2020-05-13 City Council Item No. 4.1 5 Year Capital Improvement Program Fiscal Years 2020-2021 to 2024-2025 Presentation Regular MEETING - Additional Meeting MaterialsCITY OF MENIFEE 5 YEAR CAPITAL IMPROVEMENT PROGRAM Fiscal Years 2020-21 to 2024-25 CIP GOALS The goals of the City’s Capital Improvement Program (CIP) are based on the framework of the City’s Mission Statement: That Menifee be recognized as a safe, clean, vibrant and innovative community which responds to the diverse needs of its residents, businesses and visitors The CIP is critically important and one of the major responsibilities of a local agency •The City’s CIP Program has two parts –a capital budget and a capital program o The capital budget is the upcoming FY 2020-21 spending plan for capital items o The capital program is a plan for capital expenditures that extends four years beyond the capital budget •Together, the two parts make up the City’s 5 Year CIP Program Capital Budget and Capital Program •The City developed a 5-year CIP to advance the goals and objectives of the City’s General plan •The 5-year CIP is a short-range plan which identifies Capital projects, equipment purchases and major studies for the City in conjunction with financial projections •The plan provides a working document for sustaining and improving the City’ infrastructure by coordinating strategic planning, financial capacity, and feasibility of each Capital Project 5 YEAR CIP There is a total of 117 capital projects identified in the City’s 5-year CIP under six general categories: 5 YEAR CIP PROJECT TYPE # OF PROJECTS PROJECTED COSTS Transportation Projects 25 $213,065,384 Traffic Signal Projects 22 $9,912,340 Street Improvement and Rehabilitation Projects 30 $23,175,879 Drainage Projects 13 $35,398,000.00 Facilities Projects 8 $86,370,000.00 Community Services Department Projects 19 $25,094,038 117 $393,015,641 •Staff evaluated the projects identified in the 5-year CIP as consistent with the goals and policies of the City’s General Plan •The 5-year CIP plan will facilitate the implementation of the General Plan by ensuring that infrastructure exists and delivered in a timely manner to advance the City’s strategic and long- term goals and objectives 5 YEAR CIP AND THE GENERAL PLAN FY 2020-21 CAPITAL PROJECTS Project Category Project Number Project Name FY 20-21 Allocation Transportation CIP 13-03 Holland Road Overpass $3,383,164 Transportation CIP 13-04 Bradley Road Bridge over Salt Creek $2,174,209 Transportation CIP 14-01 McCall Boulevard/I-215 Interchange $700,000 Transportation CIP 20-05 Garbani Road/ I-215 Interchange $646,869 Transportation CIP 20-13 Paloma Wash Pedestrian Bridge $870,000 Traffic Signal PW-TS-03 Menifee Road/La Piedra Road $500,000 St. Improvement CIP 19-02 Murrieta Road -McCall Boulevard to Salt Creek $1,237,589 St. Improvement CIP 20-11 Scott Road and Menifee Road Sidewalk $266,737 St. Improvement CIP 20-12 Adams Avenue Improvements -Phase 2 $219,473 St. Improvement PW-IMP-01 Hillpointe Community Street Resurfacing $975,000 St. Improvement PW-IMP-03 McCall Boulevard -Encanto Road to Antelope Road $924,729 St. Improvement PW-IMP-9 Haun Road Bus Shelter $40,000 Facilities PW-BLD-01 Fire Station #68 -Interior Improvements $200,000 Facilities PW-BLD-02 New Quail Valley Fire Station #5 -Design $820,000 Facilities PW-BLD-03 New City Hall –Feasibility Study Update $200,000 C.S.CS007 Park Amenity Enhancements $113,000 C.S.CS009 Irrigation Upgrades and Control Systems $25,000 C. S.CS010 Evans Park Design/Construction $350,000 C. S.CS014 Park Lighting $50,000 C. S.CS015 Sports Field Lighting $250,000 C.S.CS022 IT Network Upgrades $75,000 C. S.CS023 Trails Connectivity and Enhancements $170,000 C.S.CS030 Central Park Ammenities $900,000 C. S.CS042 Sports Court Resurfacing $100,000 C. S.CS047 Shade Structures $320,000 25 Projects TOTAL $15,510,771 FY 2020-21 Capital Projects Estimated Costs Category Estimated Total Cost % Transportation $ 7,774,242 50% Traffic Signals $ 500,000 3% Street Improvements $ 3,663,529 24% Drainage Improvements $ -0% Facilities $ 1,220,000 8% Parks and Trails (C.S.)$ 2,353,000 15% TOTAL $ 15,510,771 100% FY 2020-21 Estimated Available Funding Sources Fund #Fund Name Available Expenditure % used 100 General Fund $450,000 $450,000 100.0% 105 Measure DD $2,059,400 $2,059,400 100.0% 200 Gas Tax $137,589 $137,589 100.0% 201 RMRA (SB1)$1,706,886 $1,706,886 100.0% 220 Measure A $317,844 $317,844 100.0% 301 Grants $0 $0 310 TUMF $2,941,579 $700,000 23.8% 320 Capital Projects $1,381,174 $1,381,174 100.0% 410 Scott Road RBBD $646,869 $646,869 100.0% 415 Menifee Valley RBBD $973,386 $973,386 100.0% 460 CSA 86 $707,988 $0 0.0% 481 CDBG $219,473 $219,473 100.0% 490 CFD 2012-1 Audie Murphy Ranch $1,696,049 $525,000 31.0% 501 DIF 16 -Fire $61,669 $0 0.0% 502 DIF 16 -Signals $92,340 $0 0.0% 503 DIF 16 -Parks $23,886 $0 0.0% 504 DIF 16 -Trails $11,400 $0 0.0% 507 DIF 17 -Public Facilities $2,984,558 $1,250,000 41.9% 508 DIF 17 -Fire $3,080,073 $820,000 26.6% 509 DIF 17 -Roads $0 $0 510 DIF 17 -Signals $0 $0 511 DIF 17 -Parks $60,861 $50,000 82.2% 512 DIF 17 -Trails $951,246 $690,000 72.5% 520 DIF Citywide -Public Use & Comm. Fac.$116,424 $0 0.0% 521 DIF Citywide -Fire Facilities $496,885 $200,000 40.3% 522 DIF Citywide -Park Improvements $501,704 $373,000 74.3% 526 DIF Citywide -Circulation $2,424,209 $2,424,209 100.0% 527 DIF Citywide -Storm Drain Facilities $485,941 $485,941 100.0% 620 Local Park (Quimby)$481,165 $50,000 10.4% 622 CFD 2015-2 Citywide Parks $243,794 $35,000 14.4% 623 CFD 2015-2 Citywide Trails $0 $0 DEV Developer Deposits $15,000 $15,000 100.0% Total $25,269,394 $15,510,771 Public Works / Engineering Department Proposed Capital Improvement Projects Fiscal Years 2020-2025 Holland Road/I-215 Overpass •Plans are at 95% •Currently on ROW Acquisition. •Obtaining Environmental Permits. •Construction Start:December 2021 Proposed Fund #Fund Name Total 2020-21 2021-22 2022-23 Future Years 105 Measure DD 1,239,277$ 671,614$ 567,663$ -$ -$ -$ 1,239,277$ 220 Measure A 754,413$ -$ -$ 754,413$ -$ -$ 754,413$ 310 TUMF 6,455,000$ -$ -$ 2,655,000$ 3,800,000$ -$ 6,455,000$ 320 Capital Projects 4,817,366$ 3,461,192$ 1,356,174$ -$ -$ -$ 4,817,366$ 415 Menifee Valley RBBD 8,250,086$ 6,081,672$ 973,386$ 922,990$ 272,038$ -$ 8,250,086$ 509 DIF 17 - Roads 2,055,744$ 2,055,744$ -$ -$ -$ -$ 2,055,744$ 510 DIF 17 - Signals 241,797$ 241,797$ -$ -$ -$ -$ 241,797$ 526 DIF Citywide - Circulation 1,723,638$ 1,723,638$ -$ -$ -$ -$ 1,723,638$ DIF Citywide - Storm Drain 727,738$ 241,797$ 485,941$ -$ -$ -$ 727,738$ Developer Deposits 1,058,408$ -$ -$ 1,058,408$ -$ -$ 1,058,408$ UNFUNDED 1,443,088$ -$ -$ -$ -$ 1,443,088$ 1,443,088$ 28,766,555$ 14,477,454$ 3,383,164$ 5,390,811$ 4,072,038$ 1,443,088$ 28,766,555$ Fund Source TOTALS PROJECT BUDGET DETAILS TOTALFuture Funding EstimatesApproved Funding to date Bradley Bridge Over Salt Creek •Plans are at 100% •Obtaining Environmental Permits and RCFCD Permit. •Construction Start:TBD Proposed Fund #Fund Name Total 2020-21 2021-22 2022-23 Future Years 105 Measure DD 723,872$ 473,872$ 250,000$ -$ -$ -$ 723,872$ 220 Measure A 809,912$ -$ -$ -$ 809,912$ -$ 809,912$ 320 Capital Projects -$ -$ -$ -$ -$ -$ -$ 509 DIF 17 - Roads 729,511$ 729,511$ -$ -$ -$ -$ 729,511$ 526 Citywide Circulation 4,669,946$ -$ 1,924,209$ 2,049,791$ 695,946$ -$ 4,669,946$ 527 Citywide Storm Drain 675,878$ -$ -$ 307,218$ 368,660$ -$ 675,878$ Other: RCFCD 2,000,000$ -$ -$ -$ 2,000,000$ -$ 2,000,000$ UNFUNDED 1,320,392$ -$ -$ -$ -$ 1,320,392$ 1,320,392$ 10,929,511$ 1,203,383$ 2,174,209$ 2,357,009$ 3,874,518$ 1,320,392$ 10,929,511$ PROJECT BUDGET DETAILS Fund Source Approved Funding to date Future Funding Estimates TOTAL TOTALS McCall Boulevard / I-215 Interchange Proposed Fund #Fund Name Total 2020-21 2021-22 2022-23 2023-24 2024-25 Future Years 105 Measure DD -$ -$ -$ -$ -$ -$ -$ -$ -$ 220 Measure A -$ -$ -$ -$ -$ -$ -$ -$ -$ 310 TUMF 16,930,000$ -$ 700,000$ 400,000$ 1,500,000$ 252,230$ -$ 14,077,770$ 16,930,000$ 320 Capital Projects 152,230$ 152,230$ -$ -$ -$ -$ -$ -$ 152,230$ 526 DIF Citywide - Circulation -$ -$ -$ -$ -$ -$ -$ -$ -$ Developer Deposits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ UNFUNDED 18,086,000$ -$ -$ -$ -$ -$ -$ 18,086,000$ 18,086,000$ 35,168,230$ 152,230$ 700,000$ 400,000$ 1,500,000$ 252,230$ -$ 32,163,770$ 35,168,230$ PROJECT BUDGET DETAILS Fund Source Approved Funding to date Future Funding Estimates TOTAL TOTALS •Preliminary Study Report (PSR) Completed •Environmental Phase to Start in FY 2020-21. •Construction Start:TBD Garbani Road/I-215 Interchange •Feasibility Study Report in progress, to be completed on August 2020. •Project Initiation and Project Study Report (PID/PSR) Phase to start in FY 2020-21. •Construction Start:TBD Proposed Fund #Fund Name Total 2020-21 Future Years 100 General Fund -$ -$ -$ -$ -$ 320 Capital Projects -$ 229,335$ -$ -$ 229,335$ 526 Scott Road RBBD -$ 646,869$ 19,107,425$ 19,754,294$ UNFUNDED -$ -$ 40,576,371$ 40,576,371$ -$ 229,335.00$ 646,869$ 59,683,796$ 60,560,000$ PROJECT BUDGET DETAILS Fund Source Approved Funding to date re Funding Estim TOTAL TOTALS Paloma Wash Pedestrian Bridge •Project will link Central Park to Shopping Center •Preliminary Study to be completed on October 2020. •Project Design Phase to start in January 2021. •Construction Start: TBD Proposed Fund #Fund Name Total 2020-21 2021-22 2022-23 Future Years 100 General Fund -$ -$ -$ -$ -$ -$ 105 Measure DD -$ -$ -$ -$ -$ -$ 526 DIF 17 - Public Facilities -$ 600,000$ -$ -$ -$ 600,000$ 512 DIF 17 - Trails 24,500$ 270,000$ -$ -$ -$ 294,500$ UNFUNDED -$ -$ -$ -$ 1,699,500$ 1,699,500$ -$ 24,500.00$ 870,000$ -$ -$ 1,699,500$ 2,594,000$ PROJECT BUDGET DETAILS Fund Source Approved Funding to date Future Funding Estimates TOTAL TOTALS Menifee Road and La Piedra Road Traffic Signal •Project Design Phase to start in July 2020. •Construction Start: March 2021 Proposed Fund #Fund Name Total 2020-21 510 DIF 17 - Signals -$ -$ -$ 526 DIF Citywide - Circulation 500,000$ -$ 500,000$ 500,000$ -$ 500,000$ Fund Source Approved Funding to date TOTALS Menifee Road and Scott Road Missing Sidewalk •Design Plans at 50% •Construction Start: September 2020 Proposed Fund #Fund Name Total 2020-21 105 Measure DD 327,447$ 60,710$ 266,737$ 220 Grants 183,263$ 183,263$ -$ 301 UNFUNDED -$ -$ -$ 510,710$ 243,973$ 266,737$ Fund Source Approved Funding to date TOTALS Adams Avenue Improvements –Phase 2 •Widen Street, Install sidewalks, ADA ramps, driveways, street signs, and striping •Design Plans at 90% •Construction Start:TBD Proposed Fund #Fund Name Total 2020-21 Future Years 105 Measure DD -$ -$ -$ -$ -$ 481 CDBG 547,212$ 327,739$ 219,473$ -$ 547,212$ UNFUNDED 339,483$ -$ -$ 339,483$ 339,483$ -$ -$ 886,695$ 327,739$ 219,473$ 339,483$ 886,695$ PROJECT BUDGET DETAILS Fund Source Approved Funding to date re Funding Estim TOTAL TOTALS Murrieta Road Resurfacing (McCall Blvd to Salt Creek •Design Plans at 95% •Construction Start:July 2020 Proposed Fund #Fund Name Total 2020-21 105 Measure DD 267,414$ 129,825$ 137,589$ 200 Gas Tax -$ -$ -$ 201 RMRA (SB1)1,100,000$ -$ 1,100,000$ 1,367,414$ 129,825$ 1,237,589$ Fund Source Approved Funding to date TOTALS Hillpointe Community Street Resurfacing •Design Start:August 2020 •Construction Start: March 2021 Proposed Fund #Fund Name Total 2020-21 105 Measure DD 519,568$ -$ 519,568$ 200 Gas Tax -$ 137,589$ 220 Measure A -$ 317,844$ 519,568$ -$ 975,001$ Fund Source Approved Funding to date TOTALS McCall Boulevard Resurfacing (Encanto Rd to Antelope Rd) •Design Start:August 2020 •Construction Start: March 2021 Proposed Fund #Fund Name Total 2020-21 105 Measure DD 317,843$ -$ 317,843$ 201 RMRA (SB1)606,886$ -$ 606,886$ 220 Measure A -$ -$ -$ 924,729$ -$ 924,729$ Fund Source Approved Funding to date TOTALS Fire Station #68 Interior Improvements •Design Start:August 2020 •Construction Start: March 2021 Proposed Fund #Fund Name Total 2020-21 521 DIF Citywide - Fire Fac.200,000$ -$ 200,000$ 200,000$ -$ 200,000$ Fund Source Approved Funding to date TOTALS New Quail Valley Fire Station #5 •Design Start:August 2020 •Construction Start: July 2022 Proposed Fund #Fund Name Total 2020-21 2021-22 2022-23 2023-24 2024-25 Future Years 105 Measure DD -$ -$ -$ -$ -$ -$ -$ -$ -$ 508 DIF 17 - Fire 3,096,760$ -$ 820,000$ -$ 2,276,760$ -$ -$ -$ 3,096,760$ 520 DIF Citywide - Public Use 344,002$ -$ -$ -$ 253,971$ 90,031$ -$ -$ 344,002$ 521 DIF Citywide - Fire Facilities -$ -$ -$ 865,499$ 372,184$ -$ -$ 1,237,683$ UNFUNDED -$ -$ -$ -$ -$ -$ 1,091,555$ 1,091,555$ -$ -$ 3,440,762$ -$ 820,000$ -$ 3,396,230$ 462,215$ -$ 1,091,555$ 5,770,000$ PROJECT BUDGET DETAILS Fund Source Approved Funding to date Future Funding Estimates TOTAL TOTALS New City Hall at Town Center Property •Update to Feasibility Study: August 2020 •Design Start: TBD •Construction Start: TBD Proposed Fund #Fund Name Total 2020-21 2021-22 Future Years 100 General Fund 250,000$ 250,000$ -$ -$ -$ 250,000$ 507 Measure DD -$ -$ -$ -$ -$ -$ 520 DIF 17 - Public Facilities 1,956,297$ -$ 200,000$ 1,756,297$ -$ 1,956,297$ DIF Citywide - Public Use -$ -$ -$ -$ -$ -$ UNFUNDED -$ -$ -$ 33,893,703$ 33,893,703$ -$ -$ 2,206,297$ 250,000$ 200,000$ 1,756,297$ 33,893,703$ 36,100,000$ PROJECT BUDGET DETAILS Fund Source Approved Funding to date Future Funding Estimates TOTAL TOTALS Community Services Department Proposed Capital Improvement Projects Fiscal Years 2020-2025 Lazy Creek Renovation •In progress –already fully funded in FY 2019/20 •Design phase nearly complete•Bid process for construction to take place in May 2020 •Groundbreaking scheduled for June 2020 with completion of project to take place by the end of 2020 CIP # CS020 Fund Fund Name Total 100 General Fund $100,000 511 DIF 17-Parks $400,000 Additionally Requested for FY 2020/21 507 DIF 17-Public Facilities $450,000 100 General Fund*$450,000 TOTAL PROJECT COST $1,400,000 Central Park Amphitheater Projected Project Costs •Once funding sources have been secured and project design finalized, the bidding process for construction will proceed and completion of the project is currently scheduled for Fall 2020 * Proposed funding through the newly negotiated Waste Management Contract franchise fees CIP # CS030 Evans Park Paloma Valley HS Craig Ave. •Phase 1: Conceptual Design –Completed •Phase 2: Environmental Impact Report –Winter 2020 •Phase 3: Construction of Pump Track –Spring 2021 •Phase 4: Construction of Recreation Facilities –TBD Future Recreation Facility 12.97 Acres Potential Site for Pump Track, Parking Lot, Walking Trail 8.79 Acres Fund Fund Name Total 511 DIF 17-Parks $250,000 Additionally Requested for FY 2020/21 512 DIF 17-Trails $250,000 522 DIF Citywide-Parks $100,000 TOTAL PROJECT COST $600,000 Projected Project Costs CIP # CS010 •Asphalt Pump Track can be used by cyclists of all ages, with all types of bikes, and requires less maintenance than dirt tracks •10,000 SQFT Pump Track on the corner of Evans Road and Craig Avenue •Adding over a half mile of additional walking trail to City’s current trails system •Gravel parking adjacent to park to be paved in later phase of the park Evans Park CIP # CS010 City of Temecula Pump Track (Opened November 2019) Trails Connectivity & Enhancements •Interconnected Theme •Additional Trail Amenities: •Signage •Rail Fencing •Pet Waste Stations •Drinking Fountains •Workout Equipment •Improved Public Access Fund Fund Name Total 512 DIF 17-Trails $260,000 Additionally Requested for FY 2020/21 512 DIF 17-Trails $170,000 TOTAL PROJECT COST $430,000 Projected Project Costs CIP # CS023 •MUSCO LED Lighting for Centennial Park •2 Baseball Fields and 1 Multi-purpose Field Sports Field Lighting CIP # CS015 Fund Fund Name Total 511 DIF 17-Parks $400,000 Additionally Requested for FY 2020/21 522 DIF Citywide-Parks $100,000 TOTAL PROJECT COST $500,000 Projected Project Costs •Resurfacing 3 basketball courts 1 at Audie Murphy Ranch 2 at Spirit •Resurfacing 2 Tennis Courts and repurposing 1 Tennis Court into a Futsal Court at Spirit Park Sports Court ResurfacingCIP # CS042 Fund Fund Name Total 511 DIF 17-Parks $38,000 Additionally Requested for FY 2020/21 490 AMR $100,000 TOTAL PROJECT COST $138,000 Projected Project Costs Project Name CIP #Approved Funding to Date FY 2020/2021 Additional Funding Requested Total Project Cost for FY 2020/21 Park Amenity Enhancements –Replace or Add Park Furnishings CS007 $75,000-620 Quimby $25,000-620 Quimby $23,000-522 DIF Citywide-Parks $65,000-490 AMR $188,000 Irrigation Upgrades & Control System CS009 $0 $25,000-620 Quimby $25,000 Park Lighting –Upgrade of Park Security Lighting in Walkways to LED CS014 $70,000-511 DIF 17-Parks $50,000-511 DIF 17-Parks $120,000 Additional CIP Projects Additional CIP Projects Project Name CIP #Approved Funding to Date FY 2020/2021 Additional Funding Requested Total Project Cost for FY 2020/21 Parking Lot Resurfacing & Trash Enclosures at Lazy Creek Park CS021 $100,000-507 DIF 17-Public Facilities $0 $100,000 IT Network Upgrades for Park Security CS022 $25,000-511 DIF 17-Parks $75,000-490 AMR $100,000 Permanent Park Restrooms at Lyle Marsh & Lazy Creek Parks CS032 $100,000-511 DIF 17-Parks $50,000-420 CSA 33 $50,000-490 AMR $0 $200,000 Shade Structures for Playgrounds and Sports Seating Areas CS047 $0 $285,000-490 AMR $35,000-622 CFD 2015-2 Citywide-Parks $320,000 SUMMARY The 5 year CIP is a dynamic City planning and fiscal management tool used to coordinate the location, timing and financing of the City’s Capital Projects over a multi-year period It is one of the most important responsibilities for our local agency The 5 year CIP is a working document and should be reviewed and updated annually to reflect changing community needs, priorities, and funding availabilities and opportunities The 5 year CIP has been reviewed for consistency with the City of Menifee General Plan. Questions?