2021-03-03 City Council Item No. 12.3 CIP No. 19-15 (CS030) Central Park Amphitheater Conceptual Design Presentation Regular MEETING - Additional Meeting Materials12.3 CIP No. 19-15 (CS030)
Central Park Amphitheater
Conceptual Design
March 3, 2021
Ontario Town Square Park
Construction Completed 2014
$7 Million Park Project
Cost Comparisons
Murrieta Town Square Park
Projected Completion 2020
$4.9 Million Project
Fontana Miller Park & Amphitheater
Construction Completed 2018
$4.2 Million Project
Superior Shelter Structure
Estimated Cost $280,000
Evolution of Central Park Amphitheater
IDS Design
IDS Estimated Cost $1.2 Million
TY Lin Estimated Cost $2.9 Million
TY Lin Geodesic
Estimated Cost $3.1 Million
Ad Hoc Committee Selected Design –TY Lin
Ad Hoc Committee Selected Design –TY Lin
Ad Hoc Committee Selected Design –TY Lin
Funding Gap and Recommendations
Base Construction $2,820,000
Contingency (15%)$423,000
Design (14%)$454,020
Environmental $73,590
Construction Management (5%)$162,150
TOTAL $3,932,760
Estimated Costs
Fund Account Amount
General Fund 100-4555-58079 $450,000
Capital Projects 320-4555-58079 $59,031
DIF 17 –Public Facilities 507-4555-58079 $450,000
DIF 17 –Parks 511-4555-58079 $400,000
Joint CFD Town Center Allocation Pending $558,000
Waste Management Reserve Allocation Pending $2,153,433
Total $3,932,760
Recommended Funding
With FY 20/21 Mid-Year Adjustment