24464 RESERVE CT FIRE20-1209 TRIBUTE IIIliana Gutierrez
Subject:
FIRE20-1209 TR36485 SPK FINAL LOT 49
Location:
24464 RESERVE CT
Start:
Tue 2/23/2021 2:30 PM
End:
Tue 2/23/2021 3:00 PM
Recurrence:
(none)
Organizer:
Menifee OFM
Call Handling Mode 2:
2
Rep. Name: HECTOR
Co. Name: FSS
Phone#: 951-847-2908
Cell#: CrossSt: TRIBUTE II
HYDRANT SYSTEM
PASS
FAIL
FIRE ALARM
PASS
FAIL
Thrust block pre -pour
Rough -wire inspection
Under round rough
Function test
Underground hydro
Duct detectors/velocity
Flush
24 hr. battery test
Final
Sprinkler mcrnitorin
SPRINKLER U.G.
Final
Thrust block pre -pour
SPECIAL SUPPRESSION
Underground rough
Door fan test
Underground hydro
Abort test
Flush
Mechanical shutdown
Final
Detector test
FIRE SPRINKLER
Deluge/pre-action
Weld inspection
Final
Overhead rough piping
NN/
UST/AST TANK
Overhead hydro
Installation
UG flush / OK to connect
Removal
Main drain/inspect. Test
Emergency shut off
High pile storage
Primary piping
In-racksprinklers-,
Secondary piping
Hose racks
Dis ensers & shear valves
X
Final
Final
KIT EN HOOD EXTINGUISHING
MISC. INSPECTION
2efection system
Spray booths
Function Test
Hood/duct extinguishing
Gas/Electrical shut-off
High pile rack storage
Nozzle model/placement
H.P. vents/access/corridors
Fire alarm connection
Tract access/hydrant verification
Final
Other:
SPRAY BOOTHS
KNOX SYSTEM
Installation
Building Knox box
Air flow test
Gate access Knox box/padlock
Mechanical interlock
BUILDING INSPECTIONS
Extinguishing system
T/I final
Fire alarm connection
Shell final
Final
Final for occupancy
Start
Time:
Finish Time:
Start Time:
Finish Time:
1
Iliana Gutierrez
Subject: FIRE20-1209 TR36485-5 O/H ROUGH/HYDRO LOT 49
Location: 24464 RESERVE CT
Start:
End:
Recurrence:
Organizer:
Call Handling Mode 2:
Thu 12/10/2020 11:00 AM
Thu 12/10/2020 11:30 AM
(none)
Menifee OFM
2
Rep. Name: JUAN
Phone#: 951-358-9783 Cell#:
Co. Name: FSS
CrossSt: TRIBUTE II
HYDRANT SYSTEM
PASS
FAIL
FIRE ALARM
PASS
FAIL
Thrust block pre -pour
Rough -wire inspection
Underground rough
Function test
Underground hydro
Duct detectors/velocity
Flush
24 hr. battery test
Final
Sprinkler monitoring
SPRINKLER U.G.
Final
Thrust block pre -pour
SPECIAL SUPPRESSION
Underground rough
Door fan test
Underground hydro
Abort test
Flush
Mechanical shutdown
Final
Detector test
FIRE SPRINKLER
Deluge/pre-action
Weld inspection
Final
X
Overhead rough piping
UST/AST TANK
X
Overhead hydro
Installation
UG flush / OK to connect
Removal
Main drain/Inspect. Test
Emergency shut off
High pile storage
Primary piping
In -rack sprinklers
Secondary piping
Hose racks
Dispensers & shear valves
Final
Final
KITCHEN HOOD EXTINGUISHING
MISC. INSPECTION
Detection system
Spray booths
Function Test
Hood/duct extinguishing
Gas/Electrical shut-off
High pile rack storage
Nozzle model/placement
H.P. vents/access/corridors
Fire alarm connection
Tract access/hydrant verification
Final
Other:
SPRAY BOOTHS
KNOX SYSTEM
Installation
Building Knox box
Air flow test
Gate access Knox box/padlock
Mechanical interlock
BUILDING INSPECTIONS
Extinguishing system
T/I final
Fire alarm connection
Shell final
Final
Final for occupancy