2018/02/08 L.C. Paving and Sealing, Inc. CIP No.18-05 Sherman Rd Missing Sidewalk CITY OF MENIFEE
?' DEPARTMENT OF PUBLIC WORKS
ni
ENIFE 5}
CONTRACT CHANGE ORDER N0.001
Page 1 of 2
DATE: 5/10/2018
PROJECT DESCRIPTION: New Sidewalk Installation
PROJECT NO: CIP No.18-05(Sherman Road Missing Sidewalk) PURCHASE ORDER NO: 1460
CONTRACTOR: L.C.Paving and Sealing,INC
DESCRIPTION OF CHANGES AND/OR EXTRA WORK:
The Contractor is hereby directed to make the herein described changes from the plans and specifications and/or perform the following described work
not included in the Plans and Specifications for this project.
ITEM DESCRIPTION U/M QUANTITY UNIT PRICE TOTAL
1 Bid Item 2:Additional removal and disposal of existing PCC SF 284 $3.50 $994.00
2 Bid Item 3:Additional 4"PCC SF 284 $5.50 $1,562.00
3 Bid Item 5:Deletion: Install glue down truncated domes EA 3 $ 550.00 ($1,650.00)
4 Bid Item 5:Install wet set truncated domes EA 4 300.00 $1,200.00
5 Bid Item 6:Additional cross gutter CY 4 54.00 $216.00
TOTAL ESTIMATED PRICE FOR THIS CHANGE ORDER: $2,322.00
This document shall become an amendment to the Contract and all provisions of the Contract will apply hereto. This Change Order constitutes a complete and final resolution
of all claims of the Contract for additional time or additional compensation related to or affected by work that is the subject of this Change Order. Quantities of items other than
Lump Sum are not to exceed the amounts indicated.
JUSTIFICATION: (Be specific on each item. Attach supporting documents as necessary)
Item 1: Additional removal and disposal of existing sidewalk to fix(1)additional pedestrian ramp.
Item 2: Additional installation of new pedestrian ramp and portion of sidewalk
Item 3: Deletion of(3)glue down truncated domes
Item 4: Installation of(4)wet-set truncated domes
Item 5: Additional installation of gross cutter drain
Item 6:
M:\Public Works Department\_Public Works Projects\CIP Projects\18-05 City Sidewalk ProjectsA Sherman at Hans Christensen\CCO1
CITY OF MENIFEE
DEPARTMENT OF PUBLIC WORKS
ENIFE
CONTRACT CHANGE ORDER NO.001
4
may.
Page 2 of 2
CONTRACT VARIANCE SUMMARY
CCO# Description Amount % Additional Time Date Approved
1 $2,322.00 5.80% 0
Totals $2,322.00 5.80% 0
Original Contract Amount: $ 40,061.50 Date Started: March 19,2018
Previous Change Order Amounts: $ - Original Completion Date: April 2,2018
Current Change Order Amount: $ 2,322.00 Additional Time(Working Days) 0
Revised Contract Amount: $ 42,383.50 Revised Completion Date: April 2,2018
Change Order Amount $ 2,322.00
Total Change Orders $ 2,322.00
Remaining Change Order Amount $
AUTHORIZATION BY CITY:
Recommended for approval by:
Date:
Allen Yun
Acting Fleet&Facilities Manager
Approved by:
_ rl
Date: ' Date:"
Jo ath Smith,P.E. Armando G.Villa'
D're or of Public Works/City Engineer City Manager /
ACCEPTANCE BY CONTRACTOR:
We,the undersigned Contractor,have given Careful consideration to the above described changes and/or extra work and hereby agree that said work
is a supplement to the contract and all provis'Ons will apply hereto.
Accepted by: � Date:—01 ZI I
Sig ure
Please print name and title
M:\Public Works Department\_Public Works Projects\CIP Projects\18-05 City Sidewalk Projecls\4.Sherman at Hans Christensen\CC01
MENIFEE
CIS OF MENIFEE
AGREEMENT/CONTRACT COVERSHEET
DATE: 03/05/2018
TO: Armando G.Villa,City Manager
CC: Department Date Initials
Jonathan G. Smith, PW Director/City Engr. 3
Wendy Preece,Acting Finance Director
Jeffrey T. Melching, City Attorney C�
.�- Su'r(3J11
Sarah A. Manwaring, City Clerk Own �<<2�
FROM: Carlos E.Geronimo,Senior Civil Engineer s 'I$I\�
f L
SUBJECT: Owner-Contractor Agreement with LCP fro Sherman Rd Missing Sidewalk Link,
CIP 18-05
IS THE AGREEMENT/CONTRACT WITHIN THE CITY MANAGER'S SIGNATURE AUTHORITY?
®Yes—® Purchase of Commodities Under$50,000 ❑ Professional Services under$25,000
❑Change Order under$25,000 or less than 10%of original contract(supplies,equipment,services
or construction contracts)
❑ No—City Council authorized City Manager to sign(Council action attached)
WHY IS THIS AGREEMENT/CONTRACT NEEDED?
The City of Menifee Public Works Department is proposing to construct a portion of missing sidewalk on Sherman
Road adjacent to Hans Christensen Middle School.
WHAT IS THE TOTAL LENGTH OF THE AGREEMENT/CONTRACT?
March 5,2018 to April 5, 2018
WHAT IS THE TOTAL DOLLAR AMOUNT OF THE AGREEMENT/CONTRACT?
The Contract is in the amount not to exceed$44,067(includes 10%contingency amount).
HOW WAS THE VENDOR/CONSULTANT/CONTRACTOR DECIDED ON?
Supplies/Equipment/Maintenance/Construction Prior Contract/Expericence with the City
❑$5,000-$49,000—Three Written Quotes ❑ Yes
❑Over$50,000—Competitive Bidding and Formal Proposals
Public Works Proiects Professional Services
® Under$45,000—Purchase Order,Contract(Prudent Judgement) ❑Over$25,000—City Council Approval
❑$45,000-$174,999—Informal Bidding Process
❑Over$175,000—Formal Bidding Required
WHERE ARE THE FUNDS COMING FROM?
FY 17-18 Measure DD funds(See attached staff report)
*Please attached a second page for additional information to support this agreement.
WHAT GENERAL LEDGER ACCOUNT NUMBER SHOULD BE USED FOR THE PURCHASE ORDER?
105-4555-58063
IS THERE SUFFICIENT BUDGET? WHAT IS THE AVAILABLE BUDGET?
Yes,the total approved project budget is$550,000 of which $462,894 remain.
2
.1
r r^.
.MENIFEE:.=
CITY OF MENIFEE
------------------------------------------------------------------
SUBJECT: Budget Appropriation in the Measure DD Fund for the
School Sidewalk "Missing Link" Improvements Project
MEETING DATE: September 6, 2017
TO: Mayor and City Council
PREPARED BY: Allen Yun, Senior Administrative Analyst
REVIEWED BY: Jonathan Smith, Public Works Director/CityEnngineer
APPROVED BY: Ronald E. Bradley, Interim City Manager Q&
------------------------------------------------------------------
RECOMMENDED ACTION
Approve an increase in appropriations in the Measure DD Fund in the amount of $550,000 for
the installation of City sidewalks.
DISCUSSION
At the May 17, 2017 City Council Meeting, Council requested to have the Public
Works/Engineering Department bring a program to Council for approval to construct missing
sidewalks for routes to schools.
As requested, the Public Works/Engineering Department surveyed the City's right-of-ways near
school zones and identified the following missing public sidewalk segments:
MISSING SIDEWALK LIST
Street From To Street Length (ft) MUSD School nearby
Side (3,500 ft)
New Salt Creek Freedom Crest
Menifee Road Arrowhead Bridge West side 465 Elementary
Lindenberger
Road Trailhead Dr Southbound West Side 1,160 Ethan A Chase Middle
Southshore South Shore
Holland Road Drive Westbound North side 729 Elementary
Ridgemoor Valley Phoenix Way North side 710 Ridgemoor Elementary
City of Menifee Staff Report
School Sidewalk Missing Link
September 6, 2017
Page 2 of 2
Road Boulevard
Garbani Road Evans Rd School South Side 1,240 Menifee Elementary
Sherman Hans Christensen
Road McCall Blvd Shadel Road West Side 588 Middle
Hans Christensen
McCall Blvd Encanto Drive Sherman Rd South Side 1,120 Middle
Street From To Street Length (ft) Romoland School
Side nearby(3,500 ft)
Boulder Ridge
McCall Blvd Menifee Rd Junipero Rd North Side 1,250 Elementary
Boulder Ridge
McCall Blvd Junipero Rd Woodside Rd South Side 1,500 Elementary
Boulder Ridge
McCall Blvd Aspel Rd Eastbound South Side 500 Elementary
Street From To Street Length (ft) Charter School nearby
Side (3,500 ft)
Sherman
Road Holland Rd School East Side 1,440 Santa Rosa Academy
TOTAL 10,702.00
At the direction of the City Council, staff would prepare a notice of inviting bid (BID) to solicit
bids from properly licensed contractors to construct all or a portion of the missing sidewalk
sections listed above.
FISCAL IMPACT
Staff requests City Council to authorize an increase in appropriation in the Measure DID Fund to
account 105-4555-58063 in the amount of $550,000 for the installation of the listed sidewalks
above. This will bring the total available fund balance in the Measure DID fund from the
projected 2017/18 year-end balance of$1,369,814 to $819,814.
CITY OF MENIFEE BID AND CONTRACT DOCUMENTS
OWNER-CONTRACTOR AGREEMENT
CIP NO. 18-05, SHERMAN ROAD MISSING SIDEWALK
This Owner-Contractor Agreement ("Agreement") is made and entered into for the above
referenced Project by and between the City of Menifee ("Agency"), and L.C. PAVING &
SEALING. INC ("Contractor"), whose principal business address is 330 RANCHEROS
DRIVE, STE. 208, SAN MARCOS, CA 92069 on the 8th day of February, 2018.
In consideration of the mutual covenants and agreements set forth herein, the Agency and
Contractor have mutually agreed as follows:
1. CONSTRUCTION
The Contractor agrees to do all the Work and furnish all the labor, services, materials and
equipment necessary to construct and complete the Project in accordance with the Contract
Documents (as hereinafter defined), including all work, labor, services, materials and equipment
described and reasonably inferable from documents enumerated in Exhibit "A" attached hereto
and incorporated herein by reference (such construction and furnishing of labor, service,
materials and equipment hereinafter referred to as the "Work") in a good worker-like and
substantial manner and to the satisfaction of the Agency, in connection with the Sherman Road
Missing Sidewalk Proieet, CIP No. 18-05 to be constructed on Sherman Road in the City of
Menifee, California. The term Contract Documents shall mean this Agreement, and all of the
items enumerated in Exhibit "A" and all change orders or addenda issued by the Agency with
respect thereto. Agency must consent in writing to any changes in the scope of Work. Exhibit
"A" shall be deemed revised in accordance with any revisions for which Agency's consent has
been issued. Any revisions to the scope of Work for which Agency's consent has not been
issued shall be null and void.
2. CONTRACT PRICE
Agency hereby agrees to pay and the Contractor agrees to accept as full compensation for all
Work performed in accordance with these Contract Documents the Contract Price as set forth in
Exhibit "B", Contract Price, attached hereto and incorporated herein by reference. Payments to
the Contractor shall be made in the manner described in the Special Provisions.
3. TIME FOR PERFORMANCE
Time is of the essence in the performance of Work for this Agreement and all timing
requirements shall be strictly adhered to unless otherwise modified by the Agency in accordance
with these Bid and Contract Documents.
The Contractor shall complete the Work in every detail to the satisfaction of the Agency,
exclusive of maintenance periods, within the specified duration set forth in the Notice to
Proceed.
290/0 3 1 858-0008
7645681.2 a03/01/18 Page 1
4. DELAYS AND EXTENSIONS OF TIME
See Section 6-6 of the Special Provisions.
5. LABOR CODE REQUIREMENTS
Pursuant to Labor Code Section 1771.1, the Contractor and all subcontractors shall be registered
with the Department of Industrial Relations. Pursuant to Labor Code Section 1771.4, the
Contractor is hereby notified that this Project is subject to compliance monitoring and
enforcement by the Department of Industrial Relations. [EFFECTIVE APRIL 1, 2015.]
6. NON-DISCRIMINATION
In the performance of this Agreement, the Contractor shall not refuse or fail to hire or employ
any qualified person, or bar or discharge from employment any person, or discriminate against
any person, with respect to such person's compensation, terms, conditions or privileges of
employment because of such person's race, religious status, sex or age.
7. AUTHORIZED AGENCY REPRESENTATIVES
On behalf of the Agency, the City Engineer of the City of Menifee shall be the Agency's
authorized representative in the interpretation and enforcement of all Work performed in
connection with this Agreement. The City Engineer may delegate authority in connection with
this Agreement to his/her assigned designees.
8. WORKERS' COMPENSATION INSURANCE
a) By my signature hereunder, as Contractor, I certify that I am aware of the
provisions of Section 3700 of the Labor Code, which requires every employer to be insured
against liability for Workers' Compensation or to undertake self-insurance in accordance with
the provisions of that Code, and I will comply with such provisions before commencing the
performance of the Work of this Agreement.
b) The Contractor shall require each subcontractor to comply with the requirements
of Section 3700 of the Labor Code. Before commencing any Work, the Contractor shall cause
each subcontractor to execute the following certification:
"I am aware of the provisions of Section 3700 of the Labor Code, which
requires every employer to be insured against liability for worker's
compensation or to undertake self-insurance in accordance with the
provisions of that Code, and I will comply with such provisions before
commencing the performance of the Work of this Agreement."
9. ENTIRE AGREEMENT; CONFLICT
The Contract Documents comprise the entire agreement between the Agency and the Contractor
with respect to the Work. In the event of conflict between the terms of this Agreement and the
bid of the Contractor, then this Agreement shall control and nothing herein shall be considered as
an acceptance of the terms of the bid conflicting herewith.
290/031858-0008
7645681.2 a03/01/18 Page 2
10. MAINTENANCE OF AGREEMENT DOCUMENTATION
Contractor shall maintain all books, documents, papers, employee time sheets, accounting
records and other evidence pertaining to costs incurred and shall make such materials available at
its office at all reasonable times during the term of this Agreement and for three (3) years from
the date of final payment under this Agreement, for inspection by Agency and copies thereof
shall be furnished to Agency if requested.
11. INDEPENDENT CONTRACTOR
At all times during the term of this Agreement, Contractor shall be an independent contractor and
shall not be an employee, agent, partner or joint venturer of the Agency. Agency shall have the
right to control Contractor insofar as the results of Contractor's services rendered pursuant to this
Agreement; however, Agency shall not have the right to control the means by which Contractor
accomplishes such services.
12. LICENSES AND PERMITS
Contractor represents and declares to Agency that it has all licenses, permits, qualifications and
approvals of whatever nature which are legally required to practice its profession. Contractor
represents and warrants to Agency that Contractor shall, at its sole cost and expense, keep in
effect at all times during the term of this Agreement, any licenses, permits, qualifications or
approvals which are legally required for Contractor to practice its profession.
13. GOVERNING LAW, VENUE
This Agreement and the Contract Documents shall be construed under and in accordance with
the laws of the State of California, and the appropriate venue for any action or proceeding arising
from this Agreement and/or the Contract Documents shall be had in the Superior Court of
Riverside, Temecula Branch
14. COUNTERPARTS
This Agreement may be executed in any number of counterparts, each of which shall for all
purposes be deemed to be an original.
15. FALSE CLAIMS
Contractor acknowledges that if a false claim is submitted to the Agency, it may be considered
fraud and Contractor may be subject to criminal prosecution. Contractor acknowledges that the
False Claims Act, California Government Code sections 12650, et seq., provides for civil
penalties where a person knowingly submits a false claim to a public entity. These provisions
include within their scope false claims made with deliberate ignorance of the false information or
in reckless disregard'of the truth or falsity of the information. In the event the Agency seeks to
recover penalties pursuant to the False Claims Act, it is entitled to recover its litigation costs,
including attorneys' fees. Contractor hereby acknowledges that the filing of a false claim may
the Contractor to an administrative debarment proceeding wherein Contractor may be prevented
from further bidding on public contracts for a period of up to five (5) years.
I have read and understood all of the provisions of this Section 15, above:
290/031858-0008
7645681.2 a03/01/18 Page 3
(Initial) (InA ial)
16. AGREEMENT MODIFICATION
This Agreement and the Contract Documents may not be modified orally or in any manner other
than by an amendment in writing and signed by the Agency and the Contractor.
IN WITNESS WHEREOF this Agreement is executed as of the date first written above.
AGENCY: CONTRACTOR:
City of Menifre L.C. PAV iG & SE LING, INC.
By: By:
Armando 61villa, City Manager /Na - Jose A Salinas
resident, Sec., Treas., VP, Manager
APPROVED AS TO FORM: By:
Name:
By: Its:
JggeflT. Melching, City Attor y
ATTEST•
B ; - 040665
6S rah A. Ma aring, City Cler Contractor's City Business License No.
621610A—B —C12
State Contractor License No. & Class
330 Rancheros Dr. Suite 208
Street Address
San Marcos, CA 92069
City, State, Zip Code
[NOTE: In the event the Contractor is a Corporation, the signatures of two separate
persons holding different offices must be provided.]
290/031858-0008
7645691.2a03/0Ii18 Page 4
EXHIBIT A
CONTRACT DOCUMENTS
Scope of Work
Construction Plans and Exhibits
City of Menifee Special Provisions
Standard Specifications for Public Works Construction (Greenbook latest edition)
City of Menifee Standard Plans
290/031858-0008
7645681.2 a03/01/18 Page 5
EXHIBIT B
CONTRACT PRICE
[NOTE - TO BE COMPLETED TO CONFORM WITH BID SCHEDULE ITEMS]
The Contract Price for performing all Work described in the Contract Documents, including
labor, materials, services and equipment is the total amount of all lump sum items and of all unit
price sums, determined by multiplying the unit price for each item times the actual quantity of
each such item, as determined by the Agency.
290/031858-0008
7645681.2 a03/01/18 Page 6
CIP 18-05 SHERMAN ROAD MISSING SIDEWALK
EXHIBIT A
SCOPE OF WORK
1. Contractor shall remove approximately 56 CY of material from the site over the proposed
sidewalk area to a depth of 4" max. The contractor shall compact the subgrade to 90%
relative compaction prior to placing concrete.
2. Contractor shall remove and dispose of approximately 414 sf of existing concrete surface.
.3. Contractor shall adjust to grade utility boxes inside the project area and protect-in-place
all other existing utilities.
4. Contractor shall place PCC sidewalk 7.5' wide x 4" thick as shown in the construction
exhibits. Sidewalk shall be placed per City of Menifee Standard Plan No. 400.
5. Contractor shall install ADA pedestrian ramps per City of Menifee Standard Plan No.405.
6. Contractor shall install Safety Step glue down truncated domes color yellow.
7. Contractor shall be responsible to meet the grade requirements of the ADA ramp. If after
construction the pedestrian ramps is not compliant to ADA and City requirements,
contractor shall be responsible at his own cost to remove and replace the ramp.
8. Contractor shall install cross gutter per City of Menifee Standard Plan 209. Contractor is
responsible to meet and match the existing flow line elevations of the cross gutter.
9. All work shall be performed per 2015 Standard Specifications for Public Works
Construction "Greenbook" unless otherwise specified in these contract documents.
10. Contractor is responsible for providing and maintaining all traffic control devices for the
duration of construction. Note that an elementary school is nearby and pedestrian traffic
may be present during construction hours.
11. Contractor is solely responsible for verifying grades. Sidewalk cross fall shall not
exceed 1.5%.
12. Contractor is responsible for removal and disposal to a legal site of any export, trash,
debris, and all other materials related to the work performed under this contract.
13. Contractor shall warranty all work performed under this contract for a period of not less
than 365 days from the date of completion.
14. Unless otherwise agreed to in writing working hours shall be from 7:30 am to 4:30pm
Monday through Friday. No weekend or holiday work is allowed unless permission is
requested and granted in writing 1 week prior to performing the work. The City shall accept
or deny such a request at its sole discretion.
15. Contractor shall obtain a no fee encroachment permit from the City of Menifee prior to
beginning the work.
16. Due to the short duration of the project no progress payments shall be made. A single
payment shall be made after completion of all work. Final billing shall include certified
payroll and adequate documentation to the satisfaction of the City Engineer that all
subcontracts and material suppliers have been paid. Payment shall be withheld until such
items are received and verified. No bonding shall be required for this project.
17. Contractor shall provide the City 72 hour notice prior to beginning of construction and shall
provide 24 hr notice prior to any inspections.
18. Contractor responsible for contacting Underground Service Alert at least 48 hours prior to
any excavation.
EXHIBIT B
CONTRACT PRICE
Sherman Rd Missing Sidewalk
ITEM ESTIMATED EXTENDED
No DESCRIPTION UNIT QUANTITY UNIT PRICE ITEM
AMOUNT
1 Unclassified excavation, include CY 56
subgrade compaction and grading 31 i� S9.3oG
2 Remove and dispose of existing PCC SF 414 $3.50 1A°-^^
S 1.449 00
3 Install 4" PCC per City standard SF 4,579 $5.50 $25,184.50
4 Raise water valve cover to grade EA 1
S�0 S50
5 Install glue down Safety Step truncated EA 3 $550
$1,650.00
domes
6 Install Cross Gutter per City standard SY 32 $54.00 $1,728.00
7 Remove and relocate STOP SIGN EA 1
S200 S200
TOTAL
540.061.50
Total Contract Amount = $ S40.061 .50
Price for items 2, 3, 5, and 6 are based on contractor's unit bid price per PW 17-02 On-Call Concrete
Maintenance Services contract executed on November 2, 2017.