28203 ZIPPER WAY FIRE21-1365 INDIGOJohnathan Baker
Subject: FIRE21-1365 TR29835 SPK FINAL LOT 44
Location: 28203 ZIPPER WAY
Start:
End:
Recurrence:
Meeting Status:
Organizer:
Call Handling Mode 2:
Rep. Name: RACHEL
Phone#: 909-906-5921
Thu 2/17/2022 11:00 AM
Thu 2/17/2022 11:30 AM
(none)
Meeting organizer
Johnathan Baker
2
Cell#:
Co. Name: KPS
CrossSt: INDIGO
HYDRANT SYSTEM
PASS
FAIL
FIRE ALARM
PASS
FAIL
Thrust block pre -pour
Rough -wire inspection
Under round rough
Function test
Underground hydro
Duct detectors/velocity
Flush
24 hr. battery test
Final
Sprinkler monitoring
SPRINKLER U.G.
Final
Thrust block pre -pour
SPECIAL SUPPRESSION
Underground rough
Boor fan test
Underground hydro
Abort test
Flush
NJ
Mechanical shutdown
Final
/
Detector test
FIRE SPRINKLER
\ /
Deluge/pre-action
Weld inspection
\ 1 /
Final
Overhead rough piping
/
UST/AST TANK
Overhead hydro
\ /
Installation
UG flush / OK to connect
` /
Removal
Main drain/Inspect. Test
/
/
Emergency shut off
High pile storage
Primary piping
In -rack sprinklers
Secondary piping
Hose racks
Dispensers & shear valves
Final
Final
KITCHEN HOOD EXTINGUISHING
MISC. INSPECTION
Detection system
/
Spray booths
Function Test
Hood/duct extinguishing
Gas/Electrical shut-off
High pile rack storage
Nozzle model/placement
H.P. vents/access/corridors
Fire alarm connection
Tract access/hydrant verification
Final
Other:
SPRAY BOOTHS
KNOX SYSTEM
Installation
Building Knox box
Air flow test
Gate access Knox box/padlock
Mechanical interlock
BUILDING INSPECTIONS
Extinguishing system
T/I final
Fire alarm connection
Shell final
25
Johnathan Baker
Subject:
FIRE21-1365 TR29835 O/H ROUGH/HYDRO LOT 44
Location:
28203 ZIPPER WAY
Start:
Tue 11/30/2021 10:00 AM
End:
Tue 11/30/2021 10:30 AM
Recurrence:
(none)
Organizer:
Johnathan Baker
Call Handling Mode 2:
2
Rep. Name: RACHEL
Phone#: 909-906-5921
Cell#:
Co. Name: KPS
CrossSt: INDIGO
HYDRANT SYSTEM
PASS
FAIL
FIRE ALARM
PASS
FAIL
Thrust block pre -pour
Rough -wire inspection
Underground rough
Function test
Under round hydro
Duct detectors/velocity
Flush
24 hr. battery test
Final
Sprinkler monitoring
SPRINKLER U.G.
Final
Thrust block pre -pour
SPECIAL SUPPRESSION
Underground rough
Door fan test
Underground hydro
Abort test
Flush
Mechanical shutdown
Final
Detector test
FIRE SPRINKLER
Deluge/pre-action
Weld inspection
Final
X
Overhead rough piping
UST/AST TANK
X
Overhead hydro
Installation
UG flush / OK to connect
Removal
Main drain/Inspect. Test
Emergency shut off
High pile storage
Primary piping
In -rack sprinklers
Secondary piping
Hose racks
Dispensers & shear valves
Final
Final
KITCHEN HOOD EXTINGUISHING
MISC. INSPECTION
Detections stem
Spray booths
Function Test
Hood/duct extinguishing
Gas/Electrical shut-off
High pile rack storage
Nozzle model/placement
H.P. vents/access/corridors
Fire alarm connection
Tract access/hydrant verification
Final
Other:
SPRAY BOOTHS
KNOX SYSTEM
Installation
Building Knox box
Air flow test
Gate access Knox box/padlock
Mechanical interlock
BUILDING INSPECTIONS
Extinguishing system
T/I final
Fire alarm connection
Shell final
Final
Final for occupancy
Start Time:
Finish Time:
Start Time:
I Finish Time:
11
Iliana Gutierrez
Subject: FIRE21-1365 TR29835-2 OH/ROUGH/HYDRO LOT 44
Location: 28203 ZIPPER WAY
Start: Tue 11/23/2021 8:00 AM
End: Tue 11/23/2021 8:30 AM
Recurrence: (none)
Meeting Status: Meeting organizer
Organizer: Johnathan Baker
Call Handling Mode 2: 2
Rep. Name: RACHEL
Phone#: 909-906-5921
Cell#:
Co. Name: KPS
CrossSt: INDIGO
HYDRANT SYSTEM
PASS
FAIL
FIRE ALARM
PASS
FAIL
Thrust block pre -pour
Rough -wire inspection
Underground rough
Function test
Underground hydro
Duct detectors/velocity
Flush
24 hr. battery test
Final
Sprinkler monitoring
SPRINKLER U.G.
Final
Thrust block pre -pour
SPECIAL SUPPRESSION
Underground rough
Door fan test
Underground hydro
Abort test
Flush
Mechanical shutdown
Final
Detector test
FIRE SPRINKLER
Deluge/pre-action
Weld inspection
Final
X
Overhead rough piping
UST/AST TANK
X
Overhead hydro
Installation
UG flush / OK to connect
Removal
Main drain/Inspect. Test
Emergency shut off
High pile storage
Primary piping
In -rack sprinklers
Seconds piping
Hose racks
Dispensers & shear valves
Final
Final
KITCHEN HOOD EXTINGUISHING
MISC. INSPECTION
Detection system
Spray booths
Function Test
Hood/duct extinguishing
Gas/Electrical shut-off
High pile rack storage
Nozzle model/placement
H.P. vents/access/corridors
Fire alarm connection
Tract access/hydrant verification
Final
Other:
SPRAY BOOTHS
KNOX SYSTEM
Installation
Building Knox box
Air flow test
Gate access Knox box/padlock
Mechanical interlock
BUILDING INSPECTIONS
Extinguishing system
T/I final
Fire alarm connection
Shell final
3 NOT r-"rDRlNSPotTioN