Loading...
2019/06/05 I.E. General Engineering, Inc. Contract Change Order No. 002 - CIP 18-08 Adams Street Improvement Phase 1 CITY OF MENIFEE DEPARTMENT OF PUBLIC WORKS NI CONTRACT CHANGE ORDER NO.002 Page 1 of 2 DATE: 6/5/2019 PROJECT DESCRIPTION: ADAMS STREET IMPROVEMENT PHASE I PROJECT NO: CIP 18-08 PURCHASE ORDER NO: CONTRACTOR: IE GENERALL ENGINEERING DESCRIPTION OF CHANGES AND/OR EXTRA WORK: The Contractor is hereby directed to make the herein described changes from the plans and specifications and/or perform the following described work not included in the Plans and Specifications for this project. ITEM DESCRIPTION Ulm QUANTITY UNITPRICE TOTAL Bid Item NO 17 Unclassified Excavation on the original Bid sheet reflected Ilhe quantity of 207.00 Cubic Yards.However the actual quantity was CO2 795.00 Cubic Yards for a difference of 588 Cubic Yards CY 588 40.00 S21520 00 TOTAL ESTIMATED PRICE FOR THIS CHANGE ORDER: $23,520.00 This document shall become an amendment to the Contract and all provisions of the Contract will apply hereto. This Change Order constitutes a complete and final resolution of all claims of the Contract for additional time or additional compensation related to or affected by work that is the subject of this Change Order Quantities of items other than Lump Sum are not to exceed the amounts indicated JUSTIFICATION: (Be specific on each item. Attach supporting documents as necessary) On the orginal Engineers Bid sheet bid item NO.17 total cubic yards was 207.the actual cubic yards for this bid item was 795.00 for an increase of 588 cubic yards.This added$23,520.00 to the contract. O additional WOr to a S will. B require requirea to perform this work. M:\PubljcWorke DepadmeW_Public Works PmjeclslCIP Pmjecls119-e11 Adams Stmat Impmvemenls Ph11G.Change OrderslADAMS STREET IMPROVMENT CHANGE ORDER 02 r.: CITY OF MENIFEE DEPARTMENT OF PUBLIC WORKS N l CONTRACT CHANGE ORDER NO,002 .r Page 2 of 2 CONTRACT VARIANCE SUMMARY CCO# Description Amount % Additional Time Date Approved 2 increase in bid item 17 $23,520-00 5.24% 0 'Totals $23.520 00 5.24% 0 (Original Contract Amount: $448,872,50 Date Started: April 8,2019 Previous Change Order Amounts: $0 00 Original Completion Date: June 11,2019 Current Change Order Amount: $23,520-OD .Additional Time(Working Days) 0 Revised Contract Amount: $472.392.50 Revised Completion Date: June 11,2019 AUTHORIZATION BY CITY: Weeanimo roval Date: l( _ --- Date: IP Senor Engineer ODn T,Construction Manager /kublic y: 1 Date:_7,1!' 19 s Director/City Engineer ACCEPTANCE BY CONTRACTOR: We,the undersigned Contractor,have given careful consideration to the above described changes and/or extra work and hereby agree that said work is a supplement to the contract and all provisions will apply hereto. Accepted by: _ Date: 6/5/1" Signatur Gio nand RME Please print name and title M:1Public Works Depadmenll_Public Works PmjoclslCIP Prejecls110-0a Adams Street Improvements Ph1tC.Chango OrdBm\ADAMS STREET IMPROVMENT CHANGE ORDER 02