Loading...
2021/10/11 I.E. General Engineering, Inc. Anelope Road Raised Safety Median Improvements CIP 19-03 Additional StripingPage 1 of 2 DESCRIPTION OF CHANGES AND/OR EXTRA WORK: ITEM U/M QUANTITY % CHANGE UNIT PRICE TOTAL 18 LS 1 4,125.00$ $4,125.00 TOTAL ESTIMATED PRICE FOR THIS CHANGE ORDER:$4,125.00 JUSTIFICATION:Additional Striping was requested by the city due to safety concerns and alignment of existing striping south of La Piedra. Please see attached documentation for details. PROJECT NAME: PROJECT NO: CONTRACTOR: Antelope Road Raised Safety Median Improvements The Contractor is hereby directed to make the herein described changes from the plans and specifications and/or perform the following described work not included in the Plans and Specifications for this project. Work items shall include labor, materials, neccesary for the performance and completion of the additional work.equipment, traffic control, and incidentals 10/11/2021DATE: 05 additional Working Days will be granted to the Contractor due to pending additional striping Change Order for Median Noses. CIP 19-03 IE General Engineering, Inc. This document shall become an amendment to the Contract and all provisions of the Contract will apply hereto. This Change Order constitutes a complete and final resolution of all claims of the Contract for additional time or additional compensation related to or affected by work that is the subject of this Change Order. Quantities of items other than Lump Sum are not to exceed the amounts indicated. DESCRIPTION Additional Striping C:\Users\Ryan Moore\Dropbox\CIP 19-03 Menifee\10.00 Change Order\10.01 CCO-001\10.01.01 CCO -001 Revised\19-03_10.00 City of Menifee Change Order No. 01 DocuSign Envelope ID: 80F543EE-2972-4EE6-A66A-049D3C4E761A Page 2 of 2 CCO #Amount % Additional Time Date Approved 1 $4,125.00 5 Days 10/19/2021 Totals June 28, 2021 September 7, 2021 5 September 14, 2021 AUTHORIZATION BY CITY: Recommended for approval by: Date: ______________________________________________Date: __________ Tom Berg, PE Carlos E. Geronimo, PE Construction Manager Project Manager Approved by: Date: ______________________________________________Date: __________ Nicolas Fidler, PE Armando G. Villa Public Works Director/City Enigineer City Manager ACCEPTANCE BY CONTRACTOR: Accepted by: _____________________________________________________Date: ____________________________ Signature _____________________________________________________ Please print name and title Additional Striping Description 507,115.00$ Previous Change Order Amounts: Current Change Order Amount: Revised Contract Amount: Original Contract Amount: -$ 4,125.00$ 511,240.00$ ________________________________________ Revised Completion Date: ____________________________________________ CONTRACT VARIANCE SUMMARY We, the undersigned Contractor, have given careful consideration to the above described changes and/or extra work and hereby agree that said work is a supplement to the contract and all provisions will apply hereto. Date Started: Original Completion Date: Additional Time (Working Days) C:\Users\Ryan Moore\Dropbox\CIP 19-03 Menifee\10.00 Change Order\10.01 CCO-001\10.01.01 CCO -001 Revised\19-03_10.00 City of Menifee Change Order No. 01 10/21/21 DocuSign Envelope ID: 80F543EE-2972-4EE6-A66A-049D3C4E761A 11/15/2021 11/15/2021 11/16/2021