30463 UNIONTOWN WAY FIRE20-0680 THE TOWNESIliana Gutierrez
Subject:
Location:
Start:
End:
Recurrence:
Organizer:
Call Handling Mode 2:
Rep. Name: HECTOR
Phone#: 951-847-2908
FIRE20-0680 TR37178 SPK FINAL LOT 61
30463 UNIONTOWN WAY
Mon 10/19/2020 9:30 AM
Mon 10/19/2020 10:00 AM
(none)
Menifee OFM
2
Cell#:
Co. Name: FSS
CrossSt: THE TOWNES
HYDRANT SYSTEM
PASS
FAIL
FIRE ALARM
PASS
FAIL
Thrust block pre -pour
Rough -wire inspection
Underground rough
Function test
Underground hydro
Duct detectors/velocity
Flush
24 hr. battery test
Final
Sprinklarf monitoring
SPRINKLER U.G.
Fin l
Thrust block pre -pour
SPECIAL SUPPRESSION
Underground rough
OZ
Door fan test
Underground hydro
01
Abort test
Flush
Mechanical shutdown
Final
Detector test
FIRE SPRINKLER
Deluge/pre-action
Weld inspection
Final
Overhead rough piping
UST/AST TANK
Overhead hydro
Installation
UG flush / OK to connect
Removal
Main drain/Inspect. Test
Emergency shut off
High pile storage
Primary piping
In -rack sprinklers
Secondary piping
Hose racks
Dispensers & shear valves
X
Final
Final
KITCHEN HOOD EXTINGUISHING
MISC. INSPECTION
Detection syste
Spray booths
Function Test:--
Hood/duct extinguishing
GaslElectri I shut-off
High pile rack storage
Nozzle W6del/placement
H.P. vents/access/corridors
Fire 2l6rm connection
Tract access/hydrant verification
Final
Other:
SPRAY BOOTHS
KNOX SYSTEM
Installation
Building Knox box
Air flow test
Gate access Knox box/padlock
Mechanical interlock
BUILDING INSPECTIONS
Extinguishing system
T/I final
Fire alarm connection
Shell final
Final
Final for occupancy
Start Time: Finish Time:
21
(liana Gutierrez
Subject:
FIRE20-0680 TR37178 O/H ROUGH/HYDRO LOT 61
Location:
30463 UNIONTOWN WAY
Start:
Mon 8/10/2020 8:30 AM
End:
Mon 8/10/2020 9:00 AM
Recurrence:
(none)
Organizer:
Menifee OFM
Call Handling Mode 2:
2
Rep. Name: HECTOR
Phone#: 951-847-2908
Cell#:
Co. Name: FSS
lilubboL. 1 rir- 1 UM14rZo
HYDRANT SYSTEM
PASS
FAIL
FIRE ALARM
PASS
FAIL
Thrust block pre -pour
Rough -wire inspection
Underground rough
Function test
Underground hydro
Duct detectors/velocity
Flush
24 hr. battery test
Final
Sprinkler monitoring
SPRINKLER U.G.
Final
Thrust block pre -pour
SPECIAL SUPPRESSION
Underground rough
Door fan test
Underground hydro
Abort test
Flush
Mechanical shutdown
Final
Detector test
FIRE SPRINKLER
Deluge/pre-action
Weld inspection
Final
X
Overhead rough piping
UST/AST TANK
X
Overhead hydro
Installation
UG flush / OK to connect
Removal
Main drain/Inspect. Test
Emergency shut off
High pile storage
Primary piping
In -rack sprinklers
Secondary piping
Hose racks
Dispensers & shear valves
Final
Final
KITCHEN HOOD EXTINGUISHING
MISC. INSPECTION
Detection system
Spray booths
Function Test
Hood/duct extinguishing
Gas/Electrical shut-off
High pile rack storage
Nozzle model/placement
H.P. vents/access/corridors
Fire alarm connection
Tract access/hydrant verification
Final
Other:
SPRAY BOOTHS
KNOX SYSTEM
Installation
Building Knox box
Air flow test
Gate access Knox box/padlock
Mechanical interlock
BUILDING INSPECTIONS
Extinguishing system
T/I final
Fire alarm connection
Shell final
Final
Final for occupancy
Start Time: Finish Time:
5