2022-02-16 City Council Item No. 10.9 CannonDesign Agreement Amendment for Fire Station No. 5 Presentation Regular MEETING - Additional Meeting MaterialsConsent Item 10.9
CannonDesign Agreement
Amendment for Fire Station No. 5
Nick Fidler
Public Works Director
February 16, 2022
•Design plans, specification and estimates (PS&E) package at 90% completion.
•Agreement with CannonDesign set to expire February 28, 2022.
•Project scope modified
•Expansion of the building footprint.
•Addition of traffic signal at apparatus bay
•Design support services during bidding
•Design support services needed to ensure building is built in conformance with specifications.
•Services at post-construction phase needed to obtain as-builts and final project walk through for review of warranty items.
Discussion
Original Scope Change in Scope
Fire Station No. 5: Change in Scope
Fire Station No. 5: Change in Scope
•Increase building size by 2,500 sq. ft.
Task Fee
Project Scope Expansion $113,821
Construction Administration $223,149
Post-Construction Phase $12,743
Total $349,713
Discussion cont’d
•Additional services result
in cost of $349,713.
•Time extension through
June 30, 2023 needed to
meet construction and
post-construction phase.
Questions?Thank you