27073 MALTESE WAY FIRE21-0120 MEADOW RUNIn
(liana Gutierrez
Subject: FIRE21-0120 TR37576 O/H>ROU DRO LOT 6
Location: 27073 MALTESE WAY
Start: Tue 5/11/2021 9:00 AM
End: Tue 5/11/2021 9:30 AM ( I 1
Recurrence: (none)
Organizer: Menifee OFM
Call Handling Mode 2: 2
Rep. Name: DANIEL
Phone#: 951-703-5210
Cell#:
Co. Name: NP MECHANICAL
CrossSt: MEADOW RUN
HYDRANT SYSTEM
PASS
FAIL
FIRE ALARM
PASS
FAIL
Thrust block pre -pour
Rough -wire inspection
Underground rough
Function test
Under round hydro
Duct detectopKelocity
Flush
24 hr. bot&y test
Final
Sprinkier monitoring
SPRINKLER U.G.
nal
Thrust block pre -pour
SPECIAL SUPPRESSION
Underground rough
Door fan test
Underground hydro
Abort test
Flush
Mechanical shutdown
Final
Detector test
FIRE SPRINKLER
Deluge/pre-action
_
Weld inspection
Final
Overhead rou h piping
UST/AST TANK
Overhead hydro
Installation
UG flush / OK to connect
Removal
Main drain/Inspect- Te
Emergencv shut off
High pile storage X
Primary piping
In -rack sprinkl
Seconda piping
Hose racksZ
Dispensers & shear valves
Final ooe
Final
Kl HEN HOOD EXTINGUISHING
MISC. INSPECTION
ection system
Spray booths
Function Test
Hood/duct extinguishing
Gas/Electrical shut-off
High pile rack storage
Nozzle model/placement
H.P. vents/access/corridors
Fire alarm connection
Tract access/hydrant verification
Final
Other:
SPRAY BOOTHS
KNOX SYSTEM
Installation
Building Knox box
Air flow test
Gate access Knox box/padlock
Mechanical interlock
BUILDING INSPECTIONS
Extinguishing system
T/I final
Fire alarm connection
Shell final
Final
Final for occupanc
Start
Time:
Finish Time:
Start Time:
I
I Finish Time:
3
Steven Fox
Subject:
FIRE21-0120 TR37576 O/H ROUGH/HYDRO LOT 6
Location:
27073 MALTESE WAY
Start:
Tue 3/2/2021 10:30 AM
End:
Tue 3/2/2021 11:00 AM
Recurrence:
(none)
Organizer:
Menifee OFM
Call Handling Mode 2:
2
Rep. Name: DANIEL
Phone#: 951-703-5210
Cell#:
Co. Name: NP MECHANICAL
CrossSt: MEADOW RUN
HYDRANT SYSTEM
PASS
FAIL
FIRE ALARM
PASS
FAIL
Thrust block pre -pour
Rough -wire inspection
Under round rough
Function test
Underground hydro
Duct detectors/velocity
Flush
24 hr. batte test
Final
Sprinkler monitoring
SPRINKLER U.G.
Final
Thrust block pre -pour
SPECIAL SUPPRESSION
Underground rough
Door fan test
Underground hydro
Abort test
Flush
Mechanical shutdown
Final
Detector test
FIRE SPRINKLER
Deluge/pre-action
Weld inspection
Final
X
Overhead rough piping
>'"'
UST/AST TANK
X
Overhead hydro
Installation
UG flush / OK to connect
Removal
Main drain/Inspect. Test
Emergency shut off
High pile storage
Primary piping
In -rack sprinklers
Secondary _piping
Hose racks
Dispensers & shear valves
Final
Final
KITCHEN HOOD EXTINGUISHING
MISC. INSPECTION
Detection system
Spray booths
Function Test
Hood/duct extinguishing
Gas/Electrical shut-off
High pile rack storage
Nozzle model/placement
H.P. vents/access/corridors
Fire alarm connection
Tract access/hydrant verification
Final
Other:
SPRAY BOOTHS
KNOX SYSTEM
Installation
Building Knox box
Air flow test
Gate access Knox box/padlock
Mechanical interlock
BUILDING INSPECTIONS
Extinguishing system
T/I final
Fire alarm connection
Shell final
Final
Final for occupancy
Start Time:
Finish Time:
Start Time:
Finish Time:
1
Steven Fox
Subject:
FIRE21-0120 TR37576 O/H ROUGH/HYDRO LOT 6
Location:
27073 MALTESE WAY
Start:
Tue 3/2/2021 10:30 AM
End:
Tue 3/2/2021 11:00 AM
Recurrence:
(none)
Organizer:
Menifee OFM
Call Handling Mode 2:
2
Rep. Name: DANIEL
Phone#: 951-703-5210
Cell#:
Co. Name: NP MECHANICAL
VIUJJOL. IVICP1LJllVV r[UIV
HYDRANT SYSTEM
PASS
FAIL
FIRE ALARM
PASS
FAIL
Thrust block pre -pour
Rough -wire inspection
Underground rough
Function test
Underground hydro
Duct detectors/velocity
Flush
24 hr. battery test
Final
Sprinkler monitoring
SPRINKLER U.G.
Final
Thrust block pre -pour
SPECIAL SUPPRESSION
Underground rough
Door fan test
Underground hydro
Abort test
Flush
Mechanical shutdown
Final
Detector test
FIRE SPRINKLER
Deluge/pre-action
Weld inspection
Final
X
Overhead rough piping
Xw
UST/AST TANK
X
Overhead hydro
Installation
UG flush / OK to connect
Removal
Main drain/Inspect. Test
Emergency shut off
High pile storage
Primary piping
In -rack sprinklers
Secondary piping
Hose racks
Dispensers & shear valves
Final
Final
KITCHEN HOOD EXTINGUISHING
MISC. INSPECTION
Detection system
Spray booths
Function Test
Hood/duct extinguishing
Gas/Electrical shut-off
High pile rack storage
Nozzle model/placement
H.P. vents/access/corridors
Fire alarm connection
Tract access/hydrant verification
Final
Other:
SPRAY BOOTHS
KNOX SYSTEM
Installation
Building Knox box
Air flow test
Gate access Knox box/padlock
Mechanical interlock
BUILDING INSPECTIONS
Extinguishing system
T/I final
Fire alarm connection
Shell final
Final
Final for occupanc
Start
Time:
Finish Time:
Cf sr N f���tr. i •fir/c, y� ,,,
Start Time:
Finish Time:
5
Iliana Gutierrez
Subject:
FIRE21-0120 TR37576 O/H ROUGH/HYDRO LOT 6
Location:
27073 MALTESE WAY
Start:
Thu 2/11/2021 1:30 PM
End:
Thu 2/11/2021 2:00 PM
Recurrence:
(none)
Organizer:
Menifee OFM
Call Handling Mode 2:
2
Rep. Name: DANIEL
Phone#: 951-703-5210
Cell#:
Co. Name: NP MECHANICAL
VI VJJJ I. IVICP1L %.JVV FAUN
HYDRANT SYSTEM
PASS
FAIL
FIRE ALARM
PASS
FAIL
Thrust block pre -pour
Rough -wire inspection
Underground rough
Function test
Under round hydro
Duct detectors/velocity
Flush
24 hr. battery test
Final
Sprinkler monitoring
SPRINKLER U.G.
Final
Thrust block pre -pour
SPECIAL SUPPRESSION
Underground rough
Door fan test
Underground hydro
Abort test
Flush
Mechanical shutdown
Final
Detector test
FIRE SPRINKLER
Deluge/pre-action
Weld inspection
Final
X
Overhead rough piping
UST/AST TANK
X
Overhead hydro
Installation
UG flush / OK to connect
Removal
Main drain/Inspect. Test
Emergency shut off
High pile storage
Primary piping
In -rack sprinklers
Secondary piping
Hose racks
Dispensers & shear valves
Final
Final
KITCHEN HOOD EXTINGUISHING
MISC. INSPECTION
Detection system
Spray booths
Function Test
Hood/duct extinguishing
Gas/Electrical shut-off
High pile rack storage
Nozzle model/placement
H.P. vents/access/corridors
Fire alarm connection
Tract access/hydrant verification
Final
Other:
SPRAY BOOTHS
KNOX SYSTEM
Installation
Building Knox box
Air flow test
Gate access Knox box/padlock
Mechanical interlock
BUILDING INSPECTIONS
Extinguishing system
T/I final
Fire alarm connection
Shell final
Final
Final for occupancy
Start
Time:
Finish Time:
PW
Start Time:
Finish Time:
9
Iliana Gutierrez
Subject: FIRE21-0120 TR37576 O/H ROUGH/HYDRO LOT 6
Location: 27073 MALTESE WAY
Start: Tue 2/23/2021 12:00 PM
End: Tue 2/23/2021 12:30 PM
Recurrence: (none)
Organizer: Menifee OFM
Call Handling Mode 2: 2
Rep. Name: DANIEL
Phone#: 951-703-5210
Cell#:
Co. Name: NP MECHANICAL
CrossSt: MEADOW RUN
HYDRANT SYSTEM
PASS
FAIL
FIRE ALARM
PASS
FAIL
Thrust block pre -pour
Rough -wire inspection
Under round rough
Function test
Underground hydro
Duct detectors/velocity
Flush
24 hr. battery test
Final
Sprinkler monitoring
SPRINKLER U.G.
Final
Thrust block pre -pour
SPECIAL SUPPRESSION
Underground rough
Door fan test
Underground hydro
Abort test
Flush
Mechanical shutdown
Final
Detector test
FIRE SPRINKLER
Deluge/pre-action
Weld inspection
Final
X
Overhead rough piping
I UST/AST TANK
X
Overhead hydro
Installation
UG flush / OK to connect
Removal
Main drain/Inspect. Test
Emergency shut off
High pile storage
Primary piping
In -rack sprinklers
Secondary piping
Hose racks
Dispensers & shear valves
Final
Final
KITCHEN HOOD EXTINGUISHING
MISC. INSPECTION
Detection system
Spray booths
Function Test
Hood/duct extinguishing
Gas/Electrical shut-off
High pile rack storage
Nozzle model/placement
H.P. vents/access/corridors
Fire alarm connection
Tract access/hydrant verification
Final
Other:
SPRAY BOOTHS
KNOX SYSTEM
Installation
Building Knox box
Air flow test
Gate access Knox box/padlock
Mechanical interlock
BUILDING INSPECTIONS
Extinguishing system
T/I final
Fire alarm connection
Shell final
Final
Final for occupant
Start Time:
Finish Time:
.144 /��
Start Time:
Finish Time:
15 V