24706 WINTER CIRCLE FIRE20-0803 VALOR WESTSteven Fox
Subject:
Location:
Start:
End:
Recurrence:
Organizer:
FIRE20-0803 TR36485-7 SPK FINAL LOT 3
24706 WINTER CIRCLE
Tue 1/19/2021 10:30 AM
Tue 1/19/2021 11 :00 AM
(none)
Steven Fox
Call Handling Mode 2: 2
Rep. Name: JUAN Co. Name: ----------------FSS
Phone#: 951-358-9783 Cell#: CrossSt: VALOR WEST ---------
HYDRANT SYSTEM PASS FAIL FIRE ALARM PASS
Thrust block pre-pour Rough-wire inspection
UnderQround rouQh Function test
Underground hydro Duct detectors/velocity
Flush 24 hr. battery test
Final Sprinkler monitorinQ
SPRINKLER U.G. Final
Thrust block pre-pour SPECIAL SUPPRESSION
Underground rough Door fan test
Underground hydro Abort test
Flush Mechanical shutdown
Final Detector test
FIRE SPRINKLER DeluQe/pre-action
Weld inspection Final
Overhead rough piping UST/AST TANK
Overhead hydro Installation
UG flush / OK to connect Removal
Main drain/Inspect. Test EmerQency shut off
High pile storage Primary piping
In-rack sprinklers Secondary pipinQ
Hose racks Dispensers & shear valves
X Final x:::::-Final
KITCHEN HOOD EXTINGUISHING MISC. INSPECTION
Detection system Spray booths
Function Test Hood/duct extinQuishinQ
Gas/Electrical shut-off High pile rack storage
Nozzle model/placement H.P. vents/access/corridors
Fire alarm connection Tract access/hydrant verification
Final Other:
SPRAY BOOTHS KNOX SYSTEM
Installation Building Knox box
Air flow test Gate access Knox box/padlock
Mechanical interlock BUILDING INSPECTIONS
Extinguishing system T/1 final
Fire alarm connection Shell final
Final Final for occupancy
Start Time: I I Finish Time: I � -
Start Time: I : I Finish Time: I :
23
FAIL
-
Iliana Gutierrez
Subject:
Location:
Start:
End:
Recurrence:
Organizer:
Call Handling Mode 2:
Rep. Name: JUAN
FIRE20-0803 TR36485-7 O/H ROUGH/HYDRO LOT 3
24706 WINTER CIRCLE
Wed 10/21/2020 12:00 PM
Wed 10/21/2020 12:30 PM
(none)
Menifee OFM
2
Co. Name: FSS ----------------
Phone#: 951-358-9783 Cell#: CrossSt: VALOR WEST---------
HYDRANT SYSTEM PASS FAIL FIRE ALARM PASS
Thrust block pre-pour Rough-wire inspection
Underground rough Function test
Underground hydro Duct detectors/velocitv
Flush 24 hr. battery test
Final Sprinkler monitoring
SPRINKLER U.G. Final
Thrust block pre-pour SPECIAL SUPPRESSION
Underground rough Door fan test
Underground hydro Abort test
Flush Mechanical shutdown
Final Detector test
FIRE SPRINKLER Deluge/pre-action
Weld inspection Final
X Overhead rough piping 'I-... UST/AST TANK
X Overhead hydro '-L Installation
UG flush / OK to connect I Removal
Main drain/Inspect. Test Emergency shut off
High pile storage Primary piping
In-rack sprinklers Secondary piping
Hose racks Dispensers & shear valves
Final Final
KITCHEN HOOD EXTINGUISHING MISC. INSPECTION
Detection system Spray booths
Function Test Hood/duct extinguishing
Gas/Electrical shut-off High pile rack storage
Nozzle model/placement H.P. vents/access/corridors
Fire alarm connection Tract access/hydrant verification
Final Other:
SPRAY BOOTHS KNOX SYSTEM
Installation Building Knox box
Air flow test Gate access Knox box/padlock
Mechanical interlock BUILDING INSPECTIONS
Extinguishing system T/1 final
Fire alarm connection Shell final
Final Final for occupancy
Start Time: I I Finish Time: I _--;;; -,,.,...-r--,...-r-,...
29
FAIL