2021-09-15 City Council Item No. 10.15 NV5 Inc Amendment No. 5 Bradley Bridge Over Salt Creek Presentation Regular MEETING - Additional Meeting MaterialsConsent Item 10.15
NV5 Inc. Amendment No. 5,
Bradley Bridge Over Salt Creek
Nick Fidler
Public Works Director/City Engineer
September 15 ,2021
Project Location
•Bradley Road between Newport Road and Potomac Drive runs through the
Salt Creek Channel.Mild to moderate rains result in inclement flooding
which result in closures for public safety
Background
Original Agreement
•City Council approved agreement with NV5 Inc. for Design of Bradley Bridge Project $729,511
September 2015
Amendment 1
•time extension only approved
July 2018 Amendment 2
•time extension only approved
November 2019
Amendment 3
•Stormwater Pollution Prevention Plan (SWPPP) preparation approved $8,500
September 2020 Amendment 4
•time extension only approved
June 2021
•Riverside County completed Salt Creek Trail Project early
2021 which included signalized crossing at Bradley Road.
•Plans for Salt Creek Trail Project were not available at time
of Bradley Bridge design plan
•Revisions to Bradley Bridge plans needed to re-align Salt
Creek Trail to conform with proposed Bradley Bridge.
•Received scope and fee from NV5 to revise plans, assist
with processes/surveys, and include support services
during bidding and construction phase.
Discussion
Approve and authorize the City Manager to execute
Amendment No. 5 to the Professional Services Agreement with NV5, Inc., for Capital Improvement Project No. 13-04, extending the term of service through June 30, 2023 and
providing funding for additional services in the amount of $187,950.
Recommendation