2020-06-03 City Council Item No. 11.2 Legado Newport Pacific Land Applicant Presentation Regular MEETING - Additional Meeting MaterialsCity Council Meeting
June 3, 2020
1
•Newport Pacific Land is Committed to Investing in Local Neighborhoods through Community Partnerships and Local School Support
2
3
Project Timeline
•Land Acquisition –December 2016
•Planning Commission Workshop –March 2017
•Initiate and Process Specific Plan and Tentative Maps –2017 –2018
•Legado Concept –January 2019
•Revise Community Vision and Continue Project Processing –2019 –2020
•Planning Commission Hearing –May 2020
•City Council Meeting –June 2020
4
Goals and Objectives
To Identify Community Needs through Extensive Public
Outreach and Coordination with City Staff and Civic Leaders
To Create a New Community that Responds to the Needs of
Present and Future Residents
To Build a Community for All Ages that Encourages Creativity
and Wellness
Community Outreach
•Held Community Meetings:
•Life Care Center
•Rancho La Vita
•Bel Air Mobile Estates
•Evans Brown Mortuary
•Chamber of Commerce
•Boys & Girls Club
•Menifee Union School District
•Menifee Community Partners
•Sent Resident Letters & Direct Mailers to
373 Neighbors around the Project Site
•Email Newsletter Sent to 350 Members
of the Community
•Created a Project Website
•www.legado-menifee.com 5
6
7
Fleming Ranch 2017 2020
•1,123 Units
•19.2 Acres of Public Open Space
•Lot Sizes 4,000 –6,500 SF
•Active Adult Overlay
•Neighborhood Parks Surrounded by New Homes
•1,022 Units (per TTM)
•20.8 Acres of Public Open Space
•Lot Sizes 5,000 –7,000 SF.
•Removed Active Adult Overlay
•Community Park Adjacent to Hans Christensen
Middle School
•Additional Public Park Amenities
$23 Million in Excess
Contributions for Public Benefits
8
•$8.4 Million in Circulation Improvements
•McCall Boulevard
•Encanto Drive
•Ethanac Road
•Sherman Road
•$6.6 Million in Drainage Improvements
•Over 800 Acre Drainage Solution
•Resolves Seasonal Flooding Along Encanto Drive
•$8.0 Million in Public Park Improvements
9
Public Neighborhood Parks
9
•Gathering Spaces
•Picnic Tables and Shelter
•Tot Lot
•Outdoor Classroom
•Community Garden Plots
•Reading Garden
10
Paseo Legado
•1/3 Mile Public Trail with Workout Exercise Stations
•Chest press
•Elliptical
•Pull-ups
•Stretching
•1/3 Mile Public Trail with Interactive Art and Music Pieces
•Engaging Play
•Hands-On Activities
•Creative Expression 10
Public Multi-Use Trails
11
Wellness Walks
Public Community Park
•Walking Trail
•3 Full-Size Soccer Fields with Sports Lighting
•Community Center
•$8.0 Million Developer Contribution 12
•Tot Lots for 2 Age Groups
•Adjacent to Hans Christensen Middle School
Honoring Historic Route 395
13
•Locations will be Represented with a Historical Marker
•Contributing to the “Three Flags Highway, Historic Route 395”
•Will Showcase Historic Route 395 from Canada to Mexico
Monument Post MarkerMonument
14
Project Buildout Timeline
•Start Grading-2021
•Start Home Construction–2022
•First Occupancies –2022 –2023
•Community Buildout –2023 –2030
•* Depending on Market Conditions
Project Amenities Timeline
Paseo Legado and Neighborhood Parks
*In Each Village
Paseo and Park Plot Plan Approval 1
Paseo and Park Construction
Drawing Approval 70
Paseo and Park Completion 140
Task Completed CofO
Community Park and Community Center
*In Overall Community
Community Park Plot Plan Approval 250
Community Park Construction
Drawing Approval 300
Community Park Completion 500
Community Center
Construction Drawing Approval 600
Community Center Completion 750
15
16
Summary
Identify Create Build
Staff Recommendation
17
Adopt 7 Resolutions to:
•Certify the EIR and Adopt the Statement of Overriding Considerations
•Approve the Specific Plan and Change of Zone
•Approve the Tentative Tract Maps
•Approve the Development Agreement
Thank You
18
Questions?
Public Community Center Concept
•Seamlessly Integrated Community Center for all Menifee Residents
•Local Community Groups and After School Programs will Benefit from a Safe and Centralized Gathering Spot
•Adjacent to Hans Christensen
Middle School
•$3.0 Million Developer Contribution 19
Public Community Center Concept
•Developer Proposal:
•Multi-Purpose Rooms for Groups of
20 to 200 persons
•Outdoor Room with Overflow Space
for 50 Persons
•Flexible Space
•Office & Storage Space
•Concessions
•Restrooms
•Final Design To Be Determined by
Extensive Community Involvement
Managed by the City of Menifee 20