31595 DILL CT FIRE21-0153 PEPPERTREESteven Fox
Subject: FIRE21-0153 TR30142 SPK FINAL LOT 58
Location: 31595 DILL CT
Start: Wed 9/8/2021 9:30 AM
End: Wed 9/8/2021 10:00 AM
+r
Recurrence: (none) i C`
Organizer: Steven Fox
Call Handling Mode 2: 2
Rep. Name: RACHEL
Phone#: 909-906-5921
Cell#:
Co. Name: KPS
VIUJJJL. rCrrCRIRCC
HYDRANT SYSTEM
PASS
FAIL
FIRE ALARM
PASS
FAIL
Thrust block pre -Dour
Rough -wire inspection
Underground rough
Function test
Under round hydro
Duct detectors/velocity
Flush
24 hr. battery test
Final
Sprinkler monitoring
SPRINKLER U.G.
Final
Thrust block pre -pour
SPECIAL SUPPRESSION
Underground rough
Door fan test
Underground hydro
Abort test
Flush
Mechanical shutdown
Final
Detector test
FIRE SPRINKLER
Deluge/pre-action
Weld inspection
Final
Overhead rough piping
UST/AST TANK
Overhead hydro
Installation
UG flush / OK to connect
Removal
Main drain/Inspect. Test
Emergency shut off
High pile storage
Primary piping
In -rack sprinklers
Secondary piping
Hose racks
Dispensers & shear valves
X
Final
Final
KITCHEN HOOD EXTINGUISHING
MISC. INSPECTION
Detection system
Spray booths
Function Test
Hood/duct extinguishing
Gas/Electrical shut-off
High pile rack storage
Nozzle model/placement
H.P. vents/access/corridors
Fire alarm connection
Tract access/hydrant verification
Final
Other:
SPRAY BOOTHS
KNOX SYSTEM
Installation
Building Knox box
Air flow test
Gate access Knox box/padlock
Mechanical interlock
BUILDING INSPECTIONS
Extinguishing system
T/I final
Fire alarm connection
Shell final
Final
Final for occupancy
Start Time:
Finish Time:
Start Time:
Finish Time:
7
Steven Fox
Subject:
FIRE21-0153 TR30142 O/H ROUGH/HYDRO LOT 58
Location:
31595 DILL CT
Start:
Fri 7/9/2021 12:30 PM
End:
Fri 7/9/2021 1:00 PM
Recurrence:
(none)
Organizer:
Steven Fox
Call Handling Mode 2:
2
Rep. Name: RACHEL
Phone#: 909-906-5921
Cell#:
Co. Name: KIPS
%rl WOOL. rCrr CRI RCC
HYDRANT SYSTEM
PASS
FAIL
FIRE ALARM
PASS
FAIL
Thrust block pre -pour
Rough -wire inspection
Underground rough
Function test
Underground hydro
Duct detectors/velocity
Flush
24 hr. battery test
Final
Sprinkler monitoring
SPRINKLER U.G.
Final
Thrust block pre -pour
SPECIAL SUPPRESSION
Underground rough
Door fan test
Underground hydro
Abort test
Flush
Mechanical shutdown
Final
Detector test
FIRE SPRINKLER
Deluge/pre-action
Weld inspection
Final
X
Overhead rough piping
UST/AST TANK
X
Overhead hydro
Installation
UG flush / OK to connect
Removal
Main drain/Inspect. Test
Emergency shut off
High pile storage
Primary piping
In -rack sprinklers
Seconds piping
Hose racks
Dispensers & shear valves
Final
Final
KITCHEN HOOD EXTINGUISHING
MISC. INSPECTION
Detection system
Spray booths
Function Test
Hood/duct extinguishing
Gas/Electrical shut-off
High pile rack storage
Nozzle model/placement
H.P. vents/access/corridors
Fire alarm connection
Tract access/hydrant verification
Final
Other:
SPRAY BOOTHS
KNOX SYSTEM
Installation
Building Knox box
Air flow test
Gate access Knox box/padlock
Mechanical interlock
BUILDING INSPECTIONS
Extinguishing system
T/I final
Fire alarm connection
Shell final
Final
Final for occupancy
Start Time:
Finish Time:
Start Time:
Finish Time:
5