2020-05-13 City Council Item No. 4.1 Capital Improvement Program Update Fiscal Year 2019-2020 Presentation Regular MEETING - Additional Meeting MaterialsCapital Improvement Program Update
FY 2019-20
Jonathan G. Smith
Director of Public Works/City Engineer
May 13, 2020
Discussion
•The capital improvement projects have long-term life spans and are
generally non-recurring and multi-year.
•They were developed based on economic feasibility, community
enhancement, infrastructure needs, safety and community needs.
•The following list of projects were adopted by City Council in June
2019.
FY 19/20 Project List and Status
*Excludes 14 Community Services Department projects budgeted at $2,597,000
Projects highlighted in BLUE are Multi-Year projects
Project Category Project
Number Project Name Past Years
Allocation
FY 19-20
Allocation
Spent to
date
Fiscal Year
End Estimate Project Status
Anticipated
Construction
Start/End
Transportation CIP 13-03 Holland Road Overpass $5,253,070 $10,668,576 $4,572,121 $4,979,921 ROW Nov-21
Transportation CIP 13-04 Bradley Bridge over Salt Creek $729,511 $250,000 $713,226 $743,226 Permits TBD
Transportation CIP 20-01 Scott Road/Bundy Canyon Road Widening $2,971,794 $595,465 $720,465 Design TBD
Transportation CIP 20-05 Garbani Rd/I-215 IC (Feasibility Study)$360,000 $49,113 $89,113 Design TBD
Traffic Signal CIP 16-07 Traffic Signal Interconnect (West) HSIP 7 $571,700 $191,300 $35,721 $155,721 Construction Sep-20
Traffic Signal CIP 16-08 Traffic Signal Interconnect (East) HSIP 7 $569,900 $41,100 $110,685 $520,685 Construction Jun-20
Traffic Signal CIP 20-06 Menifee/Holland Traffic Signal $475,000 $18,605 $168,605 Construction Oct-20
Traffic Signal CIP 20-07 Menifee/Camino Cristal Traffic Signal $475,000 $19,000 $169,000 Construction Oct-20
St. Improvement CIP 20-02 Sherman Rd and Ethanac Rd Street Resurfacing $1,735,000 $161,165 $661,165 Construction Aug-20
St. Improvement CIP 20-03 Goetz Road AC Resurfacing $1,265,288 $93,260 $1,093,260 Construction Jun-20
St. Improvement CIP 20-12 Adams Street Improvements -Phase 2 $274,210 $36,440 $70,100 Design Nov-20
Drainage Menifee Master Drainage Plan $442,860 $127,977 $277,977 Design Dec-20
Facilities CIP 16-13 Maintenance and Operations Center (Phase 2)$230,000 $150,000 $71,598 $75,000 Final Design Oct-20
Facilities CIP 19-18 Menifee Interim Police Facility $1,500,000 $1,274,678 $1,500,000 Construction Jun-20
PMP*FY 19-20 Pavement Management Program $3,285,000 $533,644 $3,285,000 Construction May-20
TOTAL $7,354,181 $24,085,128 $8,412,698 $14,509,237
FY 19/20 Program Overview (PMP)
Pavement Management Project (PMP)Project Budget Project Status
Anticipated
Construction
Start/End
PMP 19-01 Miralago/Lakepointe Street Resurfacing $443,715 Completed
PMP 20-01 Arterial Road Resurfacing $856,285 Construction Jun-20
PMP 20-02 Quail Valley East Street resurfacing $617,000 Construction May-20
CIP 20-10 Andalusia/Belcanto AC resurfacing $1,368,000 Construction May-20
TOTAL $3,285,000
All Projects Overview
Project No.Project Name Environ.Constructon
Start
Construct.
%
Construction
End
Completed FY 19-20:
1 CIP 17-02 Lyle Marsh All Inclusive Playground CEQA Exempt 100%
2 CIP 18-05 McCall and Newport Sidewalk links CEQA Exempt 100%
3 CIP 18-08 Adams Avenue Resurfacing from Antelope Road to 3rd Street CEQA Exempt 100%
4 CIP 19-04 Traffic Signal at McCall/Oakhurst CEQA Exempt 100%
5 CIP 19-05 Traffic Signal at Murrieta Road/Park City Avenue CEQA Exempt 100%
6 CIP 19-08 Encanto Neighborhoods Street Resurfacing CEQA Exempt 100%
7 CIP 20-10 Andalusia/Belcanto Ac resurfacing CEQA Exempt 100%
8 PMP 19-01 MIralago/Lakepointe Street Resurfacing CEQA Exempt 100%
9 PMP 19-02 Quail Valley west Street Resurfacing CEQA Exempt 100%
10 PMP 19-03 Menifee Lakes Slurry Seal Phase 1 CEQA Exempt 100%
11 PMP 20-01
Arterial Road Resurfacing:
CEQA Exempt 100%-Newport Road Resurfacing (Murrieta to City Limits)
-Murrieta Road Resurfacing (McCall Boulevard to Rouse Rd)
-Scott Road Resurfacing (Menifee Road to City Limits)
12 PMP 20-02 PMP 20-02 Quail Valley East Street resurfacing CEQA Exempt 100%
Under Design:
1 Menifee Active Transportation Plan
2 Menifee Master Drainage Plan
3 CIP 13-03 Holland Road Overpass CEQA MND Winter 2021 Summer 2023
4 CIP 13-04 Bradley Bridge over Salt Creek CEQA MND TBD TBD
5 CIP 19-03 Antelope Road Safety Medians –HSIP 9 NEPA TBD TBD
6 CIP 19-16 Lazy Creek Campus Improvements CEQA Exempt
7 CIP 20-01 Scott Road/Bundy Canyon Road Widening EIR -MND TBD TBD
8 CIP 20-04 Paloma Wash Trail Improvements CEQA Exempt Feb-21 Jun-21
9 CIP 20-05 Garbani Rd/I-215 Interchange NEPA
10 CIP 20-11 Scott Road/Menifee Road Missing Sidewalks CEQA Exempt Aug-20 Nov-20
11 CIP 20-12 Adams Street Improvements from 3rd street to Watson Road CEQA Exempt Sep-20 Nov-20
12 CIP 20-13 Paloma Wash Pedestrain Bridge
All Projects Overview
Project No.Project Name Environ.Constructon
Start
Construct.
%
Construction
End
Under Construction:
1 CIP 14-03 Scott Road/I-215 Interchange NEPA 90%
2 CIP 16-07 Traffic Signal Interconnect (West) HSIP 7 0%Jun-20
3 CIP 16-08 Traffic Signal Interconnect (East) HSIP 7 NEPA Exempt Jan-20 40%Jun-20
4 CIP 17-05 Citywide ADA improvements at Signalized Intersection –HSIP 8 NEPA Exempt May-20 0%Aug-20
5 CIP 19-06 Scott Road/Murrieta Road Traffic Signal EIR Mitigation May-20 0%Oct-20
6 CIP 19-18 Menifee Police Headquarters 80%Jun-20
7 CIP 20-02 Sherman Rd and Ethanac Rd Street Resurfacing CEQA Exempt May-20 0%Aug-20
8 CIP 20-03 Goetz Road AC Resurfacing CEQA Exempt Mar-20 5%Jun-20
9 CIP 20-06 Menifee/Holland Traffic Signal CEQA Exempt May-20 0%Oct-20
10 CIP 20-07 Menifee/Camino Cristal Traffic Signal CEQA Exempt May-20 0%Oct-20
Ready for Construction:
1 CIP 16-13 Menifee Operations Center (MOC)CEQA Exempt Jul-20 Oct-20
2 CIP 19-02 Murrieta Road Resurfacing (McCall to Salt Creek)CEQA Exempt Jul-20 Oct-20
PMP: Menifee Lakes Slurry Seal –Phase 134
Status:
•Project Completed
•Project Cost: $ 398,152
•Funding Sources: Gas Tax,
Capital Projects
PMP Arterial Roads Resurfacing
Status:
•Construction start: April
2020
•Construction completion:
June 2020
•Contractor: Roy Allen
Slurry
PMP Quail Valley East
Status:
•Construction start: March 2020
•Construction completion: May 2020
•Contractor: American asphalt South
CIP 20-03 Goetz Road Resurfacing
Status:
•Construction start: April
2020
•Construction completion:
June 2020
•Contractor: Hardy and
Harper, Inc.
CIP 20-10 Belcanto &Andalusia Neighborhoods
Status:
•Construction start: February 2020
•Construction completion: May 2020
•Contractor: All American Asphalt
CIP 20-02 Sherman/Ethanac/Mathews
Resurfacing
Status:
•Construction start: May 2020
•Construction completion: Aug. 2020
•Contractor: All American Asphalt
City Traffic Signal Projects
Traffic signal installation takes an estimated 8-9 months to complete due to
various factors such as location, type, size, shipping, weather, etc.
Project No. Location Phase
Anticipated
Construction
Start/End
CIP 16-07 Traffic Signal Interconnect (West) HSIP 7*Construction Sep-20
CIP 16-08 Traffic Signal Interconnect (East) HSIP 7*Construction Jun-20
CIP 17-05 Citywide ADA Upgrades at Traffic Signals HSIP 8*Construction Aug-20
CIP 19-06 Scott Rd/Murrieta Rd Construction Oct-20
CIP 20-06 Menifee Rd/Holland Rd Construction Oct-20
CIP 20-07 Menifee Rd/Camino Cristal Construction Oct-20
* Wireless upgrades to all existing signals
Antelope Road Raised Safety Median Project
CIP 19-03 (2018) -HSIP Cycle 9
Status:
•Funded by Federal Grant –Highway
Safety Improvement Program (HSIP)
Cycle 9
•Multi-year project
•Design is 30% complete
•Schedule:
-Design End: July 2020
-FHWA Construction Fund Request:
August 2020 through January 2021
-Bid and Award: January 2021 through
March 2021.
-Construction Start: April 2021
CIP 14-03 Scott Road / I-215 Interchange
Status:
•Design began 2003
•Construction start October 2018
•Loop ramps near completion
•Construction completion: June 2020
•Construction Cost: $26,423,544
CIP 13-03 Holland Road Overpass
Status:
•Multi-year project
•Currently in Right-of-Way acquisition
•Design is 95% Compete
•Estimated construction start: Winter 2021
•Estimated construction end: Summer 2023
CIP 13-04 Bradley Bridge over Salt Creek
Status:
•Multi-year project
•Design complete
•Currently being reviewed by permitting agencies: US Army Corps of Engineers,
California Fish and Wildlife, Regional Water Quality Control Board, Riverside Flood
Control And Water Conservation District
•Construction phased programmed to be funded by FY 2023-24
CIP 20-01 Scott Road / Bundy Canyon
Road Widening
Status:
•Multi-year project
•Design is 30% complete
•Estimated design completion: August 2022
•Estimated construction start: TBD
CIP 20-05 Garbani Road / I-215 Interchange
Status:
•Multi-year project
•Contract awarded January 15, 2020
•Feasibility study est. August 2020
•Next Phase: Project Initiation Development
and Preliminary Study Report (PID/PSR)
Programmed fro FY 2020-21
CIP 16-13 Maintenance & Operations Center –
Phase 2 •Additional Exterior Improvements: Trash
Enclosure, Landscape screening, equipment
and material bays.
•Design 95% complete
•Construction Start: July 2020
CIP 20-12 Adams Avenue Improvements Phase 2
Status:
•Multi-year project
•Design is 90% complete
•Estimated construction
start: October 2020
•Estimated construction
completion: January
2021
CIP 20-08 Menifee Interim Police Facility
Status:
•In construction phase
•Estimated construction completion: June 2020
Menifee Master Drainage Plan (MDP)
Status:
•Multi-year project
•Contract awarded October 2019
•MDP December 2020
QUESTIONS?