27369 TARANTO CT FIRE20-0608 SALERNO(liana Gutierrez
Subject: ZOOM FIRE20-0608 TR29835 SPK FINAL LOT 51
Location: 27369 TARANTO CT
Start:
End:
Recurrence:
Organizer:
Call Handling Mode 2:
Rep. Name: JUAN
Phone#: 951-858-7939
Tue 9/29/2020 2:00 PM
Tue 9/29/2020 2:30 PM
(none)
Menifee OFM
2
Cell#:
Co. Name: NP MECHANICAL
CrossSt: SALERNO
HYDRANT SYSTEM
PASS
FAIL
FIRE ALARM
PASS
FAIL
Thrust block pre -pour
Rough -wire inspection
Underground rough
Function test
Underground hydro
Duct detectors/veloc'
Flush
24 hr. battery tes
Final
Sprinkler mojjiffring
SPRINKLER U.G.
Final
Thrust block pre -pour
PPECIAL SUPPRESSION
Underground rough
D fan test
Underground hydro
0 ort test
Flush
Mechanical shutdown
Final
Detector test
FIRE SPRINKLER
Deluge/pre-action
Weld inspection
Final
Overhead rough pi in
UST/AST TANK
Overhead hydro
Installation
UG flush / OK to connect
Removal
Main drain/Inspect. Test
Emergency shut off
High pile storage
Prima piping
In -rack sprinklers
Secondaa piping
Hose racks
Dispensers & shear valves
X
Final
Final
KITCHEN HOOD EXTINGUISHING
MISC. INSPECTION
Detections stem
Spray booths
Function Test
Hood/duct extinguishing
Gas/Electrical s -off
High pile rack storage
Nozzle model acement
H.P. vents/access/corridors
Fire alarm c6Wnection
Tract access/hydrant verification
Final
Other:
SPRAY BOOTHS
KNOX SYSTEM
Installation
Building Knox box
Air flow test
Gate access Knox box/padlock
Mechanical interlock
BUILDING INSPECTIONS
Extinguishing system
T/I final
Fire alarm connection
Shell final
r—TFinal
Final for occupancy
Start Time: I I Finish Time:
15
Steven Fox
Subject: FIRE20-0608 TR29835-1 O/H ROUGH/HYDRO LOT 51
Location: 27369 TARANTO COURT
Start: Thu 7/2/2020 12:30 PM
End: Thu 7/2/2020 1:00 PM
Recurrence: (none)
Organizer: Steven Fox
Rep. Name: DANIEL Co. Name
Phone#: 951-703-5210 Cell#:
NP MECHANICAL
CrossSt: SALERNO
HYDRANT SYSTEM
PASS
FAIL
FIRE ALARM
PASS
FAIL
Thrust block pre -pour
Rough -wire inspection
Underground rough
Function test
Underground hydro
Duct detectors/velocity
Flush
24 hr. battery test
Final
Sprinkler monitoring
SPRINKLER U.G.
Final
Thrust block pre -pour
SPECIAL SUPPRESSION
Underground rough
Door fan test
Underground hydro
Abort test
Flush
Mechanical shutdown
Final
Detector test
FIRE SPRINKLER
Deluge/pre-action
Weld inspection
Final
X
Overhead rough piping
UST/AST TANK
X
Overhead hydro
Installation
UG flush / OK to connect
Removal
Main drain/Inspect. Test
Emergency shut off
High pile storage
Primary piping
In -rack sprinklers
Secondary piping
Hose racks
Dispensers & shear valves
Final
Final
KITCHEN HOOD EXTINGUISHING
MISC. INSPECTION
Detection system
Spray booths
Function Test
Hood/duct extinguishing
Gas/Electrical shut-off
High pile rack storage
Nozzle model/placement
H.P. vents/access/corridors
Fire alarm connection
Tract access/hydrant verification
Final
Other:
SPRAY BOOTHS
KNOX SYSTEM
Installation
Building Knox box
Air flow test
Gate access Knox box/padlock
Mechanical interlock
BUILDING INSPECTIONS
Extinguishing system
T/I final
Fire alarm connection
Shell final
Final
Final for occupancy
Start Time:
Finish Time:
Start Time: