVERHEAD 0 FEET X $.00 UNIT COST $.00
(F) UNDERGROUND
(G) PROJECT SPECIFIC ( IF 2X UNIT COST OR COMPETITIVE BID )
(H) TOTAL SCE RULE 15 COST TO SERVE
0 FEET X $.00 UNIT COST $.00
2 . APPLICANT ALLOWANCES (FROM LINE 1. (D) )
3 . REFUNDABLE :
(A) SCE RULE 15 COST TO SERVE (LINE 1 . (H) )
(B) PLUS ESTIMATED VALUE OF STRUCTURES
(C) SUBTOTAL ( LINE 3 . (A) + 3 . (B) )
(D) LESS ALLOWANCE ( LINE 2 )
(E) REFUNDABLE AMOUNT ( LINE 3 . (C) - 3 . (D) )
(F) PLUS REFUNDABLE ITCC* ON LINE 3. (E)
(G) TOTAL AMOUNT ( LINE 3 . (E) + 3 . (F) )
4 . PAYMENT OPTION SELECTED : REFUNDABLE HAS CHOSEN :SIGN
(A) REFUNDABLE OPTION :LINE 3 . (G)
1 )
2 )
3 )
VALUE OF STRUCTURES :
REFUNDABLE PAYMENT :
AMOUNT SUBJECT TO REFUND/CREDIT
5 . OTHER NON-REFUNDABLE ADVANCES & CREDITS
(A) OTHER NON-REFUNDABLE CHARGES
( RULE 16 , FLAT RATE , INSPECTION , R/W , ETC . )
(B) ITCC* ON OTHER NON-REFUNDABLE
(C) ITCC* ON APPLICANT FURNISHED FACILITIES
(D) INSTALLED COST OF SUBSTRUCTURE BY SCE
(E) LESS APPLICANT DESIGN OR REIMBURSABLE CREDITS
(F) TOTAL NON-REFUNDABLE ( LINE 5 . (A) THRU 5 . (D) - 5 . (E) )
(G) TOTAL CREDITS ( LINE 5 . (E) - 5 . (A) THRU 5 . (D) )
6 . AMOUNT TO BE PAID BY APPLICANT TO SCE
7 . AMOUNT TO BE REFUNDED TO APPLICANT UPON FULFILLMENT OF ALL
CONTRACTUAL OBLIGATIONS
HAS NOT CHOSEN : SIGN
* INCOME TAX COMPONENT OF CONTRIBUTION
$29,629.44
$5,718.00
$23,911.44
$0.00
$23,794.92
$23,794.92
$0.00
$23,794.92
$0.00
$23,794.92
$0.00
$23,794.92
$5,710.79
$29,505.71
$29,505.71
$0.00
$29,505.71
$29,505.71
$25,554.44
$6,133.07
$0.00
$0.00
$0.00
$31,687.51
$0.00
$61,193.22
$0.00
DocuSign Envelope ID: 9A68AA9B-67CC-4C3A-88C4-C1143D7F85E8
Product Number :
Project Specific Location :
SCE’s estimated refundable costs:*
SCE Rule 16 credit amount :*
SCE street light credit amount :*
SCE associated work credit amount :*
SOUTHERN CALIFORNIA EDISON ( "SCE " )
DISTRIBUTION LINE AND/OR SERVICE EXTENSION
APPLICANT'S INSTALLATION OPTION AND
STATEMENT OF APPLICANT'S CONTRACT ANTICIPATED COSTS
Applicant :
29745 GOETZ RD CA 92587
$23,794.92
$23,653.42
$0.00
$0.00
2097543
1. INSTALLATION OPTIONS
Applicant understands that in accordance with SCE’s Rule 15 and/or Rule 16, Applicant can elect to
have either SCE install the Distribution Line and/or Service Extension or a Qualified
Contractor/Subcontractor install the Distribution Line and/or Service Extension.
2. SCE’S ESTIMATED REFUNDABLE COST INFORMATION
SCE’s estimated refundable costs are based on the work that SCE would normally perform that can
be performed by a Qualified Contractor/Subcontractor under the provisions of the Applicant
Installation Option, Rule 15, Section G, and in accordance with SCE’s Terms and Conditions
Agreement for Installation of Distribution Line Extension by Applicant (Form 14-188).
If applicable, other estimated cost information may be provided below. This could include the credit
amount for Rule 16, street light, or other associated installation work.
3. APPLICANT SELECTION
Applicant understands the installation options under Section 1 above, and hereby elects the following
Installation Option by initialing the appropriate selection below:
_________ Installation by SCE
_________ Installation by Qualified Contractor/Subcontractor
Under installation by Qualified Contractor/Subcontractor, Applicant shall secure project specific bid
information from Qualified Contractors/Subcontractors for the installation of the Distribution Line
and/or Service extension. Applicant shall contribute or advance before the start of construction any
refundable or non-refundable amounts as specified in Rules 15 and 16.
*Please refer to the specific contract, Appendix A, for detailed financial information.
Form 14-754, Rev. 2/2013
DocuSign Envelope ID: 9A68AA9B-67CC-4C3A-88C4-C1143D7F85E8
X
City of Menifee
4.APPLICANT'S CONTRACT ANTICIPATED COST INFORMATION (to be completed only
if installation is performed by a Qualified Contractor/Subcontractor as selected in Section 3 above)
Option 1 Applicant elects to provide SCE with the Applicants Contract Anticipated Costs, which are
subject to refund, that are associated with that portion of the new Distribution Line and/or
Service Extension normally installed by SCE, and understands that the lower of SCE's
estimated refundable cost or the Applicant's Contract Anticipated Costs, which are subject
to refund, as submitted below, shall apply to any applicable SCE refunds and allowances
provided in accordance with Rule 15 and 16, 1 or
Option 2 Applicant elects not to provide SCE with the Applicants Contract Anticipated Costs, which
are subject to refund. The Applicant understands that by selecting this option, the Applicant
is directing SCE to use SCE's estimated refundable cost for all billing and accounting.
Applicant understands the Applicants Cost Information, as described above, and hereby elects the
following by initialing the appropriate selection below :
________Option 1 - Applicants Contract Anticipated Costs $ _________________
________Option 2 - SCE's Estimated Refundable Costs $ _________________
5.ITCC
SCE shall value all trenching, conduit, backfill, street repair, substructures, and encasement, based on
SCE's estimate of such items, for the purpose of collecting the applicable governmental taxes
(ITCC) on contributions to SCE.
6.UTILITY RESPONSIBILITIES
Upon receipt of this completed and signed form, SCE shall begin the process of producing the
applicable contracts and forms based on the selection made by the Applicant.
Applicant and/or Applicant’s Qualified Contractor/Subcontractor understands that for the portion of
the Electrical Distribution and/or Service Extension that SCE would normally install, in accordance
with SCE’s Rule’s 15 and/or 16 and the Terms and Conditions Agreement for Installation of
Distribution Line Extension by Applicant, the Applicant, prior to performing any work associated
with the installation of these electrical facilities, and for the purpose of utility billing and accounting,
shall elect one of the following options, and return this form to SCE prior to SCE proceeding with any
further work on the Applicant’s project.
Form 14-754, Rev. 2/2013
DocuSign Envelope ID: 9A68AA9B-67CC-4C3A-88C4-C1143D7F85E8
7.SIGNATURE
I declare under penalty of perjury that the foregoing is true and correct
Applicant : ______________________________________________
Corporation, Partnership, or DBA: ____________________________
Name of Authorized Individual: ______________________________
Applicant’s signature: ______________________________________
Title: ___________________________________
Date: __________________________
1 Excludes the estimated costs of work the Applicant cannot perform, such as, work on or in proximity
to, energized equipment.
Form 14-754, Rev. 2/2013
DocuSign Envelope ID: 9A68AA9B-67CC-4C3A-88C4-C1143D7F85E8
City of Menifee
Public Works Director
Nicolas Fidler
5/30/2023
Form No. 16-330 1
Rev. 11/18
CONTRACT FOR EXTENSION OF ELECTRIC DISTRIBUTION LINE
RULE 15
1.PARTIES
This Contract for Extension of Electric Distribution Line ("Contract") is issued this day of
, .
The Parties to this Contract are: MENIFEE, CITY OF
("Applicant")
and Southern California Edison Company ("SCE"). Applicant and SCE are referred to individually as
"Party" and collectively as "Parties".
2.RECITALS
Applicant has requested SCE, pursuant to SCE's Rule 15, Distribution Line Extensions, to install an
electric Distribution Line Extension to the location or locations described as follows: 29745 GOETZ RD MENIFEE CA 92587
(Hereinafter referred to as "Project")
3.AGREEMENT
3.1 Responsibilities of Applicant
Construction
Applicant shall, in accordance with SCE's specifications and timing requirements for the
Project:
o Perform route clearing, tree trimming, trenching, excavating, and backfilling and
compacting;
o Furnish imported backfill material and dispose of trench spoil as required;
o Furnish, install and transfer ownership to SCE any substructures, conduit, and
protective structures required;
o Obtain any necessary construction permits for all work performed by Applicant under
this Contract.
If Applicant elects to have SCE perform any part of this work, Applicant shall pay to SCE, as
specified herein and before the start of construction, SCE's estimated-installed costs thereof.
20TH
APRIL 2023
DocuSign Envelope ID: 9A68AA9B-67CC-4C3A-88C4-C1143D7F85E8
City of Menifee
5/30/2023
Form No. 16-330 2
Rev. 11/18
Rights of Way
Applicant hereby grants to SCE the rights of way and easements for the Distribution Line
Extension over the shortest, most practical, available, and acceptable route within Applicant's
property for the purpose of making delivery of electric service hereunder. Such easement
shall include the right of access and right to trim trees as necessary. Where formal rights of
way, easements, land leases, or permits are required by SCE for installation of facilities on
or over Applicant's property, or the property of others, Applicant understands and agrees that
SCE shall not be obligated to install the Distribution Line Extension for the Project unless and
until any necessary permanent rights of way, easements, land leases, and permits,
satisfactory to SCE, are granted to or obtained for SCE without cost to or condemnation by
SCE.
Advances
Applicant shall contribute or advance, before the start of construction, the refundable and
non-refundable amounts as set forth in Appendix A to this Contract. This includes the costs
for substructures and conduits which SCE had previously installed at its expense in
anticipation of the current Distribution Line Extension. Any necessary riser conduit, conduit
covering, and miscellaneous riser material required for the Distribution Line Extension shall
be furnished or paid for by Applicant and shall be installed by SCE.
All contributions and advances by Applicant are taxable and shall include an Income Tax
Component of Contribution (ITCC) at the rate provided in SCE's Preliminary Statement.
ITCC will be either refundable or non-refundable depending on whether the corresponding
contribution or advance is refundable or non-refundable.
Joint Applicants. The total contribution or advance from joint Applicants will be apportioned
by SCE among the members of the group in such manner as Applicants mutually agree.
3.2 Responsibilities of SCE
Construction
SCE shall install, own, operate, and maintain the Distribution Line Extension to serve the
Project. SCE will install only those facilities that, in SCE's judgment, will be used within a
reasonable time to serve permanent loads.
Refunds
SCE shall make refunds to Applicant in accordance with the provisions of Rule 15.
3.3 Ownership of Facilities
Title to and ownership of the Distribution Line Extension shall vest in SCE. Applicant does
hereby agree that upon completion and acceptance by SCE of any Applicant-installed
facilities, title to each and every component part thereof shall immediately pass to SCE free
and clear of all liens and encumbrances.
DocuSign Envelope ID: 9A68AA9B-67CC-4C3A-88C4-C1143D7F85E8
Form No. 16-330 3
Rev. 11/18
3.4 Service Facilities
Service extensions shall be installed pursuant to SCE's Rule 16, Service Extensions.
3.5 Street Lighting Facilities
Street lighting and Distribution Line Extensions within the Project solely for service to street
lighting equipment shall be installed in accordance with the appropriate street light tariff
schedule. Street light revenues are not applicable toward allowances or refunds for
Distribution Line Extensions. Electroliers shall be located at points determined by the
governmental agency having jurisdiction over streets to be dedicated to that agency or by
Applicant for privately owned and maintained streets open to and used by the general public.
3.6 Non-Refundable Discount Option
In lieu of contributing the total refundable amount, Applicant has the option of contributing,
on a non-refundable basis, a percentage of such refundable amount as set forth in Appendix
A to this Contract. Applicant has or has not chosen this option as indicated by signature on
Appendix A.
3.7 Refunds
The total refundable amount shall be subject to refund, without interest, in accordance with
the provisions of Rule 15, which include the following:
Residential. Refunds will be made on the basis of any new customer permanent load
connected to the Distribution Line Extension which produces additional revenues to SCE.
The refund will be deducted from the total refundable amount, and the remaining amount
subject to refund will represent that portion of the Distribution Line Extension cost not
supported by revenues.
Non-Residential. Refunds will be made on the basis of Applicant or any new customer
permanent load connected to the Distribution Line Extension which produces additional
revenues to SCE. SCE shall be responsible to review Applicant's actual net revenue for the
first three years from the date SCE is first ready to serve. Applicant shall be responsible for
notifying SCE if new, permanent load is added the fourth through tenth year from the date
SCE is first ready to serve. Such review shall determine if additional net revenue justifies
refunds to Applicant.
Unsupported Distribution Line Extension Cost. When any portion of a refundable amount
has not qualified for a refund at the end of twelve (12) months from the date SCE is first ready
to serve, Applicant will pay to SCE a Monthly Ownership Charge of 0.40% on the remaining (R)
refundable balance. The difference between the total refundable advance and any refunds
made or eligible to be made to Applicant shall serve as the basis of a monthly ownership
charge ("base"). The Monthly Ownership Charge includes replacement for 60 years at no
additional cost and is derived from the Customer-Financed With Replacement at Additional
Cost Added Facilities rates determined in SCE’s general rate case proceeding and/or
periodic annual review. Monthly ownership charges are distinct from the refundable amount
and will normally be accumulated and deducted from refunds due to Applicant. This provision
does not apply to individual residential Applicants.
DocuSign Envelope ID: 9A68AA9B-67CC-4C3A-88C4-C1143D7F85E8
Form No. 16-330 4
Rev. 11/18
The monthly ownership charges herein shall automatically increase or decrease if the
California Public Utilities Commission should subsequently authorize a higher or lower
percentage rate for the monthly ownership charges, effective on the date of such
authorization.
Refund Period. The total refundable amount is subject to refund for a period of ten (10)
years after the Distribution Line Extension is first ready to serve. Any unrefunded amount
remaining at the end of the ten-year period shall become property of SCE.
3.8 Payment Adjustments
Contract Compliance. If, after six (6) months following the date SCE is first ready to serve
residential loads for which allowances were granted, one (1) year for non-residential loads,
Applicant fails to take service, or fails to use the service contracted for, Applicant shall pay to
SCE an additional contribution, based on the allowances for the revenue actually generated.
Excess Facilities. If the load information provided by Applicant results in SCE having
installed facilities which are in excess of those needed to serve the actual loads, and SCE
elects to reduce such excess facilities, Applicant shall pay to SCE its estimated total costs to
remove, abandon, or replace the excess facilities, less the estimated salvage of any removed
facilities.
3.9 Reimbursement to Applicant
Where mutually agreed upon by SCE and Applicant, Applicant may perform SCE's work or
install facilities normally installed by SCE. Such work shall be in accordance with SCE's
specifications and timing requirements. SCE shall reimburse Applicant SCE's estimated
installed cost of such facilities and work by applying a credit toward Applicant's advance. Any
amount not so credited shall be reimbursed to Applicant upon acceptance of the work and
facilities by SCE.
3.10 Delays in Construction
Force Majeure. SCE shall not be responsible for any delay in the installation or completion
of the facilities by SCE resulting from the late performance of Applicant's responsibilities
under this Contract, shortage of labor or material, strike, labor disturbance, war, riot, weather
conditions, governmental rule, regulation or order, including orders or judgements of any
court or commission, delay in obtaining necessary land rights, act of God, or any other cause
or condition beyond the control of SCE.
Resources. SCE shall have the right, in the event it is unable to obtain sufficient supplies,
materials, or labor for all of its construction requirements, to allocate materials and labor to
construction projects which it deems, in its sole discretion, most important to serve the needs
of its customers. Any delay in construction hereunder resulting from such allocation shall be
deemed to be cause beyond SCE's control.
DocuSign Envelope ID: 9A68AA9B-67CC-4C3A-88C4-C1143D7F85E8
Form No. 16-330 5
Rev. 11/18
Contract Revision. If Applicant does not commence installation of any facilities which are
Applicant's responsibility or SCE is prevented from commencing the installation of the
facilities for causes beyond its reasonable control within one year from the effective date of
this Contract, SCE may, in its discretion, revise its cost estimate and recalculate the
refundable and/or non-refundable amounts set forth herein. SCE will notify Applicant of such
increased costs and give the option to either terminate this Contract or pay SCE the additional
charges.
3.11 Contract Termination
If at any time during the term of this Contract, SCE is not the sole deliverer of electrical
requirements for the Project, this Contract may be terminated. Upon termination of the
Contract, Applicant agrees to forfeit that portion of the advance paid to SCE for its expenses
covering any engineering, surveying, right of way acquisition and other associated work
incurred by SCE. If such expenses are greater or less than the refundable and/or non-
refundable advance, Applicant shall pay to SCE, or SCE shall refund the balance to
Applicant, without interest, as the case may be.
3.12 Indemnification
Applicant shall, at its own cost, defend, indemnify, and hold harmless SCE, its officers,
agents, employees, assigns, and successors in interest from and against any and all liability,
damages, losses, claims, demands, actions, causes of action, costs including attorney's fees
and expenses, or any of them, resulting from the death or injury to any person or damages
to any property caused by Applicant or its contractor and employees, officers or agents of
either Applicant or its contractor, or any of them, and arising out of the performance or
nonperformance of their obligations under this Contract.
3.13 Assignment of Contract
Applicant may assign this Contract, in whole or in part, only if SCE consents in writing and
the party to whom the Contract is assigned agrees in writing, to perform the obligations of
Applicant hereunder. Assignment of the Contract shall not release Applicant from any of the
obligations under this Contract unless otherwise provided therein.
3.14 Joint and Several Liability
Where two or more individuals or entities are joint Applicants under this Contract, all
Applicants shall be jointly and severally liable to comply with all terms and conditions herein.
DocuSign Envelope ID: 9A68AA9B-67CC-4C3A-88C4-C1143D7F85E8
Form No. 16-330 6
Rev. 11/18
3.15 Warranty
Applicant warrants that all work and/or equipment furnished or installed by Applicant or its
contractor shall be free of defects in workmanship and material. The warranty period shall
begin from the date of final acceptance by SCE and extend for one (1) year. Should the work
develop defects during that period, SCE, at its election, shall either (a) repair or replace the
defective work and/or equipment, or (b) demand that Applicant repair or replace the defective
work and/or equipment and, in either event, Applicant shall be liable for all costs associated
with such repair and/or replacement. Applicant upon demand by SCE, shall promptly correct,
to SCE's satisfaction and that of any governmental agency having jurisdiction, any breach of
any warranty.
3.16 Contract Effective Date
This Contract shall not be effective unless it is (1) signed by SCE’s authorized individual, (2)
executed and delivered by Applicant to SCE together with payment required hereunder within
ninety (90) days of the date in Paragraph 1 of this Contract and (3) accepted by SCE. This
Contract shall then be effective on the date executed by SCE and shall take effect without
further notice to Applicant.
3.17 Commission Jurisdiction
This Contract is subject to the applicable provisions of SCE's tariffs, including Rule 15, filed
and authorized by the California Public Utilities Commission.
This Contract shall, at all times, be subject to such changes or modifications by the Public
Utilities Commission of the State of California, as said Commission may, from time to time,
direct in the exercise of its jurisdiction.
3.18 Completion Date
The completion date requested by Applicant is .
4.SIGNATURE CLAUSE
The signatories hereto represent that they have been appropriately authorized to enter into this
Contract on behalf of the party for whom they sign.
APPLICANT(S)
CORPORATION, PARTNERSHIP, OR DBA:
NAME OF AUTHORIZED INDIVIDUAL:
SIGNATURE:
TITLE:
MAILING ADDRESS:
TELEPHONE:
DocuSign Envelope ID: 9A68AA9B-67CC-4C3A-88C4-C1143D7F85E8
Nicolas Fidler
29844 Huan Road Menifee CA 92586
City of Menifee
951-723-3703
Public Works Director
Form No. 16-330 7
Rev. 11/18
ADDITIONAL SIGNATURES FOR JOINT APPLICANTS
NAME OF AUTHORIZED INDIVIDUAL:
SIGNATURE:
TITLE:
MAILING ADDRESS:
TELEPHONE:
NAME OF AUTHORIZED INDIVIDUAL:
SIGNATURE:
TITLE:
MAILING ADDRESS:
TELEPHONE:
APPORTIONMENT OF ADVANCE AMONG JOINT APPLICANTS:
SOUTHERN CALIFORNIA EDISON COMPANY
NAME OF AUTHORIZED INDIVIDUAL:
SIGNATURE:
TITLE:
DATE EXECUTED:
PRODUCT NO. 2097543
DocuSign Envelope ID: 9A68AA9B-67CC-4C3A-88C4-C1143D7F85E8
Jose Camarena Jr
6/2/2023
PLANNING MANAGER
DocuSign Envelope ID: 9A68AA9B-67CC-4C3A-88C4-C1143D7F85E8
DocuSign Envelope ID: 9A68AA9B-67CC-4C3A-88C4-C1143D7F85E8
Certificate Of Completion
Envelope Id: 9A68AA9B67CC4C3A88C4C1143D7F85E8 Status: Completed
Subject: Please DocuSign: TD2097543 R15 Edison Install Package.pdf
Custom Envelope Field: TD2097543 CONTRACT
Source Envelope:
Document Pages: 18 Signatures: 6 Envelope Originator:
Certificate Pages: 5 Initials: 0 DOCUSIGN INBOX
AutoNav: Enabled
EnvelopeId Stamping: Enabled
Time Zone: (UTC-08:00) Pacific Time (US & Canada)
P.O. Box 700
Rosemead, CA 91770
DOCUSIGN.INBOX@SCE.COM
IP Address: 163.116.248.47
Record Tracking
Status: Original
4/20/2023 9:54:04 AM
Holder: DOCUSIGN INBOX
DOCUSIGN.INBOX@SCE.COM
Location: DocuSign
Signer Events Signature Timestamp
Nicolas Fidler
nfidler@cityofmenifee.us
Public Works Director
City of Menifee
Security Level: Email, Account Authentication
(None)
Signature Adoption: Pre-selected Style
Using IP Address: 47.180.183.201
Sent: 4/20/2023 10:00:56 AM
Viewed: 4/20/2023 10:05:42 AM
Signed: 5/30/2023 4:15:17 PM
Electronic Record and Signature Disclosure:
Accepted: 4/20/2023 10:05:42 AM
ID: d8e9b26d-2d9f-4f5e-bdd1-074c143a41a4
Jose Camarena Jr
jose.camarena@sce.com
PLANNING MANAGER
Southern California Edison Company
Security Level: Email, Account Authentication
(None)
Signature Adoption: Pre-selected Style
Using IP Address: 163.116.248.48
Sent: 6/2/2023 7:31:47 AM
Viewed: 6/2/2023 7:39:36 AM
Signed: 6/2/2023 7:40:19 AM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
In Person Signer Events Signature Timestamp
Editor Delivery Events Status Timestamp
DOCUSIGN INBOX
docusign.inbox@sce.com
Southern California Edison Company
Security Level: Email, Account Authentication
(None)
Using IP Address: 163.116.248.42
Sent: 5/30/2023 4:15:19 PM
Viewed: 6/2/2023 7:31:42 AM
Completed: 6/2/2023 7:31:47 AM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Agent Delivery Events Status Timestamp
Intermediary Delivery Events Status Timestamp
Certified Delivery Events Status Timestamp
Carbon Copy Events Status Timestamp
Carbon Copy Events Status Timestamp
Nicholas R Lopez
Nicholas.Lopez@sce.com
Security Level: Email, Account Authentication
(None)
Sent: 6/2/2023 7:40:21 AM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
DCCM
DCCM@sce.com
Security Level: Email, Account Authentication
(None)
Sent: 6/2/2023 7:40:22 AM
Electronic Record and Signature Disclosure:
Accepted: 1/28/2021 7:49:52 AM
ID: b2f3ce52-71ac-4dcc-8f40-32dae4378a57
DesignSupport Communications
designsupportcommunications@sce.com
Southern California Edison Company
Security Level: Email, Account Authentication
(None)
Sent: 6/2/2023 7:40:22 AM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Witness Events Signature Timestamp
Notary Events Signature Timestamp
Envelope Summary Events Status Timestamps
Envelope Sent Hashed/Encrypted 4/20/2023 10:00:56 AM
Certified Delivered Security Checked 6/2/2023 7:39:36 AM
Signing Complete Security Checked 6/2/2023 7:40:19 AM
Completed Security Checked 6/2/2023 7:40:22 AM
Payment Events Status Timestamps
Electronic Record and Signature Disclosure
ELECTRONIC RECORD AND SIGNATURE DISCLOSURE
From time to time, Southern California Edison Company (we, us or Company) may be required
by law to provide to you certain written notices or disclosures. Described below are the terms
and conditions for providing to you such notices and disclosures electronically through the
DocuSign system. Please read the information below carefully and thoroughly, and if you can
access this information electronically to your satisfaction and agree to this Electronic Record and
Signature Disclosure (ERSD), please confirm your agreement by selecting the check-box next to
‘I agree to use electronic records and signatures’ before clicking ‘CONTINUE’ within the
DocuSign system.
Getting paper copies
At any time, you may request from us a paper copy of any record provided or made available
electronically to you by us. You will have the ability to download and print documents we send
to you through the DocuSign system during and immediately after the signing session and, if you
elect to create a DocuSign account, you may access the documents for a limited period of time
(usually 30 days) after such documents are first sent to you. After such time, if you wish for us to
send you paper copies of any such documents from our office to you, you will be charged a
$0.00 per-page fee. You may request delivery of such paper copies from us by following the
procedure described below.
Withdrawing your consent
If you decide to receive notices and disclosures from us electronically, you may at any time
change your mind and tell us that thereafter you want to receive required notices and disclosures
only in paper format. How you must inform us of your decision to receive future notices and
disclosure in paper format and withdraw your consent to receive notices and disclosures
electronically is described below.
Consequences of changing your mind
If you elect to receive required notices and disclosures only in paper format, it will slow the
speed at which we can complete certain steps in transactions with you and delivering services to
you because we will need first to send the required notices or disclosures to you in paper format,
and then wait until we receive back from you your acknowledgment of your receipt of such
paper notices or disclosures. Further, you will no longer be able to use the DocuSign system to
receive required notices and consents electronically from us or to sign electronically documents
from us.
All notices and disclosures will be sent to you electronically
Electronic Record and Signature Disclosure created on: 1/26/2021 9:55:29 PM
Parties agreed to: Nicolas Fidler, DCCM
Unless you tell us otherwise in accordance with the procedures described herein, we will provide
electronically to you through the DocuSign system all required notices, disclosures,
authorizations, acknowledgements, and other documents that are required to be provided or made
available to you during the course of our relationship with you. To reduce the chance of you
inadvertently not receiving any notice or disclosure, we prefer to provide all of the required
notices and disclosures to you by the same method and to the same address that you have given
us. Thus, you can receive all the disclosures and notices electronically or in paper format through
the paper mail delivery system. If you do not agree with this process, please let us know as
described below. Please also see the paragraph immediately above that describes the
consequences of your electing not to receive delivery of the notices and disclosures
electronically from us.
How to contact Southern California Edison Company:
You may contact us to let us know of your changes as to how we may contact you electronically,
to request paper copies of certain information from us, and to withdraw your prior consent to
receive notices and disclosures electronically as follows:
To contact us by email send messages to: IGInformationgovernance@sce.com
To advise Southern California Edison Company of your new email address
To let us know of a change in your email address where we should send notices and disclosures
electronically to you, you must send an email message to us
at IGInformationgovernance@sce.com and in the body of such request you must state: your
previous email address, your new email address. We do not require any other information from
you to change your email address.
If you created a DocuSign account, you may update it with your new email address through your
account preferences.
To request paper copies from Southern California Edison Company
To request delivery from us of paper copies of the notices and disclosures previously provided
by us to you electronically, you must send us an email
to IGInformationgovernance@sce.com and in the body of such request you must state your email
address, full name, mailing address, and telephone number. We will bill you for any fees at that
time, if any.
To withdraw your consent with Southern California Edison Company
To inform us that you no longer wish to receive future notices and disclosures in electronic
format you may:
i. decline to sign a document from within your signing session, and on the subsequent page,
select the check-box indicating you wish to withdraw your consent, or you may;
ii. send us an email to IGInformationgovernance@sce.com and in the body of such request you
must state your email, full name, mailing address, and telephone number. We do not need any
other information from you to withdraw consent.. The consequences of your withdrawing
consent for online documents will be that transactions may take a longer time to process..
Required hardware and software
The minimum system requirements for using the DocuSign system may change over time. The
current system requirements are found here: https://support.docusign.com/guides/signer-guide-
signing-system-requirements.
Acknowledging your access and consent to receive and sign documents electronically
To confirm to us that you can access this information electronically, which will be similar to
other electronic notices and disclosures that we will provide to you, please confirm that you have
read this ERSD, and (i) that you are able to print on paper or electronically save this ERSD for
your future reference and access; or (ii) that you are able to email this ERSD to an email address
where you will be able to print on paper or save it for your future reference and access. Further,
if you consent to receiving notices and disclosures exclusively in electronic format as described
herein, then select the check-box next to ‘I agree to use electronic records and signatures’ before
clicking ‘CONTINUE’ within the DocuSign system.
By selecting the check-box next to ‘I agree to use electronic records and signatures’, you confirm
that:
You can access and read this Electronic Record and Signature Disclosure; and
You can print on paper this Electronic Record and Signature Disclosure, or save or send
this Electronic Record and Disclosure to a location where you can print it, for future
reference and access; and
Until or unless you notify Southern California Edison Company as described above, you
consent to receive exclusively through electronic means all notices, disclosures,
authorizations, acknowledgements, and other documents that are required to be provided
or made available to you by Southern California Edison Company during the course of
your relationship with Southern California Edison Company.