29812 OLYMPIC DR FIRE20-0251 CHELSEASteven Fox
Subject:
FIRE20-0251 TR34406-6 SPK FINAL LOT 21
Location:
29812 OLYMPIC DRIVE
Start:
Wed 6/17/2020 9:00 AM
End:
Wed 6/17/2020 9:30 AM
Recurrence:
(none)
Organizer:
Steven Fox
Rep. Name: HECTOR
Phone#: 951-847-2908
Cell#:
Co. Name: FSS
CrossSt: CHELSEA
HYDRANT SYSTEM
PASS
FAIL
FIRE ALARM
PASS
FAIL
Thrust block pre -pour
Rough -wire inspection
Underground rough
Function test
Underground hydro
Duct detectors/velocity
Flush
24 hr. battery test
Final
Sprinkler monitoring
SPRINKLER U.G.
Final
Thrust block pre -pour
SPECIAL SUPPRESSION
Underground rough
Door fan test
Underground hydro
Abort test
Flush
Mechanical shutdown
Final
Detector test
FIRE SPRINKLER
Deluge/pre-action
Weld inspection
Final
Overhead rough piping
UST/AST TANK
Overhead hydro
Installation
UG flush / OK to connect
Removal
Main drain/Inspect. Test
Emergency shut off
High pile storage
Primary piping
In -rack sprinklers
Secondary piping
Hose racks
Dispensers & shear valves
X
Final
?{
Final
KITCHEN HOOD EXTINGUISHING
MISC. INSPECTION
Detection system
Spray booths
Function Test
Hood/duct extinguishing
Gas/Electrical shut-off
High pile rack storage
Nozzle model/placement
H.P. vents/access/corridors
Fire alarm connection
Tract access/hydrant verification
Final
Other:
SPRAY BOOTHS
KNOX SYSTEM
Installation
Building Knox box
Air flow test
Gate access Knox box/padlock
Mechanical interlock
BUILDING INSPECTIONS
Extinguishing system
T/I final
Fire alarm connection
Shell final
Final
Final for occupancy
Start
Time: Finish Time:
Start Time: Finish Time:
15
Bernice Rivera
Subject: FIRE20-0251 TR34406-6 O/H ROUGH/HYDRO LOT 21
Location: 29812 OLYMPIC DR
Start: Tue 3/31/2020 2:00 PM
End: Tue 3/31/2020 2:30 PM
Recurrence: (none)
Rep. Name: HECTOR-CARLOS Co. Name:
Phone#: 951 847-2908 Cell#:
FSS
CrossSt: CHELSEA
HYDRANT SYSTEM
PASS
FAIL
FIRE ALARM
PASS
FAIL
Thrust block pre -pour
Rough -wire inspection
Underground rough
Function test
Underground hydro
Duct detectors/velocity
Flush
24 hr. battery test
Final
Sprinkler monitoring
SPRINKLER U.G.
Final
Thrust block pre -pour
SPECIAL SUPPRESSION
Underground rough
Door fan test
Underground hydro
Abort test
Flush
Mechanical shutdown
Final
Detector test
FIRE SPRINKLER
Deluge/pre-action
Weld inspection
Final
X
Overhead rough piping
UST/AST TANK
X
Overhead hydro
r
Installation
UG flush / OK to connect
Removal
Main drain/Inspect. Test
Emergency shut off
High pile storage
Primary piping
In -rack sprinklers
Secondary piping
Hose racks
Dispensers & shear valves
Final
Final
KITCHEN HOOD EXTINGUISHING
MISC. INSPECTION
Detection system
Spray booths
Function Test
Hood/duct extinguishing
Gas/Electrical shut-off
High pile rack storage
Nozzle model/placement
H.P. vents/access/corridors
Fire alarm connection
Tract access/hydrant verification
Final
Other:
SPRAY BOOTHS
KNOX SYSTEM
Installation
Building Knox box
Air flow test
Gate access Knox box/padlock
Mechanical interlock
BUILDING INSPECTIONS
Extinguishing system
T/I final
Fire alarm connection
Shell final
Final
Final for occupancy
Start Time:
Finish Time:
Start Time:
Finish Time: