2017/11/27 L.C. Paving and Sealing, Inc. CIP18-05 Holland Rd Missing Sidewalk CITY OF MENIFEE BID AND CONTRACT DOCUMENTS
OWNER-CONTRACTOR AGREEMENT
CIP NO. 18-05, HOLLAND ROAD MISSING SIDEWALK
This Owner-Contractor Agreement ("Agreement") is made and entered into for the above
referenced Project by and between the City of Menifee ("Agency"), and L.C. PAVING &
SEALING, INC ("Contractor"), whose principal business address is 330 RANCHEROS
DRIVE,STE.208,SAN MARCOS,CA 92069 on the 27th day of November,2017.
In consideration of the mutual covenants and agreements set forth herein, the Agency and
Contractor have mutually agreed as follows:
1. CONSTRUCTION
The Contractor agrees to do all the Work and furnish all the labor, services, materials and
equipment necessary to construct and complete the Project in accordance with the Contract
Documents (as hereinafter defined), including all work, labor, services, materials and equipment
described and reasonably inferable from documents enumerated in Exhibit "A" attached hereto
and incorporated herein by reference (such construction and furnishing of labor, service,
materials and equipment hereinafter'referred to as the "Work") in a good worker-like and
substantial manner and to the satisfaction of the Agency, in connection with the Holland Road
Missing Sidewalk Protect, CIP No. 18-05 to be constructed on Murrieta Road in the City of
Menifee, California. The term Contract Documents shall mean this Agreement, and all of the
items enumerated in Exhibit"A" and all change orders or addenda issued by the Agency with
respect thereto. Agency must consent in writing to any changes in the scope of Work. Exhibit
"A" shall be deemed revised in accordance with any revisions for which Agency's consent has
been issued. Any revisions to the scope of Work for which Agency's consent has not been
issued shall be null and void.
2. CONTRACT PRICE
Agency hereby agrees to pay and the Contractor agrees to accept as full compensation for all
Work performed in accordance with these Contract Documents the Contract Price as set forth in
Exhibit `B", Contract Price, attached hereto and incorporated herein by reference. Payments to
the Contractor shall be made in the manner described in the Special Provisions.
3. TIME FOR PERFORMANCE
Time is of the essence in the performance of Work for this Agreement and all timing
requirements shall be strictly adhered to unless otherwise modified by the Agency in accordance
with these Bid and Contract Documents.
The Contractor shall complete the Work in every detail to the satisfaction of the Agency,
exclusive of maintenance periods, within the specified duration set forth in the Notice to
Proceed.
290/031858-0008
7645681.2 al1/17/17 Page 1
4. DELAYS AND EXTENSIONS OF TIME
See Section 6-6 of the Special Provisions.
5. LABOR CODE REQUIREMENTS
Pursuant to Labor Code Section 1771.1, the Contractor and all subcontractors shall be registered
with the Department of Industrial Relations. Pursuant to Labor Code Section 1771.4, the
Contractor is hereby notified that this Project is subject to compliance monitoring and
enforcement by the Department of Industrial Relations. [EFFECTIVE APRIL 1, 2015.]
6. NON-DISCRIMINATION
In the performance of this Agreement, the Contractor shall not refuse or fail to hire or employ
any qualified person, or bar or discharge from employment any person, or discriminate against
any person, with respect to such person's compensation, terms, conditions or privileges of
employment because of such person's race, religious status, sex or age.
7. AUTHORIZED AGENCY REPRESENTATIVES
On behalf of the Agency, the City Engineer of the City of Menifee shall be the Agency's
authorized representative in the interpretation and enforcement of all Work performed in
connection with this Agreement. The City Engineer may delegate authority in connection with
this Agreement to his/her assigned designees.
8. WORKERS' COMPENSATION INSURANCE
a) By my signature hereunder, as Contractor, I certify that I am aware of the
provisions of Section 3700 of the Labor Code, which requires every employer to be insured
against liability for Workers' Compensation or to undertake self-insurance in accordance with
the provisions of that Code, and I will comply with such provisions before commencing the
performance of the Work of this Agreement.
b) The Contractor shall require each subcontractor to comply with the requirements
of Section 3700 of the Labor Code. Before commencing any Work, the Contractor shall cause
each subcontractor to execute the following certification:
"I am aware of the provisions of Section 3700 of the Labor Code, which
requires every employer to be insured against liability for worker's
compensation or to undertake self-insurance in accordance with the
provisions of that Code, and I will comply with such provisions before
commencing the performance of the Work of this Agreement."
9. ENTIRE AGREEMENT; CONFLICT
The Contract Documents comprise the entire agreement between the Agency and the Contractor
with respect to the Work. In the event of conflict between the terms of this Agreement and the
bid of the Contractor, then this Agreement shall control and nothing herein shall be considered as
an acceptance of the terms of the bid conflicting herewith.
290/031858-0008
7645681.2 al 1/17/17 Page 2
10. MAINTENANCE OF AGREEMENT DOCUMENTATION
Contractor shall maintain all books, documents, papers, employee time sheets, accounting
records and other evidence pertaining to costs incurred and shall make such materials available at
its office at all reasonable times during the term of this Agreement and for three (3) years from
the date of final payment under this Agreement, for inspection by Agency and copies thereof
shall be furnished to Agency if requested.
11. INDEPENDENT CONTRACTOR
At all times during the term of this Agreement, Contractor shall be an independent contractor and
shall not be an employee, agent, partner or joint venturer of the Agency. Agency shall have the
right to control Contractor insofar as the results of Contractor's services rendered pursuant to this
Agreement; however, Agency shall not have the right to control the means by which Contractor
accomplishes such services.
12. LICENSES AND PERMITS
Contractor represents and declares to Agency that it has all licenses, permits, qualifications and
approvals of whatever nature which are legally required to practice its profession. Contractor
represents and warrants to Agency that Contractor shall, at its sole cost and expense, keep in
effect at all times during the term of this Agreement, any licenses, permits, qualifications or
approvals which are legally required for Contractor to practice its profession.
13. GOVERNING LAW, VENUE
This Agreement and the Contract Documents shall be construed under and in accordance with
the laws of the State of California, and the appropriate venue for any action or proceeding arising
from this Agreement and/or the Contract Documents shall be had in the Superior Court of
Riverside, Temecula Branch
14. COUNTERPARTS
This Agreement may be executed in any number of counterparts, each of which shall for all
purposes be deemed to be an original.
15. FALSE CLAIMS
Contractor acknowledges that if a false claim is submitted to the Agency, it may be considered
fraud and Contractor may be subject to criminal prosecution. Contractor acknowledges that the
False Claims Act, California Government Code sections 12650, et seq., provides for civil
penalties where a person knowingly submits a false claim to a public entity. These provisions
include within their scope false claims made with deliberate ignorance of the false information or
in reckless disregard of the truth or falsity of the information. In the event the Agency seeks to
recover penalties pursuant to the False Claims Act, it is entitled to recover its litigation costs,
including attorneys' fees. Contractor hereby acknowledges that the filing of a false claim may
the Contractor to an administrative debarment proceeding wherein Contractor may be prevented
from further bidding on public contracts for a period of up to five (5) years.
I have read and understood all of the provisions of this Section 15, above:
290/031858-0008
7645681.2 al 1/17/17 Page 3
(Initial) *(Inial)
16. AGREEMENT MODIFICATION
This Agreement and the Contract Documents may not be modified orally or in any manner other
than by an amendment in writing and signed by the Agency and the Contractor.
IN WITNESS WHEREOF this Agreement is executed as of the date first written above.
AGENCY: CONTRACTOR:
City of Menifee L.C. PAMCJV& SLING, INC.
By: -eta, By: /
Ronald E. Bradley, Interim City Mana m f 4�6c
s. �i��SV Sec . IfJ�J /rp IY1/�l1
APPROVED AS TO FORM: By:
Name:
By: Its:
JefTey Melching, i Attorney
ATTEST-
By
S� -ah A. Manwari g, City Cler Contractor's City Business License No.
State Contractor License No. & Class
3 3o R Ayi d e 165- ,OA *2ZN,
Street Address
5�4 /�ent-es, 614
City, State, Zip Code
[NOTE: In the event the Contractor is a Corporation,the signatures of two separate
persons holding different offices must be provided.]
290/031858-0008
7645681.2 al 1/17/17 Page 4
EXHIBIT A
CONTRACT DOCUMENTS
Scope of Work
Construction Plans and Exhibits
City of Menifee Special Provisions (2017 Specifications)
Standard Specifications for Public Works Construction (Greenbook latest edition)
City of Menifee Standard Plans
290/03 1 85 8-0008
7645681.2 al1/17/17 Page 5
EXHIBIT B
CONTRACT PRICE
[NOTE- TO BE COMPLETED TO CONFORM WITH BID SCHEDULE ITEMS]
The Contract Price for performing all Work described in the Contract Documents, including
labor, materials, services and equipment is the total amount of all lump sum items and of all unit
price sums, determined by multiplying the unit price for each item times the actual quantity of
each such item, as determined by the Agency.
290/031858-0008
7645681.2 a]1/17/17 Page 6
CIP 18-05 HOLLAND ROAD MISSING SIDEWALK
EXHIBIT A
SCOPE OF WORK
1. Contractor shall remove approximately 78 CY of material from the site over the proposed
sidewalk area to a depth of 4" max. The contractor shall compact the subgrade to 90%
relative compaction prior to placing concrete.
2. Contractor shall adjust to grade utility boxes inside the project area and protect-in-place
all other existing utilities.
3. Contractor shall place PCC sidewalk 8' wide x 4" thick as shown in the construction
exhibits. Sidewalk shall be placed per City of Menifee Standard Plan No. 400.
4. All work shall be performed per 2015 Standard Specifications for Public Works
Construction "Greenbook" unless otherwise specified in these contract documents.
5. Contractor is responsible for providing and maintaining all traffic control devices for the
duration of construction. Note that an elementary school is nearby and pedestrian traffic
may be present during construction hours.
6. Contractor is solely responsible for verifying grades. Sidewalk cross fall shall not
exceed 1.5%.
7. Contractor is responsible for removal and disposal to a legal site of any export, trash,
debris, and all other materials related to the work performed under this contract.
8. Contractor shall warranty all work performed under this contract for a period of not less
than 365 days from the date of completion.
9. Unless otherwise agreed to in writing working hours shall be from 7:30 am to 4:30pm
Monday through Friday. No weekend or holiday work is allowed unless permission is
requested and granted in writing 1 week prior to performing the work. The City shall accept
or deny such a request at its sole discretion.
10. Contractor shall obtain a no fee encroachment permit from the City of Menifee prior to
beginning the work.
11. Due to the short duration of the project no progress payments shall be made. A single
payment shall be made after completion of all work. Final billing shall include certified
payroll and adequate documentation to the satisfaction of the City Engineer that all
subcontracts and material suppliers have been paid. Payment shall be withheld until such
items are received and verified. No bonding shall be required for this project.
12. Contractor shall provide the City 72 hour notice prior to beginning of construction and shall
provide 24 hr notice prior to any inspections.
13. Contractor responsible for contacting Underground Service Alert at least 48 hours prior to
any excavation.
EXHIBIT B
CONTRACT PRICE
Holland Rd Missing Sidewalk
ITEM ESTIMATED EXTENDED
No DESCRIPTION UNIT QUANTITY UNIT PRICE ITEM
AMOUNT
1 Unclassified excavation, include CY 78 $116.00
subgrade compaction and grading $9,048
2 Install 4" PCC per City standard SF 5,880 $5.50 $32,340
3 Raise Utilities boxes to grade EA 2 $50.00 $100
TOTAL $41,488
Total Contract Amount = $
Price for 4" PCC is based on contractor's unit bid price for 4" sidewalk per PW 17-02 On-Call Concrete
Maintenance Services contract executed on November 2, 2017.