2021-01-20 City Council Item 10.12 Presentation Notice of Completion CIP 20-06 and 20-07 Regular MEETING - Additional Meeting MaterialsConsent Item 10.12
Notice of Completion for Traffic Signals at
Menifee Rd/Holland Rd and Menifee
Rd/Camino Cristal CIP 20-06 and CIP 20-07
Carlos Geronimo
Principal Engineer
January 20, 2021
Project Location:
Strategic Plan Objective:
Safe and Attractive Community
Project Scope:
•16 Traffic Signal Poles (8 Ea.)
•(8) –15’ Mast Arms
•(1) –20’, 25’, 40’, 50’ Mast Arms
•(4) –45’ Mast Arms
•(8) –Pedestrian Crossing poles and signals
•(8) –ADA Pedestrian curb ramps
•Video detection system at 4 approaches
•Fiber optic lines with extra conduits for future
upgrades and expansions
Viewing East on Holland
Road at Menifee Road
Menifee Road at Holland Road:
Viewing North on Menifee
Road at Holland Road
Viewing North on Menifee Road at Camino Cristal
Menifee Road at Camino Cristal:
Viewing East on Camino Cristal at Menifee Road
Final Construction Costs
Approved Budget Final Cost
Construction Contract $1,023,988.00 $ 920,898.00
Labor Compliance $ 11,800.00 $ 2,137.50
Construction
Management/Inspections
$ 28,070.00 $ 26,669.32**
Total $1,063,858.00 $ 949,704.82
** Estimated final cost from SCE and RCTD based on agreement amounts.
Recommendations
1.Accept the Traffic Signal Improvements at Menifee Road and Holland
Road, Project No. CIP 20-06; and
2.Accept the Traffic Signal Improvements at Menifee Road and Camino
Cristal Project No. CIP 20-07; and
3.Authorize the City Clerk’s Office to file the Notice of Completion for the
Traffic Signals with the Riverside County Recorder’s Office.