26086 REDOAK ST FIRE20-0567 CYPRESS(liana Gutierrez
Subject: FIRE20-0567 TR30142 SPK FINAL LOT 154
Location: 26086 REDOAK ST
Start:
End:
Recurrence:
Organizer:
Call Handling Mode 2:
Rep. Name: DENA
Phone#: 909-906-5921
Tue 9/15/2020 8:00 AM
Tue 9/15/2020 8:30 AM
(none)
Menifee OFM
2
Cell#:
Co. Name: KPS
LA U65iOL. 1. T rMr-JJ
HYDRANT SYSTEM
PASS
FAIL
FIRE ALARM
PASS
FAIL
Thrust block pre -pour
Rough -wire inspection
Underground rough
Function Zest
Underground hydro
Duct detectors/velocity
Flush
24 hr. battery test
Final
Sprinkler monitoring
SPRINKLER U.G.
11. inal
Thrust block pre -pour
SPECIAL SUPPRESSION
Underground rough
Door fan test
Underground hydro
Abort test
Flush
Mechanical shutdown
Final
Detector test
FIRE SPRINKLER
Deluge/pre-action
Weld inspection
Final
Overhead rough piping
UST/AST TANK
Overhead hydro
Installation
UG flush / OK to connect
Removal
Main drain/Inspect. Test
Emergency shut off
High pile storage
V
Primary piping
In -rack sprinklers 9L
Secondary piping
Hose racks
Dispensers & shear valves
Final
X
Final
KITCHEN HOOD EXTINGUISHING
MISC. INSPECTION
Detection system
Spray booths
Function Test ,:
Hood/duct extinguishing
Gas/Electrical` shut-off
High pile rack storage
Nozzle mo061/placement
H.P. vents/access/corridors
Fire alarm connection
Tract access/hydrant verification
Final
Other:
SPRAY BOOTHS
KNOX SYSTEM
Installation
Building Knox box
Air flow test
Gate access Knox box/padlock
Mechanical interlock
BUILDING INSPECTIONS
Extinguishing system
T/I final
Fire alarm connection
Shell final
Final
Final for occupancy
Start Time: Finish Time:
3
(liana Gutierrez
Subject: FIRE20-0567 TR30142 O/H ROUGH/HYDRO LOT 154
Location: 26086 REDOAK ST
Start: Wed 7/15/2020 8:30 AM
End: Wed 7/15/2020 9:00 AM
Recurrence: (none)
Organizer: Menifee OFM
Rep. Name: DENA Co. Name: KPS
Phone#: 909-906-5921 Cell#:
CrossSt: CYPRESS
HYDRANT SYSTEM
PASS
FAIL
FIRE ALARM
PASS
FAIL
Thrust block pre -pour
Rough -wire inspection
Underground rough
Function test
Underground hydro
Duct detectors/velocity
Flush
24 hr. battery test
Final
Sprinkler monitoring
SPRINKLER U.G.
Final
Thrust block pre -pour
SPECIAL SUPPRESSION
Under round rough
Door fan test
Underground hydro
Abort test
Flush
Mechanical shutdown
Final
Detector test
FIRE SPRINKLER
Deluge/pre-action
Weld inspection
Final
X
Overhead rough piping
UST/AST TANK
X
Overhead hydro
Installation
UG flush / OK to connect
Removal
Main drain/Inspect. Test
Emergency shut off
High pile storage
Primary piping
In -rack sprinklers
Secondary piping
Hose racks
Dispensers & shear valves
Final
Final
KITCHEN HOOD EXTINGUISHING
MISC. INSPECTION
Detection system
Spray booths
Function Test
Hood/duct extinguishing
Gas/Electrical shut-off
High pile rack storage
Nozzle model/placement
H.P. vents/access/corridors
Fire alarm connection
Tract access/hydrant verification
Final
Other:
SPRAY BOOTHS
KNOX SYSTEM
Installation
Building Knox box
Air flow test
Gate access Knox box/padlock
Mechanical interlock
BUILDING INSPECTIONS
Extinguishing system
T/I final
Fire alarm connection
Shell final
Final
Final for occupancy
Start Time:
Finish Time:
Start Time:
Finish Time: