PC19-459RESOLUTION NO. PG 19.459
A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF
MENIFEE, CALIFORNIA RECOMMENDING THAT THE CITY COUNGIL
DENY TENTATTVE TRACT MAP NO. 2017-16s (TM NO. 373241 TO
SUBDIVIDE 20.51 ACRES INTO 204 SINGLE FAMILY RESIDENTIAL
LOTS AND COMMON AREA LOTS LOCATED ALONG THE EAST
SIDE OF SHERMAN ROAD SOUTH OF GARBANI ROAD.
Whereas, on June 2, 2017 the applicant, Sherman & Garbani, LLC and Sherman
and Haun, LP, filed a formal application with the City of Menifee for Tentative Tract Map
No. 2017-165 to subdivide 20.51 acres into 204 single family residential lots and
common area lots for landscape setbacks, common open space, private streets and
street parking located at along the east side of Sherman Road south of Garbani Road;
and,
Whereas, on August 14, 2019, the Planning Commission held a duly noticed
public hearing on Tentative Tract Map No. 2017-165, considered all public testimony as
well as all materials in the staff report and accompanying documents, which hearing was
publicly noticed by a publication in the Press Enterprise, a newspaper of general
circulation, an agenda posting, and notice to property owners within 300 feet of the
project boundaries as well as both single family neighborhoods north of the project, and
to persons requesting public notice and continued the project to September 11, 2019 in
order for staff to provide findings to deny the Tentative Tract Map; and
Whereas, on September 11,2019, the Planning Commission held the continued
public hearing on Tentative Tract Map No. 2017-165 which was not required to be re-
noticed because it was continued to a date certain; and
Whereas, the Planning Commission of the City of Menifee makes the following
Findings:
Section 1:Consistency with the General Plan. The tentative tract map is
inconsistent with the General Plan Land Use Map, applicable General
Plan objectives, policies, and programs.
The General Plan land use designation for the project site is Economic
Development Corridor - Southern Gateway (EDC-SG). EDC areas are
envisioned to develop primarily as nonresidential uses, with residential
uses playing a supporting role. The proposed tentative tract map would
develop 20.51 acres into residential development with 204 single family
lots. When combined with the townhouse community proposed under
Tentative Tract Map No. 2017-166 the overall project would develop more
than sixty percent of the 58.51 acre site with residential uses. As such
the project is primarily residential with non-residential uses playing a
supporting role. Therefore the project is inconsistent with the intent and
vison of the Genera! Plan.
lnconsistencv with General Plan
Page 1 of 5
The overall primarily residential project is located adjacent to EDC-SG
designated property to the south and east and would not be compatible
with the intent of the EDC-SG which envisioned the Southern Gateway to
be developed primarily with Business Park uses.
Plannino and Land Use Government Code Section 65589.5.
Section 65589.5 of the Planning and Land Use Government Code statesthat when a proposed housing development project complies with
applicable, objective general plan, zoning, and subdivision standards and
criteria, including design review standards, the City is required to make
specific findings under this section of the Code. lt has been determined
that the project does not comply with the Genera! Plan and therefore
Section 65589.5 is not applicable to the project. However, it should be
noted that the project would generate adverse significant and unavoidable
impacts specifically, under the environmental categories of Air Quality,
Greenhouse Gases, Transportationffraffic and Noise upon the public
health and safety unless disapproved. These direct impacts generated by
the project are based on objective standards including the South Coast
Air Quality Management Plan and City's General Plan and are discussed
in the Environmental lmpact Report prepared for the project.
Consistencv with Housinq Element.
The Project site is not identified in the City's Housing Element as a
Housing Opportunity Site for residential. The Housing Element did not
assume the site would contribute any dwelling units needed to meet the
City's Regional Housing Needs Assessment (RHNA). Therefore denial of
the Project would, not conflict with any density range or housing
opportunity anticipated in the Housing Element.
Section 2:/nconsistency with the General Plan. The design of the tentative tract
map is rnconsistent with the General Plan.
The General Plan land use designation for the project site is Economic
Development Corridor - Southern Gateway (EDC-SG). EDC areas are
envisioned to develop primarily as nonresidential uses, with residential
uses playing a supporting role. The proposed tentative tract map would
develop 20.51 acres into residentia! development with 204 single family
lots. When combined with the townhouse community proposed under
Tentative Tract Map No. 2017-166 the overall project as designed would
develop more than sixty percent of the 58.51 acre site with residential
uses. As such the project would implement a design that is primarily
residential with non-residential uses playing a supporting role. Therefore
the project design is inconsistent with the General Plan.
Section 3: Consistency with the Zoning Code. The Tentative Tract Atlap is
inconsistent with the zone designation Map, and applicable development
standards within the zone designation:
Page 2 of 5
Section 4:
Section 5:
Section 6:
The project site is currently zoned EDC-SG and is consistent with the
intent and vision of the General Plan land use designation of Economic
Development Corridor- Southern Gateway. The provisions of the EDC-SG
District zoning allow for areas designated EDC to develop primarily as
nonresidential uses, with residential uses playing a supporting role as
provided for in the General Plan. ln contrast, the tentative tract map does
not implement the intent and vision of the EDC-SG as it would result in
developing more than sixty percent of site with primarily residential uses.
As such the tentative tract map is inconsistent with intent and vision of the
EDC-SG and the project is not consistent with the zoning.
The site of the proposed land division is not physically suitable for the
proposed density of the development.
The tentative tract map is a subdivision of approximately 20.51 acres into
204 single family lots with a density of 9.9 dwelling units per acre.
Environmental impacts generated by the project have been analyzed in
an Environmental lmpact Report (ElR). The EIR determined that the
project would generate significant and unavoidable impacts under the
categories of Air Quality, Greenhouse Gases, Transportation/Traffic, and
Noise. The proposed density of the tentative tract map at this location
results in the contribution to significant and unavoidable impacts identified
by the EIR prepared for the project, therefore the site is not physically
suitable the proposed density of development.
The design of the Tentative Tract Map and improvemenfs are likely to
cause serious public health problems.
Environmental impacts resulting from the implementation of the Tentative
Tract Map have been analyzed in an Environmental Impact Report (EIR).
The EIR determined that the project would generate significant and
unavoidable impacts under the categories of Air Quality, Greenhouse
Gases, Transportation/Traffic, and Noise which are likely to cause serious
health problems with other properties and land uses in the project vicinity
including residential neighborhoods north of the project site.
Compliance with CEQA. Processing and denial of the tentative tract map
application are in compliance with the requiremenfs of the California
Environmental Qual ity Act.
An Environmental lmpact Report (EIR) has been completed for the
project which determined that the project would generate significant and
unavoidable impacts under the categories of Air Quality, Greenhouse
Gases, Transportationffraffic, and Noise. More specifically, the project
would have the following impacts:
Air Quality
The project would result in significant and unavoidable impacts relating to
operational NOx emissions during operations that would exceed
applicable South Coast Air Quality Management District regional
thresholds of significance during operations even after implementation of
Page 3 of 5
mitigation measures and no feasible measures have been identified to
reduced to levels that are less than significant. Further, the NOx
exceedances would also cause significant and unavoidable impacts
because the project would not be consistent with the Air Quality
Management Plan, which would result in a cumulatively unavoidable
sig nificant adverse impact.
Greenhouse Gases
The proposed Project will contribute to global climate change by its
incremental contribution of greenhouse gasses. Even with implementation
of the recommended mitigation measures identified in Section 4.4.7 of the
Air Quality Section, the project exceeds both the SCAQMD screening
threshold of 3,000 MTCO2e (Project = 1 1,385.63 MTCO2e) and the
interpolated SCAQMD 2022 Target Service Population threshold of 4.56
MTCO2e/SP/year (Project = 7.7 MTCO2e/SP/year) for projects. Thus,
exceedances of applicable SCAQMD regional thresholds are considered
significant and unavoidable, and the operation of the proposed project
would create a significant cumulative impact to global climate change.
Project-related GHG emissions are therefore considered to be significant
and would result in an unavoidable significant adverse impact on global
climate change.
Noise
The existing noise setting of the proposed project site will be permanently
altered as a result of implementation of the proposed Project. Offsite
traffic activities are forecast to make a cumulative contribution to
significant noise along four affected roadways:
. Tupelo Street - Bradley to Sherman Roado Garbani Road - Sherman to Haun Road. Bradley Road - south of Craig Avenue. Sherman Road - Tupelo Street to Garbant Road
Mitigation is available consisting of installing noise barriers or interior
noise reducing modifications to existing homes however this mitigation
cannot be enforced. As such, the Project will contribute significant and
unavoidable offsite cumulative noise impacts and as such will cause an
unavoidable adverse noise impacts in the project area.
Trans portationff raffic
lmplementing the proposed Project will generate a substantial number of
new trips that are forecast to require modifications to the area and local
circulation systems. With implementation of the proposed circulation
system improvements the project will not cause a significant adverse
impact to the circulation system. With implementation of the identified
offsite roadway improvements, the long-term, project specific and
cumulative circulation system impacts will not be significant if these
improvements are completed prior to when the traffic is actually
generated. However, given the uncertain nature of the timing of all
Page 4 of 5
improvements, an unavoidable significant adverse transportation impact
will result from implementation of the proposed Project.
ln order to allow for the approval of the project, a Statement of Overriding
Considerations was prepared for the EIR listing possible benefits
provided by the project; however, the Planning Commission has
considered these benefits against the significant and unavoidable impacts
generated by the project and has determined that the benefits Iisted in the
Statement of Overriding Considerations do not outweigh the potential
significant unavoidable adverse environmental impacts. As such, the
Planning Commission recommends that the City Council deny
certification of the EIR pursuant to a separate Resolution.
NOW, THEREFORE, The Planning Commission of the City of Menifee
recommends to the City Council the following:
2
1 That the City Council determine that the Findings set out above are true
and correct.
That the City Council finds that the facts presented within the public
record and within the Planning Commission Resolution provide a basis to
deny Tentative Tract Map No. 2017-165 (Tentative Tract Map No. 37324).
PASSED, APPROVED AND ADOPTED this the 11th day of September, 2019.
hairman
Attest:
nie Roseen, Deputy Clerk
Approved as to form
Th , Assistant City Attorney
P
Page 5 of 5
STATE OF CALIFORNIA
COUNTY OF RIVERSIDE
CITY OF MENIFEE
l, Stephanie Roseen, Deputy City Clerk of the City of Menifee, do hereby certifythat the
foregoing Planning Commission Resolution No. PC19-459 was duly adopted by the Planning
Commission of the City of Menifee at a meeting thereof held on the 11 of September 2019 by
the following vote:
Ayes: Phillips, Thomas, Kanrvin
Noes: Diederich, Madrid
Absent: None
Abstain: None
nie Roseen, CMC