26476 KEEL CT PMT17-00739 PEPPERTREESonya Rivera-Bu
N10 ,
�kD-Mtz%\,— az8 c�
Subject: 17-MENI-00739 TR30142-2 LOT 138 SPK FINAL
Location:
Start:
End:
Recurrence:
Rep. Name: DENA
26476 KEEL CT
Thu 4/12/2018 1:00 PM
Thu 4/12/2018 1:30 PM
(none)
Phone#: 909-906-5921 Cel I#:
Co. Name: KPS
CrossSt: PEPPERTREE
HYDRANT SYSTEM
PASS
FAIL
FIRE ALARM
PASS
FAIL
Thrust block pre -pour
Rough -wire inspection
Underground rough
Function test
Underground hydro
Duct detectors/velocity
Flush
24 hr. battery test
Final
Sprinkler monitoring
SPRINKLER U.G.
Final
Thrust block pre -pour
SPECIAL SUPPRESSION
Underground rough
Door fan test
Underground hydro
Abort test
Flush
Mechanical shutdown
Final
Detector tee.,
FIRE SPRINKLER
De1ugo'pre-action
Weld inspection
-Final
Overhead rough piping
UST/AST TANK
Overhead hydro
Installation
UG flush / OK to connect
Removal
Main drain/Inspect. Test
Emergency shut off
High pile storage
Primary piping
In -rack sprinklers
Secondary piping
Hose racks
Dispensers & shear valves
X Final
Final
KITCHEN HOOD EXTINGUISHING
MISC. INSPECTION
Detection system
Spray booths
Function Test
Hood/duct extinguishing
Gas/Electrical shut-off
High pile rack storage
Nozzle model/placement
H.P. vents/access/corridors
Fire alarm connection
Tract access/hydrant verification
Final
Other:
SPRAY BOOTHS
KNOX SYSTEM
Installation
Building Knox box
Air flow test
Gate access Knox box/padlock
Mechanical interlock
BUILDING INSPECTIONS
Extinguishing system
T/I final
Fire alarm connection
Shell final
Final
Final for occupancy
Start Time:
Finish Time:
Start Time:
Finish Time:
Sonva Rivera-Bu
Subject:
17-MENI-00739 TR30142-2 LOT 138 SPK FINAL
Location:
26476 KEEL CT
Start:
Thu 4/5/2018 8:30 AM
End:
Thu 4/5/2018 9:00 AM
Recurrence:
(none)
Organizer:
Paul Villalobos
Rep. Name: DENA
Phone#:
Cell#:
Co. Name: KPS
CrossSt: PEPPERTREE
HYDRANT SYSTEM
PASS
AIL"
FIRE ALARM
PASS
FAIL
Thrust block pre -pour
Rough -wire inspection
Underground rough
Function test
Underground hydro
Duct detectors/velocity
Flush
24 hr. battery test
Final
Sprinkler monitoring
SPRINKLER U.G.
Final
Thrust block pre -pour
SPECIAL SUPPRESSION
Underground rough
Door fan test
Underground hydro
Abort test
Flush
Mechanical shutdown
Final
Detector test
FIRE SPRINKLER
Deluge/pre-action
Weld inspection
Final
Overhead rough piping
UST/AST TANK
Y�1G
Overhead hydro
Installation
UG flush / OK to connect
Removal
Main drain/Inspect. Test
Emergency shut off
High pile storage
Primary piping
In -rack sprinklers
Secondary piping
Hose racks
Dispensers & shear valves
'♦,
Final
Final
KITCHEN HOOD EXTINGUISHING
MISC. INSPECTION
Detection system
Spray booths
Function Test
Hood/duct extinguishing
Gas/Electrical shut-off
High pile rack storage
Nozzle model/placement
H.P. vents/access/corridors
Fire alarm connection
Tract access/hydrant verification
Final
Other:
SPRAY BOOTHS
KNOX SYSTEM
Installation
Building Knox box
Air flow test
Gate access Knox box/padlock
Mechanical interlock
BUILDING INSPECTIONS
Extinguishing system
T/I final
Fire alarm connection
Shell final
Final
Final for occupancy
Start Time:
Finish Time:
Start Time:
Finish Time:
Sonya Rivera-Bu
Subject: 17-MENI-00739 LOT 138 TR30142-2 O/H ROUGH/HYDRO RE -INSPECTION
Location: 26476 KEEL CT
Start: Fri 2/23/2018 1:30 PM
End: Fri 2/23/2018 2:00 PM
Recurrence: (none)
Organizer: Paul Villalobos
Rep. Name: DENA
Phone#: 909-906-5921
Cell#:
Co. Name: KPS
U[UbbOL. I'CI I CK I rSCC
HYDRANT SYSTEM
PASS
FAIL
FIRE ALARM
PASS
FAIL
Thrust block pre -pour
Rough -wire inspection
Underground rough
Function test
Underground hydro
Duct detectors/velocity
Flush
24 hr. battery test
Final
Sprinkler monitoring
SPRINKLER U.G.
Final
Thrust block pre -pour
SPECIAL SUPPRESSION
Underground rough
Door fan test
Underground hydro
Abort test
Flush
Mechanical shutdown
Final
Detector test
FIRE SPRINKLER
Deluge/pre-action
Weld inspection
Final
X
Overhead rough piping
UST/AST TANK
X
Overhead hydro
Installation
UG flush / OK to connect
Removal
Main drain/Inspect. Test
Emergency shut off
High pile storage
Primary piping
In -rack sprinklers
Secondary piping
Hose racks
Dispensers & shear valves
Final
Final
KITCHEN HOOD EXTINGUISHING
MISC. INSPECTION
Detection system
Spray booths
Function Test
Hood/duct extinguishing
Gas/Electrical shut-off
High pile rack storage
Nozzle model/placement
H.P. vents/access/corridors
Fire alarm connection
Tract access/hydrant verification
Final
Other:
SPRAY BOOTHS
KNOX SYSTEM
Installation
Building Knox box
Air flow test
Gate access Knox box/padlock
Mechanical interlock
BUILDING INSPECTIONS
Extinguishing system
T/I final
Fire alarm connection
Shell final
Final
Final for occupancy
Start Time: Finish Time:
Start Time: Finish Time:
1
Sonya Rivera-Bu
Subject: 17-MENI-00739 LOT 138 TR 30142-2 O/H ROUGH/HYDRO
Location: 26476 KEEL CT
Start: Thu 2/22/2018 9:30 AM
End: Thu 2/22/2018 10:00 AM
Recurrence: (none)
Rep. Name: DENA Co. Name:
Phone#: 909-906-5921 Cell#:
KPS
CrossSt: PEPPERTREE
HYDRANT SYSTEM
PASS
FAIL
FIRE ALARM
PASS
FAIL
Thrust block pre -pour
Rough -wire inspection
Underground rough
Function test
Underground hydro
Duct detectors/velocity
Flush
24 hr. battery test
Final
Sprinkler monitoring
SPRINKLER U.G.
Final
Thrust block pre -pour
SPECIAL SUPPRESSION
Underground rough
Door fan test
Underground hydro
Abort test
Flush
Mechanical shutdown
Final
Detector test
FIRE SPRINKLER
Deluge/pre-action
Weld inspection
Final
X Overhead rough piping
UST/AST TANK
X Overhead hydro
Installation
UG flush / OK to connect
1
Removal
Main drain/Inspect. Test
Emergency shut off
High pile storage
Primary piping
In -rack sprinklers
Secondary piping
Hose racks
Dispensers & shear valves
Final
Final
KITCHEN HOOD EXTINGUISHING
MISC. INSPECTION
Detection system
Spray booths
Function Test
Hood/duct extinguishing
Gas/Electrical shut-off
High pile rack storage
Nozzle model/placement
H.P. vents/access/corridors
Fire alarm connection
Tract access/hydrant verification
Final
Other:
SPRAY BOOTHS
KNOX SYSTEM
Installation
Building Knox box
Air flow test
Gate access Knox box/padlock
Mechanical interlock
BUILDING INSPECTIONS
Extinguishing system
T/I final
Fire alarm connection
Shell final
Final
Final for occupancy
Start Time:
Finish Time:
Start Time:
Finish Time:
I
1
Riverside County Fire Department V"tathe Fire Marshal
Riverside Office: Palm Desert Office:
2300 Market Street, Ste. 150 77-933 Las Montanas Rd., Ste 201
Riverside, CA 92501� Palm Desert CA 92211
Phone: (951) 955-4777 - Fax: (951) 955-4886 Phone: (760.] 863-8886 - Fax: 760 863-7072
PLAN REVIEW FORM CRYOF91 skeenly
Building Dept.
® New ❑ Re -Submittal # ❑ As-builts
]AN t
FD Permit # 17-MENI-00739
County/City Permit# Re Ceived
PROJECT INFORMATION
Project Name: PEPPERTREE @ HIDDEN HILLS I have read and understand that Fire Dept. fees are
Deposit Based Fees and there may be additional
Address: 26476 Keel Court Lot 138 Plan 5 (240.2544) money due prior to or after pro'1ect final
City & Zip:
Sign:
Print:
APPLICANT INFORMATION
Company Name: KPS FIRE SPRINKLERS Applicant Name. DENA BROCATO
Address: 760 S ROCHESTER SUITE B Phone: 909-906-5921
City/ Zip: ONTARIO CA 91761 Email: DBROCATO@KPSFIRE.COM
BILLING INFORMATION: ❑ Same as applicant
Company Name: SAME Applicant Name:
Address: Phone:
City/ Zip: Email:
The person listed on "Billing Information" will receive ALL billing, correspondence and refunds for any work billed to
this permit. Any changes in billing information must be made in writing to our office.
Plan Review Type (Check appropriate items)
Menifee, CA 92584
❑Commercial ❑Residential ❑Other
Construction: ❑Building ❑Tenant Improvement (New/Existing)
❑Cell Site ❑High Pile/Racks ❑HFA
Systems: ®Sprinkler DTI Sprinkler ❑Sprinkler Monitoring ❑Fire Alarm ❑Hood & Duct Suppression
❑Other Suppression ❑Spray Booth DUG Water
Other:
Storage Tanks: ❑Dispensers Only ❑Above Ground # ❑Underground #
OFFICE USE ONLY
Fee Paid:
Reviewed by: a� G1
Called for Pick -Up
Date Paid: o lS
1 , l
Date: By:
PC Review Date:
Picked -Up
Check#:
Approved ❑ Denied
Date: By:
Received By:
Plans Stamped: 4es ❑No
Shipped By / Method
Letter Attached: es ❑No
Receipt#(OCR)
Job Card Included: ❑Yel
❑DBF
❑DBF
DBF
Norm I — Kevised b/ 14/2017 visit us at www.rvctire.org