PC16-292Planning Application No. CUP 2015-156 Page 1
CITY OF MENIFEE
CEQA Environmental Checklist Form
1. Project Title: Planning Application No. CUP 2015-156
2.
Lead Agency Name and Address: City of Menifee, Community Development Department,
29714 Haun Road, Menifee, CA 92586 3. Contact person and phone number: Manny Baeza, Contract Planner (951) 723-3742
4.
Project Location: West of I-215 and east of Haun Road between Garbani Road and Wickerd
Road in the City of Menifee, California (See Exhibit 1, Regional Context and Vicinity Map)
A. Total Project Area: 9.85 acres (429,066 square feet); Storage Buildings (225,674 square feet)
Residential Acres: 0 Lots: 0 Units: 0 Projected No. of Residents: 0
Commercial Acres: 0 Lots: 0 Sq. Ft. of Bldg. Area: 0 Est. No. of Employees: 0
Industrial Acres: 9.85 Lots: 2 Sq. Ft. of Bldg. Area: 225,674 Est. No. of Employees: 0
Other: 0
B. Assessor’s Parcel No: 360-350-028-0 & 360-350-029-0
C. Map: Thomas Brothers Riverside County Street Guide 2006 Page 868, Grid E7
D. Section, Township & Range: Section 15, Township 6 South, Range 3 West of the San
Bernardino Base and Meridian
E. Latitude: 33° 39’ 3.67” N Longitude: 117° 10’ 24.30” W
5.
Project Applicant/Owners: Stephen J. Manfredi, M. D.
All Star Super Storage, LLC
P.O. Box 890880
Temecula, California 92589-0880
6. General Plan Land Use Designation: Economic Development Corridor (EDC)
7.
Zoning District: Economic Development Corridor Southern Gateway (EDC-SG)
8. Project Description:
Planning Application No. CUP 2015-156 The project site consists of two parcels. The northern
parcel (Parcel 1) (APN 360-350-028-9) currently consists of the existing All Star Super Storage
facility. Conditional Use Permit No. 2015-156 includes the expansion of the storage facility onto
the southern parcel (Parcel 2) (APN 360-350-029-0) and the redevelopment of approximately 0.08
acres of the northern parcel with new/improved access roads, driveway entrances, and the
reconfiguration of one existing building to provide for a functional collective storage facility. For
purposes of this report, the Project Site consists of the 9.77-acre Parcel 2 and the southern 0.08-
acre portion of Parcel 1 for a total 9.85-acre Project Site.
Conditional Use Permit No. 2015-156 is a proposal for the construction and operation of an
additional 225,674 square feet of storage space in 15 buildings. The project includes seven
regular parking stalls, two loading stalls, and one accessible stall. Vehicular access to the existing
Planning Application No. CUP 2015-156 Page 2
facility on Parcel 1 is provided by two driveways on Haun Road. The proposed project includes the
addition of a 25-foot wide third driveway at the southern portion of Parcel 2. The proposed project
includes the widening and improvement of the existing driveway located at the southern portion of
the existing storage facility to 44 feet.
The project site is bound to the west by Haun Road, to the east by I-215, to the north by the
existing All Star Super Storage facility, and to the south by Louie’s plant nursery.
Landscaping
All project landscaping is subject to the requirements of Menifee Municipal Code Section 9.28.110,
which requires a minimum of ten percent (10%) of the total lot area be landscaped. Parcel 2
consists of 425,714 square feet and includes 85,554 square feet of landscaping (20%). Altogether,
the entire storage facility as a whole consists of 786,665 square feet and will include 123,742
square feet of landscaping (15.7%) along the western, southern, and eastern boundaries of the
facility. Existing and proposed parking is located along the western boundary of the site and will be
surrounded by landscaping. All trees, shrubs, and ground cover are of low to moderate water
demand.
Grading and Drainage
The project site is primarily vacant. The project will include net export of approximately 1,570
cubic yards of soil.
Drainage from the project site will flow from the west to the proposed on-site detention basin at the
eastern portion of the site.
Project Phasing
The project consists of three separate construction phases. Phase 1 will consist of the
construction of the five western buildings (Buildings AA, BB, CC, DD, and EE) and the detention
basin. Phase 2 will consist of the construction of the four central buildings (Buildings FF, GG, HH,
and II) on the site. Phase 3 will consist of construction of the six eastern buildings (Buildings JJ,
KK, LL, MM, NN, and OO). 9. Surrounding Land Uses & Environmental Setting:
The subject site is comprised of two parcels located west of the I-215 and east of Haun Road
between Garbani Road and Wickerd Road. The proposed project site is primarily vacant with 0.08
acres developed with the northern self-storage facility of which the proposed project will be an
expansion of. The southern Parcel 2 has been used for agriculture and is vacant. Ruderal
vegetation and minimal riparian and riverine area occur on the project site. Topographically, the
study area is generally flat. The elevation ranges from 1,490 feet above mean sea level (AMSL) to
a minimum of 1,477 feet AMSL.
The project site and surrounding area contains a mixture of industrial, residential, plant nursery,
and vacant land uses. The site is surrounded by vacant land to the west, the existing self-storage
use to the north, plant nursery to the south, and the I-215 to the east. Table 1 (Surrounding Land
Uses) lists the different uses that are located immediately adjacent to the proposed project site.
Planning Application No. CUP 2015-156 Page 3
Table 1
Surrounding Land Uses
Direction
General Plan
Designation Zoning District Existing Land Use
Project Site Economic Development
Corridor (EDC) EDC-Southern Gateway Vacant
Storage Facility
North Economic Development
Corridor (EDC) EDC-Southern Gateway Storage Facility
South Economic Development
Corridor (EDC) EDC-Southern Gateway Plant Nursery
East
I-215
Economic Development
Corridor (EDC)
I-215 I-215
West Economic Development
Corridor (EDC) EDC-Southern Gateway
Vacant
10.
Other public agencies whose approval is required (e.g., permits, financing approval, or
participation agreement):
Permitting required under Clean Water Act Section 401 and the Santa Ana Regional
Water Quality Control Board (SARWQCB) pursuant to requirements of the National
Pollutant Discharge Elimination System (NPDES) Permit;
Various encroachment and construction permitting from the California Department of
Transportation (Caltrans) District 8 for improvements in the vicinity of Interstate 215.
Permitting may be required by/through the South Coast Air Quality Management District
(SCAQMD) for certain of the Project operations and its associated equipment.
USACOE
CDFW
Planning Application No. CUP 2015-156 Page 4
Insert Figure 1: Project Location (USGS map from Application)
Planning Application No. CUP 2015-156 Page 5
Insert Figure 2: Project Location
Planning Application No. CUP 2015-156 Page 6
Insert Figure 3: Site Plan Concept
Planning Application No. CUP 2015-156 Page 7
ENVIRONMENTAL FACTORS POTENTIALLY AFFECTED:
The environmental factors checked below (x) would be potentially affected by this project, involving at least
one impact that is a “Potentially Significant Impact” as indicated by the checklist on the following pages.
Aesthetics Greenhouse Gas Emissions Population and Housing
Agriculture Resources Hazards & Hazardous Materials Public Services
Air Quality Hydrology/Water Quality Recreation
Biological Resources Land Use/Planning Transportation/Traffic
Cultural Resources Mineral Resources Utilities and Service Systems
Geology/Soils Noise Mandatory Findings of Significance
The environmental factors checked below (x) would be potentially affected by this project, involving at least
one impact that is a “Less than Significant with Mitigation Incorporated” as indicated by the checklist on
the following pages.
Aesthetics Greenhouse Gas Emissions Population and Housing
Agriculture Resources Hazards & Hazardous Materials Public Services
Air Quality Hydrology/Water Quality Recreation
Biological Resources Land Use/Planning Transportation/Traffic
Cultural Resources Mineral Resources Utilities and Service Systems
Geology/Soils Noise Mandatory Findings of Significance
The environmental factors checked below (x) would be potentially affected by this project, involving at least
one impact that is a “Less than Significant” as indicated by the checklist on the following pages.
Aesthetics Greenhouse Gas Emissions Population and Housing
Agriculture Resources Hazards & Hazardous Materials Public Services
Air Quality Hydrology/Water Quality Recreation
Biological Resources Land Use/Planning Transportation/Traffic
Cultural Resources Mineral Resources Utilities and Service Systems
Geology/Soils Noise Mandatory Findings of Significance
The environmental factors checked below (x) would have “No Impact” by this project as indicated by the
checklist on the following pages.
Aesthetics Greenhouse Gas Emissions Population and Housing
Agriculture Resources Hazards & Hazardous Materials Public Services
Air Quality Hydrology/Water Quality Recreation
Biological Resources Land Use/Planning Transportation/Traffic
Cultural Resources Mineral Resources Utilities and Service Systems
Geology/Soils Noise Mandatory Findings of Significance
Planning Application No. CUP 2015-156 Page 8
DETERMINATION: (To be completed by the Lead Agency)
On the basis of this initial evaluation:
I find that the proposed project COULD NOT have a significant effect on the environment, and
a NEGATIVE DECLARATION will be prepared. I find that although the proposed project could have a significant effect on the environment,
there will not be a significant effect in this case because revisions in the project have been
made by or agreed to by the project proponent. A MITIGATED NEGATIVE DECLARATION will
be prepared. I find that the proposed project MAY have a significant effect on the environment, and an
ENVIRONMENTAL IMPACT REPORT is required.
I find that the proposed project MAY have a "potentially significant impact" or "potentially
significant unless mitigated" impact on the environment, but at least one effect 1) has been
adequately analyzed in an earlier document pursuant to applicable legal standards, and 2) has
been addressed by mitigation measures based on the earlier analysis as described on
attached sheets. An ENVIRONMENTAL IMPACT REPORT is required, but it must analyze
only the effects that remain to be addressed. I find that although the proposed project could have a significant effect on the environment,
because all potentially significant effects (a) have been analyzed adequately in an earlier EIR
or NEGATIVE DECLARATION pursuant to applicable standards, and (b) have been avoided or
mitigated pursuant to that earlier EIR or NEGATIVE DECLARATION, including revisions or
mitigation measures that are imposed upon the proposed project, nothing further is required.
Signature
Date
Manny Baeza, Contract Planner
Printed Name
Planning Application No. CUP 2015-156 Page 9
EVALUATION OF ENVIRONMENTAL IMPACTS:
1) A brief explanation is required for all answers except "No Impact" answers that are adequately
supported by the information sources a lead agency cites in the parentheses following each question.
A "No Impact" answer is adequately supported if the referenced information sources show that the
impact simply does not apply to projects like the one involved (e.g., the project falls outside a fault
rupture zone). A "No Impact" answer should be explained where it is based on project-specific factors
as well as general standards (e.g., the project will not expose sensitive receptors to pollutants, based
on a project-specific screening analysis).
2) All answers must take account of the whole action involved, including off-site as well as on-site,
cumulative as well as project-level, indirect as well as direct, and construction as well as operational
impacts.
3) Once the lead agency has determined that a particular physical impact may occur, then the checklist
answers must indicate whether the impact is potentially significant, less than significant with
mitigation, or less than significant. "Potentially Significant Impact" is appropriate if there is substantial
evidence that an effect may be significant. If there are one or more "Potentially Significant Impact"
entries when the determination is made, an EIR is required.
4) "Negative Declaration: Less Than Significant With Mitigation Incorporated" applies where the
incorporation of mitigation measures has reduced an effect from "Potentially Significant Impact" to a
"Less Than Significant Impact." The lead agency must describe the mitigation measures, and briefly
explain how they reduce the effect to a less than significant level (mitigation measures from "Earlier
Analyses," as described in (5) below, may be cross-referenced).
5) Earlier analyses may be used where, pursuant to the tiering, program EIR, or other CEQA process,
an effect has been adequately analyzed in an earlier EIR or negative declaration. Section
15063(c)(3)(D). In this case, a brief discussion should identify the following:
a) Earlier Analysis Used. Identify and state where they are available for review.
b) Impacts Adequately Addressed. Identify which effects from the above checklist were within
the scope of and adequately analyzed in an earlier document pursuant to applicable legal
standards, and state whether such effects were addressed by mitigation measures based on
the earlier analysis.
c) Mitigation Measures. For effects that are "Less than Significant with Mitigation Measures
Incorporated," describe the mitigation measures which were incorporated or refined from the
earlier document and the extent to which they address site-specific conditions for the project.
6) Lead agencies are encouraged to incorporate into the checklist references to information sources for
potential impacts (e.g., general plans, zoning ordinances). Reference to a previously prepared or
outside document should, where appropriate, include a reference to the page or pages where the
statement is substantiated.
7) Supporting Information Sources: A source list should be attached, and other sources used or
individuals contacted should be cited in the discussion.
8) This is only a suggested form, and lead agencies are free to use different formats; however, lead
agencies should normally address the questions from this checklist that are relevant to a project's
environmental effects in whatever format is selected.
9) The explanation of each issue should identify:
a) the significance criteria or threshold, if any, used to evaluate each question; and
b) the mitigation measure identified, if any, to reduce the impact to less than significance.
Planning Application No. CUP 2015-156 Page 10
Issues:
I. AESTHETICS
Potentially
Significant
Impact
Less Than
Significant with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
Would the project: a) Have a substantial adverse effect on a
scenic vista?
b) Substantially damage scenic resources,
including, but not limited to, trees, rock
outcroppings, and historic buildings within
view from a state scenic highway?
c) Substantially degrade the existing visual
character or quality of the site and its
surroundings?
d) Create a new source of substantial light
or glare which would adversely affect day
or nighttime views in the area?
Sources: Menifee General Plan, Exhibit C-8, “Scenic Highways” and Riverside County General Plan
Figure 5, “Mt. Palomar Nighttime Lighting Policy”; State of California, Department of Transportation,
California State Scenic Highway Mapping System; Ordinance No. 655 (Regulating Light Pollution); City
of Menifee Ordinance 2009-24 (Dark Sky)
Applicable General Plan Policies:
Goal C-6: Scenic highway corridors that are preserved and protected from change which would
diminish the aesthetic value of lands adjacent to the designated routes.
Policy C-6.1: Design developments within designated scenic highway corridors to balance the
objectives of maintaining scenic resources with accommodating compatible land uses.
Policy C-6.4: Incorporate riding, hiking, and bicycle trails and other compatible public recreational
facilities within scenic corridors.
Policy C-6.5: Ensure that the design and appearance of new landscaping, structures, equipment,
signs, or grading within eligible county scenic highway corridors are compatible with the
surrounding scenic setting or environment.
Goal CD-3: Projects, developments, and public spaces that visually enhance the character of the
community and are appropriately buffered from dissimilar land uses so that differences in type and
intensity do not conflict.
Policy CD-3.1: Preserve positive characteristics and unique features of a site during the design
and development of a new project; the relationship to scale and character of adjacent uses should
be considered.
Policy CD-3.2: Maintain and incorporate the City's natural amenities, including its hillsides,
Planning Application No. CUP 2015-156 Page 11
indigenous vegetation, and rock outcroppings, within proposed projects.
Policy CD-3.3: Minimize visual impacts of public and private facilities and support structures
through sensitive site design and construction. This includes, but is not limited to: appropriate
placement of facilities; undergrounding, where possible; and aesthetic design (e.g., cell tower
stealthing).
Policy CD-3.5: Design parking lots and structures to be functionally and visually integrated and
connected; off-street parking lots should not dominate the street scene.
Policy CD-3.6: Locate site entries and storage bays to minimize conflicts with adjacent residential
neighborhoods.
Policy CD-3.7: Consider including public art at key gateways, major projects, and public gathering
places.
Policy CD-3.8: Design retention/detention basins to be visually attractive and well integrated with
any associated project and with adjacent land uses.
Policy CD-3.9: Utilize Crime Prevention through Environmental Design (CPTED) techniques and
defensible space design concepts to enhance community safety.
Policy CD-3.10: Employ design strategies and building materials that evoke a sense of quality and
permanence.
Policy CD-3.11 Provide special building-form elements, such as towers and archways, and other
building massing elements to help distinguish activity nodes and establish landmarks within the
community.
Policy CD-3.12: Utilize differing but complementary forms of architectural styles and designs that
incorporate representative characteristics of a given area.
Policy CD-3.13: Utilize architectural design features (e.g., windows, columns, offset roof planes,
etc.) to vertically and horizontally articulate elevations in the front and rear of residential buildings.
Policy CD-3.14: Provide variations in color, texture, materials, articulation, and architectural
treatments. Avoid long expanses of blank, monotonous walls or fences.
Policy CD-3.15: Require property owners to maintain structures and landscaping to high standards
of design, health, and safety.
Policy CD-3.16: Avoid use of long, blank walls in industrial developments by breaking them up with
vertical and horizontal facade articulation achieved through stamping, colors, materials,
modulation, and landscaping.
Policy CD-3.17: Encourage the use of creative landscape design to create visual interest and
reduce conflicts between different land uses.
Policy CD-3.18: Require setbacks and other design elements to buffer residential units to the
extent possible from the impacts of abutting roadway, commercial, agricultural, and industrial uses.
Policy CD-3.19: Design walls and fences that are well integrated in style with adjacent structures
Planning Application No. CUP 2015-156 Page 12
and terrain and utilize landscaping and vegetation materials to soften their appearance.
Policy CD-3.20: Avoid the blocking of public views by solid walls.
Policy CD-3.21: Use open space, greenways, recreational lands, and water courses as community
separators.
Policy CD-3.22: Incorporate visual buffers, including landscaping, equipment and storage area
screening, and roof treatments, on properties abutting either Interstate 215 or residentially
designated property.
Goal CD-4: Recognize, preserve, and enhance the aesthetic value of the City's enhanced
landscape corridors and scenic corridors.
Policy CD-4.1: Create unifying streetscape elements for enhanced landscape streets, including
coordinated streetlights, landscaping, public signage, street furniture, and hardscaping.
Policy CD-4.2: Design new and, when necessary, retrofit existing streets to improve walkability,
bicycling, and transit integration; strengthen connectivity; and enhance community identity through
improvements to the public right-of-way such as sidewalks, street trees, parkways, curbs, street
lighting, and street furniture.
Policy CD-4.3: Apply special paving at major intersections and crosswalks along enhanced
corridors to create a visual focal point and slow traffic speeds.
Policy CD-4.4: Frame views along streets through the use of wide parkways and median
landscaping.
Policy CD-4.5: Orient new streets to maximize the view of open space, parks, mountains, and built
landmarks where possible.
Policy CD-4.6: Prohibit outdoor advertising devices (billboards, but not on-site signs identifying a
business on the same property as the sign) within 660 feet of the nearest edge of the right-of-way
line of all scenic corridors as depicted on Circulation Element Exhibit C-8 and the entire length of I-
215; City Community Information Signs or other City-sponsored signs are not subject to this
requirement.
Policy CD-4.7: Design new landscaping, structures, equipment, signs, or grading within the scenic
corridors for compatibility with the surrounding scenic setting or environment.
Policy CD-4.8: Preserve and enhance view corridors by undergrounding and/or screening new or
relocated electric or communication distribution lines, which would be visible from the City's scenic
highway corridors.
Policy CD-4.9: Require specialized design review for development along scenic corridors,
including but not limited to, building height restrictions, setback requirements, and site-orientation
guidelines.
Analysis of Project Effect and Determination of Significance:
a) Less than Significant Impact. Scenic vistas can be impacted by development in two ways. First, a
structure may be constructed that blocks the view of a vista. Second, the vista itself may be altered
Planning Application No. CUP 2015-156 Page 13
(i.e., development on a scenic hillside). The natural mountainous setting of the Menifee area is critical
to its overall visual character, and provides scenic vistas for the community. Topography and a lack of
dense vegetation or urban development offer scenic views throughout the City, including to and from
hillside areas. Scenic features include gently sloping alluvial fans, rugged mountains and steep slopes,
mountain peaks and ridges, rounded hills with boulder outcrops, farmland and open space. Scenic
vistas provide views of these features from public spaces. Many of the scenic resources are outside
the City limits and beyond the planning area boundary. Scenic views from Menifee include the San
Jacinto Mountains to the northeast and east; the San Bernardino Mountains to the north; the San
Gabriel Mountains to the northwest; and the Santa Ana Mountains to the west and southwest. The
Canyon Lake Reservoir is adjacent to the City’s western boundary.
The project site is located on a primarily vacant, previously disturbed site located immediately west of I-
215, within a suburbanized area comprised of residential, industrial use, vacant land, and surface
street features. This site is not considered to be within or to comprise a portion of a scenic vista.1
Although the portion of the I-215 that is adjacent to the project site is not designated as or eligible for
designation as a scenic highway by the California Department of Transportation, the City of Menifee
General Plan Community Design Element and Circulation Element designate the I-215 corridor as a
Scenic Corridor and Enhanced Landscape Corridor.2 The project site is located on the west side of the
I-215. The proposed project includes a vegetated water quality detention basin and landscaping on the
east side of the project site and storage buildings will be of the same size and scale as the existing
storage facility to the north. Therefore, the proposed project is consistent with General Plan Community
Design Policies. Impacts will be less than significant.
b) No Impact. The project is not adjacent to an officially designated state scenic highway as identified
by the California Scenic Highway Mapping System; however, the City of Menifee General Plan
Community Design Element and Circulation Element designate the I-215 corridor as a Scenic Corridor
and Enhanced Landscape Corridor.3 4 The project site is located in a suburbanized area comprised of
residential, industrial use, vacant land, and surface street features, and contains no scenic resources
such as rock outcroppings, significant trees, or historical buildings. Therefore, no impact to scenic
resources will occur.
c) Less Than Significant Impact. Development of the proposed project could result in a significant
impact if it resulted in substantial degradation of the existing visual character or quality of the site and
its surroundings. Degradation of visual character or quality is defined by substantial changes to the
existing site appearance through construction of structures such that they are poorly designed or
conflict with the site’s existing surroundings.
Construction of the proposed project will result in short-term impacts to the existing visual character
and quality of the area. Construction activities will require the use of equipment and storage of
materials within the project site. However, construction activities are temporary and will not result in
any permanent visual impact. Parcel 2 of the project site has been previously disturbed by agricultural
uses and is currently vacant. The southern 0.08-acre portion of Parcel 1 is currently developed with the
existing All Star Super Storage facility. The area surrounding the proposed project site is an area
comprised of industrial and vacant land uses. The site is surrounded by vacant land to the west,
existing self-storage use to the north of which the proposed project will be an expansion of, plant
nursery to the south, and the I-215 to the east.
Upon project completion, the proposed project will consist of 15 additional self-storage buildings. The
project will also include associated street, utility, parking, and landscaping improvements. All buildings
will be consistent with City design and building height requirements and limitations. The proposed
project will change the visual character of the project site by adding structures and landscaping;
however, the development will blend with the characteristics of the adjacent storage facility to the north
and the existing plant nursery to the south. With incorporation of the specified design features, the
project will have less than significant impacts on the visual character of the site and its surroundings.
Planning Application No. CUP 2015-156 Page 14
d) Less Than Significant Impact. Excessive or inappropriately directed lighting can adversely impact
nighttime views by reducing the ability to see the night sky and stars. Glare can be caused from
unshielded or misdirected lighting sources. Reflective surfaces (i.e., polished metal) can also cause
glare. Impacts associated with glare range from simple nuisance to potentially dangerous situations
(i.e., if glare is directed into the eyes of motorists). There are lighting sources adjacent to this site,
including free-standing street lights, light fixtures on buildings, vehicle headlights, and traffic lights. The
proposed project will include outdoor lighting associated with security light. Lighting associated with the
project would not be directed towards the adjacent plant nursery to the south, the vacant land use to
the west, or the I-215 to the east. The proposed project is the expansion of the existing storage use to
the north and proposed lighting will be in character and work in conjunction with existing lighting on the
northern property.
Chapter 6.01 of the Menifee Municipal Code (Dark Sky; Light Pollution) indicates that low-pressure
sodium lamps are the preferred illuminating source and that all non-exempt outdoor light fixtures shall
be shielded. A maximum of 8,100 total lumens per acre or per parcel if less than one acre shall be
allowed. When lighting is “allowed”, it must be fully shielded if feasible and partially shielded in all other
cases, and must be focused to minimize spill light into the night sky and onto adjacent properties
(Section 6.01.040). The project will be conditioned that, prior to the issuance of building permits, all
new construction which introduces light sources be required to have shielding or other light pollution
limiting characteristics such as hood or lumen restrictions.
The City of Menifee General Plan Community Design Element includes goals that encourage attractive
landscaping, lighting, and signage that conveys a positive image of the community (CD-6) and that limit
light leakage and spillage that may interfere with the operations of the Palomar Observatory (Goal CD-
6.5). Lighting proposed by the project complies with Menifee Municipal Code Section 6.01 and General
Plan goals. Accordingly, the project will have a less than significant impact on interfering with the
nighttime use of the Mt. Palomar Observatory.
Sources of daytime glare are typically concentrated in commercial areas and are often associated with
retail uses. Glare results from development and associated parking areas that contain reflective
materials such as glass, highly polished surfaces, and expanses of pavement. Exterior paint colors and
materials will be non-reflective. There are no exposed metal or other materials proposed that could
result in a substantial amount of glare. Given the minimal use of glare-inducing materials in the design
of the proposed buildings for the project, reflective glare impacts will be less than significant.
Planning Application No. CUP 2015-156 Page 15
II. AGRICULTURE AND FORESTRY
RESOURCES:
Potentially
Significant
Impact
Less Than
Significant with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
In determining whether impacts to agricultural resources are significant environmental effects, lead
agencies may refer to the California Agricultural Land Evaluation and Site Assessment Model (1997)
prepared by the California Dept. of Conservation as an optional model to use in assessing impacts on
agriculture and farmland. In determining whether impacts to forest resources, including timberland, are
significant environmental effects, lead agencies may refer to information compiled by the California
Department of Forestry and Fire Protection regarding the state’s inventory of forest land, including the
Forest and Range Assessment Project and the Forest Legacy Assessment project; and forest carbon
measurement methodology provided in Forest Protocols adopted by the California Air Resources
Board. Would the project: a) Convert Prime Farmland, Unique
Farmland, or Farmland of Statewide
Importance (Farmland), as shown on the
maps prepared pursuant to the Farmland
Mapping and Monitoring Program of the
California Resources Agency, to non-
agricultural use?
b) Conflict with existing zoning for
agricultural use, or a Williamson Act
contract?
c) Conflict with existing zoning for, or
cause rezoning of, forest land (as defined
in Public Resources Code section
12220(g)), timberland (as defined in Public
Resources Code section 4526), or
timberland zoned Timberland Production
(as defined in Government Code section
51104(g))?
d) Result in the loss of forest land or
conversion of forest land to non-forest
use?
e) Involve other changes in the existing
environment which, due to their location or
nature, could result in conversion of
Farmland, to non-agricultural use or
conversion of forest land to non-forest
use?
Sources: State of California, Department of Conservation, Division of Land Resource Protection,
Farmland Mapping and Monitoring Program. Riverside County Important Farmland 2008, Sheet 1 of 3,
map published September 2009;
Applicable General Plan Policies:
Goal OSC-6: High value agricultural lands available for long-term agricultural production in limited
areas of the City.
Planning Application No. CUP 2015-156 Page 16
Policy OSC-6.1: Protect both existing farms and sensitive uses around them as agricultural acres
transition to more developed land uses.
Analysis of Project Effect and Determination of Significance:
a) Less Than Significant Impact. The proposed project is located on a primarily vacant site
immediately west of I-215, within a suburbanized area comprised of residential, industrial use, vacant
land, and surface street features. The map of Important Farmland in California (2012) prepared by the
Department of Conservation does not identify the proposed project site as being Prime Farmland,
Unique Farmland, or Farmland of Statewide Importance.5 However, the project site is designated as
Farmland of Local Importance by the FMMP.6 The project site is designated for Economic
Development Corridor in the City’s General Plan and is zoned Economic Development Corridor –
Southern Gateway (EDC-SG) . The City is focusing on developing land in an economically productive
way that will serve the growing population. Thus, Menifee’s future development emphasizes mixed-
use, commercial, industrial, and residential projects rather than supporting the continuation of
agricultural uses, which are becoming less economically viable.7 Therefore, impacts to Farmland will
be less than significant.
b) No Impact. No Williamson Act Contracts are active for the proposed project site.8 The project site is
zoned EDC-SG , which is for business park and commercial uses. Therefore, there will be no conflict
with existing zoning for agricultural use or a Williamson Act Contract. No impact will occur.
c) No Impact. Public Resources Code Section 12220(g) identifies forest land as land that can support
10-percent native tree cover of any species, including hardwoods, under natural conditions, and that
allows for management of one or more forest resources, including timber, aesthetics, fish and wildlife,
biodiversity, water quality, recreation, and other public benefits. The project site and surrounding
properties are not currently being managed or used for forest land as identified in Public Resources
Code Section 12220(g). The project site is vacant and mostly unvegetated. Therefore, development of
this project will have no impact to any timberland zoning.
d) No Impact. The proposed project site is primarily vacant and mostly unvegetated; thus, there will be
no loss of forest land or conversion of forest land to non-forest use as a result of this project. No impact
will occur.
e) Less than Significant Impact. The proposed project is located on a primarily vacant site west of I-
215, within a suburbanized area comprised of residential, industrial use, vacant land, and surface
street features. The project site is classified as Farmland of Local Importance; however, the site is
designated for economic development in the City’s General Plan and zoned for industrial use. The site
is not currently being used for agriculture. Moreover, the City is focused on developing land in an
economically productive way that will serve the growing population. Thus, Menifee’s future
development emphasizes mixed-use, commercial, industrial, and residential projects rather than
supporting the continuation of agricultural uses, which are becoming less economically viable.9
Development of this project will not change the existing environment in a manner that will result in the
conversion of agricultural land to non-agricultural land or forest land to non-forest land. Less than
significant impacts will occur.
Planning Application No. CUP 2015-156 Page 17
III. AIR QUALITY Potentially
Significant
Impact
Less Than
Significant with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
Where available, the significance criteria established by the applicable air quality management or air
pollution control district may be relied upon to make the following determinations. Would the project: a) Conflict with or obstruct implementation
of the applicable air quality plan?
b) Violate any air quality standard or
contribute substantially to an existing or
projected air quality violation?
c) Result in a cumulatively considerable
net increase of any criteria pollutant for
which the project region is non-attainment
under an applicable federal or state
ambient air quality standard (including
releasing emissions, which exceed
quantitative thresholds for ozone
precursors)?
d) Expose sensitive receptors to
substantial pollutant concentrations?
e) Create objectionable odors affecting a
substantial number of people?
Sources: South Coast Air Quality Management District, CEQA Air Quality Handbook, 1993;
Applicable General Plan Policies:
Goal OSC-9: Reduced impacts to air quality at the local level by minimizing pollution and particulate
matter.
Policy OSC-9.1: Meet state and federal clean air standards by minimizing particulate matter
emissions from construction activities.
Policy OSC-9.2: Buffer sensitive land uses, such as residences, schools, care facilities, and
recreation areas from major air pollutant emission sources, including freeways, manufacturing,
hazardous materials storage, wastewater treatment, and similar uses.
Policy OSC-9.3: Comply with regional, state, and federal standards and programs for control of all
airborne pollutants and noxious odors, regardless of source.
Policy OSC-9.5: Comply with the mandatory requirements of Title 24 Part 11 of the California
Building Standards Code (CALGreen) and Title 24 Part 6 Building and Energy Efficiency
Standards.
Planning Application No. CUP 2015-156 Page 18
Analysis of Project Effect and Determination of Significance:
a) Less than Significant Impact. A significant impact could occur if the proposed project conflicts with
or obstructs implementation of the South Coast Air Basin 2012 Air Quality Management Plan. Conflicts
and obstructions that hinder implementation of the AQMP can delay efforts to meet attainment
deadlines for criteria pollutants and maintaining existing compliance with applicable air quality
standards. Pursuant to the methodology provided in Chapter 12 of the 1993 SCAQMD CEQA Air
Quality Handbook, consistency with the South Coast Air Basin 2012 Air Quality Management Plan
(AQMP) is affirmed when a project (1) does not increase the frequency or severity of an air quality
standards violation or cause a new violation and (2) is consistent with the growth assumptions in the
AQMP.10 Consistency review is presented below:
(1) The proposed project will result in short-term construction (with mitigation incorporated) and
long-term pollutant emissions that are less than the CEQA significance emissions thresholds
established by the SCAQMD, as demonstrated by Section III et seq of this report; therefore, the
project will not result in an increase in the frequency or severity of any air quality standards
violation and will not cause a new air quality standard violation.
(2) The CEQA Air Quality Handbook indicates that consistency with AQMP growth assumptions
must be analyzed for new or amended General Plan Elements, Specific Plans, and significant
projects. Significant projects include airports, electrical generating facilities, petroleum and gas
refineries, designation of oil drilling districts, water ports, solid waste disposal sites, and offshore
drilling facilities. This project does not involve a General Plan Amendment and is not considered
a significant project.
According to the Air Quality Analysis prepared for the proposed project and the consistency analysis
presented above, the proposed project will not conflict with the AQMP; less than significant impacts will
occur.
b) Less Than Significant Impact with Mitigation Incorporated. A project may have a significant
impact if project-related emissions exceed federal, state, or regional standards or thresholds, or if
project-related emissions substantially contribute to existing or project air quality violations. The
proposed project is located within the South Coast Air Basin, where efforts to attain state and federal
air quality standards are governed by the South Coast Air Quality Management District (SCAQMD).
Both the state of California (state) and the federal government have established health-based ambient
air quality standards (AAQS) for seven air pollutants (known as ‘criteria pollutants’). These pollutants
include ozone (O3), carbon monoxide (CO), nitrogen dioxide (NO2), sulfur dioxide (SO2), inhalable
particulate matter with a diameter of 10 microns or less (PM10), fine particulate matter with a diameter
of 2.5 microns or less (PM2.5), and lead (Pb). The state has also established AAQS for additional
pollutants. The AAQS are designed to protect the health and welfare of the populace within a
reasonable margin of safety. Where the state and federal standards differ, California AAQS are more
stringent than the national AAQS.
Air pollution levels are measured at monitoring stations located throughout the air basin. Areas that are
in nonattainment with respect to federal or state AAQS are required to prepare plans and implement
measures that will bring the region into attainment. Table 2 (South Coast Air Basin Attainment Status –
Riverside County) summarizes the attainment status in the project area for the criteria pollutants.
Discussion of potential impacts related to short-term construction impacts and long-term area source
and operational impacts are presented below.
Planning Application No. CUP 2015-156 Page 19
Table 2
South Coast Air Basin Attainment Status – Riverside County
Pollutant Federal State
O3 (1-hr) N/A Nonattainment
O3 (8-hr) Nonattainment Nonattainment
PM10 Nonattainment Nonattainment
PM2.5 Nonattainment Nonattainment
CO Attainment Attainment
NO2 Attainment Attainment
SO2 Attainment Attainment
PB Attainment Nonattainment
Source: CalEPA Air Resources Board. State and National Area Designation Maps. 2015.
Construction Emissions
The California Emissions Estimator Model (CalEEMod) version 2013.2.2 was utilized to estimate
emissions from the proposed construction activities (see Appendix A, Air Quality Modeling Data). The
project consists of three separate construction phases.
The project consists of three separate construction phases. Phase 1 will consist of the construction of
the five western buildings (Buildings AA, BB, CC, DD, and EE) and the detention basin. Phase 2 will
consist of the construction of the four central buildings (Buildings FF, GG, HH, and II) on the site.
Phase 3 will consist of construction of the six eastern buildings (Buildings JJ, KK, LL, MM, NN, and
OO).
To provide a worst case analysis, CalEEMod was run assuming that all proposed buildings will be
constructed as part of one phase. CalEEMod default construction phase lengths were utilized with the
exception of demolition. The proposed project includes the demolition of approximately 2,200 square
feet of the existing structure on Parcel 1. The total area that will be disturbed on Parcel 1 is less than
one acre. Therefore, CalEEMod default demolition length and construction equipment usage for areas
less than one acre have been utilized. CalEEMod defaults were utilized for all other construction
equipment and construction parameters in the model. The maximum (summer or winter) results of the
analysis are summarized in Table 3 (Unmitigated Maximum Daily Construction Emissions (lbs/day)).
The model indicates that construction of the proposed project will result in excessive emissions of
volatile organic chemicals (identified as reactive organic gases) associated with interior and exterior
coating activities.
Table 3
Unmitigated Maximum Daily Construction Emissions (lbs/day)
Year ROG NOX CO SO2 PM10 PM2.5
Summer 497.80 54.73 42.27 0.07 10.19 6.63
Winter 497.80 54.74 42.18 0.07 10.19 6.63
SCAQMD Threshold 75 100 550 150 150 55
Potential Impact? Yes No No No No No
Source: MIG, 2016
Note: Volatile organic compounds are measured as reactive organic compounds
To compensate for excessive VOC emissions from coating activities, the model includes use of a
Planning Application No. CUP 2015-156 Page 20
maximum zero g/l VOC content for interior coatings and 50 g/l VOC content for exterior coatings. Use
of low-VOC coatings during construction activities will reduce VOC emissions to 25.3 in winter and
summer months, less than the threshold established by SCAQMD. The requirement of use of low-VOC
coatings has been included as Mitigation Measure AQ-1 below. The results of the CalEEMod outputs
with mitigation incorporated are summarized in Table 4 (Mitigated Maximum Daily Construction
Emissions for ROG (lbs/day)) below.
Table 4
Mitigated Maximum Daily Construction Emissions for ROG (lbs/day)
Source ROG
Summer 25.33
Winter 25.34
Threshold 75
Substantial? No
Source: MIG, 2016
Operational Emissions
Long-term criteria air pollutant emissions will result from the operation of the proposed project. Long-
term emissions are categorized as area source emissions, energy demand emissions, and operational
emissions. Operational emissions will result from automobile and other vehicle sources associated
with daily trips to and from the proposed project. CalEEMod was utilized to estimate mobile source
emissions. Trip generation is based on the project traffic analysis prepared by TJW Engineering, Inc.11
Area source emissions are the combination of many emission sources that include use of outdoor
landscape maintenance equipment, use of consumer products such as cleaning products, and periodic
repainting of the proposed structure. Energy demand emissions result from use of electricity and
natural gas. Emissions from area sources were estimated using CalEEMod using program default
values for area and energy demand emissions. Operational emissions are summarized in Table 5
(Long-Term Daily Emissions (lbs/day)). Long-term emissions will not exceed the daily thresholds
established by SCAQMD; impacts will be less than significant.
Table 5
Long-Term Daily Emissions (lbs/day)
Source ROG NOX CO SO2 PM10 PM2.5
Summer 11.89 2.26 8.64 0.03 1.70 0.48
Winter 11.91 2.37 8.36 0.02 1.70 0.48
Threshold 55 55 550 150 150 55
Potential Impact? No No No No No No
Source: MIG, 2016
Note: Volatile organic compounds are measured as reactive organic compounds
Mitigation Measure
AQ-1 Prior to issuance of building permits, the project proponent shall submit, to the satisfaction of
the City of Menifee Planning Division of the Community Development Department, a Coating
Restriction Plan (CRP), consistent with South Coast Air Quality Management District
(SCAQMD) guidelines and a letter agreeing to include in any construction contracts and/or
subcontracts a requirement that the contractors adhere to the requirements of the CRP. The
CRP measures shall be implemented to the satisfaction of the Planning Division. These may
include the following:
• The volatile organic compounds (VOC) of proposed architectural coatings shall not exceed
0 g/l for interior applications.
• The volatile organic compounds (VOC) of proposed architectural coatings shall not exceed
Planning Application No. CUP 2015-156 Page 21
50 g/l for exterior applications.
This measure shall conform to the performance standard that emissions of volatile organic
compounds from application of interior or exterior coatings shall not exceed the daily emissions
thresholds established by the South Coast Air Quality Management District. The CRP shall
specify use of High-Volume, Low Pressure (HVLP) spray guns for application of coatings.
c) Less Than Significant Impact. Cumulative short-term, construction-related emissions and long-
term, operational emissions from the project would not contribute considerably to any potential
cumulative air quality impact because short-term project and operational emissions would not exceed
any SCAQMD daily threshold. As is required of the proposed project, other concurrent construction
projects and operations in the region would be required to implement standard air quality regulations
and mitigation pursuant to State CEQA requirements. Such measures include compliance with
SCAQMD Rule 403, which requires daily watering to limit dust and particulate matter emissions.
Impacts would be less than significant.
d) Less Than Significant Impact. Sensitive receptors are those segments of the population that are
most susceptible to poor air quality such as children, the elderly, the sick, and athletes who perform
outdoors. Land uses associated with sensitive receptors include residences, schools, playgrounds,
childcare centers, outdoor athletic facilities, long-term health care facilities, rehabilitation centers,
convalescent centers, and retirement homes. The nearest land uses that are considered sensitive
receptors are existing single-family residential dwelling units located approximately 0.15 miles south of
the project site. The proposed development will not generate toxic pollutant emissions.
Localized Significance Thresholds
As part of SCAQMD’s environmental justice program, attention has recently been focusing more on the
localized effects of air quality. Although the region may be in attainment for a particular criteria
pollutant, localized emissions from construction activities coupled with ambient pollutant levels can
cause localized increases in criteria pollutant that exceed national and/or State air quality standards.
Construction-related criteria pollutant emissions and potentially significant localized impacts were
evaluated pursuant to the SCAQMD Final Localized Significance Thresholds Methodology. This
methodology provides screening tables for one- through five-acre project scenarios, depending on the
amount of site disturbance during a day using the Fact Sheet for equipment usage in CalEEMod. Daily
oxides of nitrogen (NOX), carbon monoxide (CO), and particulate matter (PM10 and PM2.5) emissions
will occur during construction of the project, grading of the project site, and paving of facility parking
area and drive aisles. Table 6 (Localized Significance Threshold Analysis) summarize on- and off-site
emissions as compared to the local thresholds established for Source Receptor Area (SRA) 24 (Perris
Valley). Based on the use of four tractors and three dozers during site preparation activities, a 3.5-acre
threshold will be used (using linear regression). A 500-meter receptor distance was used to reflect the
proximity of sensitive receptors; however, the nearest residential uses are located greater than 800
feet (0.15 miles) to the south of the project site. Note that particulate matter emissions account for daily
watering required by SCAQMD Rule 403 (three times per day for a 61 percent reduction in fugitive
dust). Emissions from construction activities will not exceed any localized threshold.
Planning Application No. CUP 2015-156 Page 22
Table 6
Localized Significance Threshold Analysis (lbs/day)
Phase CO NOX PM10 PM2.5
Demolition 8.69 11.22 0.89 0.78
Site Preparation 41.11 54.63 9.98 6.58
Grading 26.08 38.45 4.75 3.34
Building Construction 18.51 28.51 1.97 1.85
Paving 14.73 20.30 1.14 1.05
Architectural Coating 1.87 2.19 0.17 0.17
Threshold 20,719 732 196.3 97.9
Potentially Substantial? No No No No
Operation-related LSTs become of concern when there are substantial on-site stationary sources that
could impact surrounding receptors. The proposed project does not include such on-site operations;
therefore, impacts related to operational LSTs will not occur.
Carbon Monoxide Hotspots
A carbon monoxide (CO) hotspot is an area of localized CO pollution that is caused by severe vehicle
congestion on major roadways, typically near intersections. CO hotspots have the potential for violation
of state and federal CO standards at study area intersections, even if the broader Basin is in
attainment for federal and state levels. The potential for violation of state and federal CO standards at
study area intersections and exposure to sensitive receptors at those intersections is addressed using
the methodology outlined in the California Department of Transportation (Caltrans) Project-Level
Carbon Monoxide Protocol (CO Protocol). In general, SCAQMD and the California Department of
Transportation Project-Level Carbon Monoxide Protocol recommend analyzing CO hotspots when a
project has the potential to result in higher CO concentrations within the region and increase traffic
congestion at an intersection operating at level of service (LOS) D or worse by more than two percent.
Caltrans notes that because of the age of the assumptions used in the screening procedures and the
obsolete nature of the modeling tools utilized to develop the screening procedures in the Protocol, they
are no longer accepted. More recent screening procedures based on more current methodologies
have been developed. The Sacramento Metropolitan Air Quality Management District (SMAQMD)
developed a screening threshold in 2011, which states that any project involving an intersection
experiencing 31,600 vehicles per hour or more will require detailed analysis. In addition, the Bay Area
Air Quality Management District developed a screening threshold in 2010, which states that any project
involving an intersection experiencing 44,000 vehicles per hour would require detailed analysis. The
proposed project’s operations would not involve an intersection experiencing this level of traffic;
therefore, the proposed project passes the screening analysis and impacts are deemed less than
significant. Furthermore, the project does not meet any of the special conditions that may be a cause of
concern for air quality impacts such as urban street canyons, high percentages of gasoline-powered
heavy duty trucks in the project vehicle mix, high cold starts coupled with high traffic volumes, location
near a significant stationary source of CO emissions, or location with a high CO background. The
proposed project is satisfactory pursuant to the CO Protocol because it will not result in a CO hotspot
and no additional analysis is needed. Impacts to sensitive receptors due to localized carbon monoxide
emissions will be less than significant.
e) No Impact. According to the CEQA Air Quality Handbook, land uses associated with odor
complaints include agricultural operations, wastewater treatment plants, landfills, and certain industrial
operations (such as manufacturing uses that produce chemicals, paper, etc.). Odors are typically
associated with industrial projects involving the use of chemicals, solvents, petroleum products, and
other strong-smelling elements used in manufacturing processes, as well as sewage treatment
facilities and landfills. The proposed development does not include any of the above noted uses or
process; no impact would occur.
Planning Application No. CUP 2015-156 Page 23
IV. BIOLOGICAL RESOURCES Potentially
Significant
Impact
Less Than
Significant with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
Would the project: a) Have a substantial adverse effect, either
directly or through habitat modifications, on
any species identified as a candidate,
sensitive, or special status species in local
or regional plans, policies, or regulations,
or by the California Department of Fish and
Wildlife or U.S. Fish and Wildlife Service?
b) Have a substantial adverse effect on
any riparian habitat or other sensitive
natural community identified in local or
regional plans, policies, regulations or by
the California Department of Fish and
Wildlife or US Fish and Wildlife Service?
c) Have a substantial adverse effect on
federally protected wetlands as defined by
Section 404 of the Clean Water Act
(including, but not limited to, marsh, vernal
pool, coastal, etc.) through direct removal,
filling, hydrological interruption, or other
means?
d) Interfere substantially with the
movement of any native resident or
migratory fish or wildlife species or with
established native resident or migratory
wildlife corridors, or impede the use of
native wildlife nursery sites?
e) Conflict with any local policies or
ordinances protecting biological resources,
such as a tree preservation policy or
ordinance?
f) Conflict with the provisions of an adopted
Habitat Conservation Plan, Natural
Community Conservation Plan, or other
approved local, regional, or state habitat
conservation plan?
Sources: Menifee General Plan; Riverside County Transportation and Land Management Agency,
Western Riverside County Multiple Species Habitat Conservation Plan (MSHCP), Approved June 7,
2003; Glenn Lukos Associates, Inc, Biological Technical Report for the All Star Super Storage Project
2015-156, September 22, 2015; Glenn Lukos Associates, Inc., Determination of Biologically Equivalent
or Superior Preservation Analysis for Impacts to MSHCP Riparian/Riverine Areas, All Star Self Storage
Project 2015-156, September 22, 2015
Planning Application No. CUP 2015-156 Page 24
Applicable General Plan Policies:
Goal OSC-8: Protected biological resources, especially sensitive and special status wildlife species
and their natural habitats.
Policy OSC-8.1: Work to implement the Western Riverside County Multiple Species Habitat
Conservation Plan in coordination with the Regional Conservation Authority.
Policy OSC-8.2: Support local and regional efforts to evaluate, acquire, and protect natural habitats
for sensitive, threatened, and endangered species occurring in and around the City.
Policy OSC-8.4: Identify and inventory existing natural resources in the City of Menifee.
Policy OSC-8.5: Recognize the impacts new development will have on the City's natural resources
and identify ways to reduce these impacts.
Policy OSC-8.8: Implement and follow MSHCP goals and policies when making discretionary
actions pursuant to Section 13 of the Implementing Agreement.
Analysis of Project Effect and Determination of Significance:
a, f) Less Than Significant Impact with Mitigation Incorporated. The proposed project site is
located on a primarily vacant site immediately west of I-215, within a suburbanized area comprised of
residential, industrial, vacant land, and surface street features. The site was previously used for
agriculture and is currently vacant. The project site is not located within a Critical Habitat area
according to the USFWS.12 According to the Biological Technical Report prepared by Glenn Lukos
Associates, Inc. (Appendix B), no special-status plant species were on the project site. Based on the
presently disked and disturbed nature of the project site and the lack of suitable habitat, no impacts to
special-status plant species are expected as a result of the project.
According to the Biological Technical Report, the project site has a low potential to support three
special-status animal species, including the loggerhead shrike (foraging only), the northwestern San
Diego pocket mouse, and the San Diego black-tailed jackrabbit. Each of these species is covered
under the Western Riverside Multiple Species Habitat Conservation Plan (MSHCP) without
survey/conservation requirements. The loss of habitat for these species would be less than significant.
The project site also has a low potential to support Stephens’ kangaroo rat (SKR), which is federally
listed as endangered and state listed as threatened. The project site is located within the SKR Habitat
Conservation Plan (HCP) and SKR Fee Assessment Area. Impacts to SKR are covered under the SKR
HCP, and would be less than significant through project compliance with the SKR HCP.
The proposed project site is within the planning area of the Western Riverside Multiple Species Habitat
Conservation Plan (MSHCP).13 The proposed project is located within the Sun City/Menifee Valley
Area Plan of the MSHCP, and is not within a criteria cell (see Appendix C). The proposed project is not
located within or near any MSHCP Special Linkage areas and will not interfere with the goals of the
MSHCP. The study area is not within a Criteria Area Plant Species habitat assessment area. The
study area is not within a Narrow Endemic Plant Species Survey Area.14
The proposed project is located in the MSHCP Survey Area for burrowing owl. According to the
Biological Technical Report, the project site does not contain suitable burrows with the potential to
support burrowing owls due to the absence of ground squirrel activity. However, the general habitat of
the site is suitable for burrowing owls, and if ground squirrels were to become active onsite in the
future, then the site may have the potential to support burrowing owls in the future. Therefore,
Mitigation Measure BIO-1 has been incorporated. Mitigation Measure BIO-1 requires a pre-
construction burrowing owl survey pursuant to Objective 6 of the MSHCP within 30 days prior to
disturbance of the site. Mitigation Measure BIO-1 will reduce potential impacts to burrowing owls to
Planning Application No. CUP 2015-156 Page 25
less-than-significant levels.
Mitigation Measure
BIO-1 A 30-day preconstruction survey for burrowing owl is required by the Western Riverside County
Multiple Species Habitat Conservation Plan (MSHCP) to determine if burrowing owl is present
within the survey area. The survey shall be conducted by a qualified biologist no more than 30
days prior to ground disturbance in accordance with MSHCP survey requirements to avoid
direct take of burrowing owl. If burrowing owl are determined to occupy the project site or
immediate vicinity, the City of Menifee Planning Division will be notified and avoidance
measures will be implemented, as appropriate, pursuant to the MSHCP, the California Fish and
Game Code, the Migratory Bird Treaty Act, and the mitigation guidelines prepared by the
CDFW (2012).
The following measures are recommended in the CDFW guidelines to avoid impacts on an
active burrow:
No disturbance should occur within 50 meters (approximately 160 feet) of occupied burrows
during the non-breeding season.
No disturbance should occur within 75 meters (approximately 250 feet) of occupied burrows
during the breeding season.
For unavoidable impacts, passive or active relocation of burrowing owls would need to be
implemented by a qualified biologist outside the breeding season, in accordance with
procedures set by the MSHCP and in coordination with the CDFW.
b & c) Less than Significant Impact. According to the National Wetlands Inventory, the project site
does not contain any wetlands. Approximately 0.04 acre of U.S. Army Corps of Engineers water of the
U.S. was detected within Drainage A and the adjacent Caltrans flood control channel; however, none
of these waters were determined to be wetlands.15 The proposed project site has been previously used
for agriculture and is currently primarily vacant. The northern 0.08 acres of the project site is developed
with structures associated with the storage facility on Parcel 1 to the north. Approximately 0.12 acre of
MSHCP riparian/riverine areas were detected within Drainage A and the adjacent Caltrans flood
control channel. Riparian areas total 0.09 acre, consisting entirely of the mulefat thickets within
Drainage A, while riverine areas total 0.03 acre. The proposed project will offset permanent impacts to
riparian/riverine areas by purchasing credits through an approved mitigation bank/in-lieu fee program
within the Santa Ana River watershed. The proposed project will compensate for project-specific
impacts at a minimum 1:1 ratio for Corps/Regional Board jurisdiction and CDFW unvegetated
streambed, and a minimum of 2:1 ratio for riparian vegetation, ensuring that any impacts are reduced
to less than significant.
In addition, according to the Determination of Biologically Equivalent or Superior Preservation (DBESP)
prepared for the project, the proposed project will reconstruct a concrete trapezoidal channel in the
southeast corner of the site, just southeast of where it currently exists, and this channel will continue to
convey flows from offsite areas into the adjacent Caltrans flood control channel. Given the low habitat
quality within the project site itself, the proposed off-site mitigation, described above, will result in a
biologically equivalent or superior condition within the MSHCP Plan Area compared within the existing
conditions of the riparian/riverine areas. This determination is based on one or more of the following
factors, described below: effects on Conserved Habitats; effects on riparian/riverine planning species;
and effects on riparian linkages and function of the MSHCP conservation area.
Effects on Conserved Habitats
The project site is not located within the MSCHP Criteria Area or existing PQP Conserved Lands, and
therefore will not impact lands under existing conservation or lands targeted for conservation. Although
Planning Application No. CUP 2015-156 Page 26
the project will directly impact approximately 0.12 acre of riparian/riverine areas, the proposed
mitigation would result in superior preservation in the amount and quality of riparian/riverine habitat
within the MSHCP. The project will purchase credits at an off-site mitigation bank or in-lieu fee program
within the Santa Ana River Watershed at a 2:1 ratio for impacts to riparian habitat, and at a 1:1 ratio for
impacts to unvegetated riverine areas.
Effects on Riparian/Riverine Planning Species
The project will not impact habitat with the potential to support wildlife typical of riparian areas. The
proposed off-site mitigation will provide habitat with better opportunity for MSHCP riparian/riverine
planning species, and other planning species.
Effects on Riparian Linkages and Function of the MSHCP Conservation Area
The project will not adversely impact existing or proposed Conservation Areas, and will not adversely
impact existing or proposed Linkages or Constrained Linkages. Furthermore, the project is designed to
minimize adverse hydrologic effects to downstream resources. As such, the proposed project will not
adversely affect linkage and/or overall MSHCP conservation function.
As such, impact to riparian habitat or other sensitive natural habitat will be less than significant.
Because measures to mitigate impacts have been incorporated into the project as laid out in the
DBESP, impacts to will be less than significant without the need for additional mitigation.
d) Less than Significant Impact with Mitigation Incorporated. The project site has been previously
disturbed and is currently primarily vacant. The northern 0.08 acres of the project site is developed with
structures associated with the storage facility on Parcel 1 to the north. The project site is surrounded by
the existing storage facility to the north, vacant land to the west, a plant nursery to the south, and I-215
to the east. The project site contains limited vegetation, including 0.09 acre of mulefat stands occurring
within Drainage A, which is a Blue Line stream, 0.003 acre of disturbed Riversidean sage scrub
occurring offsite within the Caltrans flood control channel, and limited disturbed and ruderal vegetation.
There are no trees on site. There are no substantial vegetated areas or water bodies located on-site.
The project site does not provide for the movement of any native resident or migratory fish or wildlife.
Less than significant impacts will occur.
According to the Biological Technical Report, the limited amount of ruderal/disturbed vegetation and
the mulefat thickets within the proposed project have the potential to support nesting birds. Impacts to
nesting birds by the proposed project are prohibited under the Migratory Bird Treaty Act (MBTA) and
California Fish and Wildlife Code. Mitigation Measure BIO-2 has been incorporated to ensure that
impacts to nesting birds are reduced to less than significant levels. Mitigation Measure BIO-2 requires
that vegetation removal occur outside of the nesting season (February 15th to August 31st). If
vegetation is removed during the nesting season, a qualified biological shall conduct a nesting bird
survey no more than three days prior to scheduled removals. Within implementation of Mitigation
Measure BIO-2, impacts will be less than significant.
Mitigation Measure
BIO-2 Removal of vegetation shall not occur during the nesting season, between February 15 to
August 31 to the extent that this is feasible. Should vegetation require removal during the
nesting season, a qualified biologist shall conduct a nesting bird survey prior to removal.
Surveys shall be conducted no more than three days prior to scheduled removals. If active
nests are identified, the biologist shall establish appropriate buffers around the vegetation
containing the active nest. The vegetation containing the active nest shall not be removed, and
no grading shall occur within the established buffer, until a qualified biologist has determined
that the nest is no longer active. If clearing is not conducted within three days of a negative
survey, the nesting survey must be repeated to confirm the absence of nesting birds.
Planning Application No. CUP 2015-156 Page 27
e) No Impact. The project site is primarily vacant and is largely unvegetated. There are no trees on
site. The proposed development will include landscaping along the western, southern, and eastern
portion of the site and will not involve the removal of any trees considered a Heritage Tree as defined
in the City’s Tree Preservation Ordinance (Section 9.86.110 of the Menifee Municipal Code).
Therefore, the proposed project shall not conflict with any local policies or ordinances protecting
biological resources, such as a tree preservation policy or ordinance. Therefore, there will be no
impact.
Planning Application No. CUP 2015-156 Page 28
V. CULTURAL RESOURCES Potentially
Significant
Impact
Less Than
Significant with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
Would the project: a) Cause a substantial adverse change in
the significance of a historical resource as
defined in § 15064.5?
b) Cause a substantial adverse change in
the significance of an archaeological
resource pursuant to § 15064.5?
c) Directly or indirectly destroy a unique
paleontological resource or site or unique
geologic feature?
d) Disturb any human remains, including
those interred outside of formal
cemeteries?
Sources: Menifee General Plan; National Park Service, National Register of Historic Places; California
State Parks, Office of Historic Preservation; Scientific Resource Surveys, Inc., Phase 1 Cultural
Resources Assessment All Star Super Storage, October 1, 2015;
Applicable General Plan Policies:
Goal OSC-5: Archaeological, historical, and cultural resources that are protected and integrated
into the City's built environment.
Policy OSC-5.1: Preserve and protect significant archeological, historic, and cultural sites, places,
districts, structures, landforms, objects and native burial sites, and other features, such as Ringing
Rock and Grandmother Oak, consistent with state law.
Policy OSC-5.3: Preserve sacred sites identified by the Pechanga Band of Luiseno Indians and
Soboba Band of Luiseno Indians, such as tribal burial grounds, by avoiding activities that would
negatively impact the sites.
Policy OSC-5.5: Establish clear and responsible practices to identify, evaluate, and protect
previously unknown archeological, historic, and cultural sites, following CEQA and NEPA
procedure.
Analysis of Project Effect and Determination of Significance:
a) No Impact. This proposed project site does not satisfy any of the criteria for a historic resource
defined in Section 15064.5 of the State CEQA Guidelines. The project site is not listed with the State
Office of Historic Preservation or the National Register of Historic Places.16, 17 No known historically or
culturally significant resources, structures, buildings, or objects are located on the project site.18 As
such, the proposed project will not cause an adverse change in the significance of a historical
resource, and impacts to historic resources are not anticipated. No impact will occur.
b) Less Than Significant With Mitigation Incorporated. The proposed project site is located on a
primarily vacant site immediately west of I-215, within a suburbanized area comprised of residential,
Planning Application No. CUP 2015-156 Page 29
industrial use, vacant land, and surface street features. The proposed project consists of the expansion
of the existing self-storage facility to the north. No cultural resources of prehistoric (i.e. Native
American) or historical origin were identified in the Phase I Cultural Resources/Archeological Study
(Appendix D), which includes a records search at the Eastern Information Center (EIC) and a field
survey.19 In addition, the site was previously used for agriculture, which likely included ground-
disturbing activities that would likely have unearthed cultural resources at the site, if they were present.
A Sacred Lands File Search request was sent to the Native American Heritage Commission (NAHC)
on August 27, 2015. The NAHC provided the contact information to 40 individuals with tribal affiliation.
Scoping letters were sent to all 40 contacts by Scientific Resource Surveys, Inc. on September 9,
20185 to request any information regarding the use of the project area or any known cultural resources
within the vicinity. Productive comments were received from the Pechanga Band of Luiseno Indians
and the Soboba Band of Mission Indians and formal consultation with the City has been requested and
is under way in accordance with AB 52 guidelines.
Although the project site will not have an impact on any known cultural resources, because of the
identification of prehistoric site and historic structures located within one mile of the project site and the
existence of a natural intermittent stream/drainage which traverses the property, buried materials may
be unearthed during construction. As such, Mitigation Measures C-1 through C-3 are incorporated.
Mitigation Measure C-1 requires that recommended procedures be followed in the event of an
inadvertent archeological find. Mitigation Measure C-2 requires that a qualified archaeological monitor
be present during earth-moving activities in the areas of construction most likely to uncover resources
(areas of the drainage/blue line stream, detention basin and utility trenches). Mitigation Measure C-3
and C-4 require that a tribal monitor from both the Pechanga Band of Luiseno Indians and Soboba
Band of Luiseno Indians be present during ground-disturbing activities involving clearing and grubbing
and grading in the areas of the blue line stream, detention basin, and utility trenches. Furthermore,
General Plan policies are in place to preserve and protect archaeological and historic resources and
cultural sites, places, districts, structures, landforms, objects and native burial sites, traditional cultural
landscapes and other features, consistent with state law and any laws, regulations or policies which
may be adopted by the City (OCS-5.1). Impacts to buried cultural resources will be less than significant
with mitigation incorporated.
Mitigation Measure
C-1 Inadvertent Archeological Find. If during ground disturbance activities, unique cultural
resources are discovered that were not assessed by the archaeological report(s) and/or
environmental assessment conducted prior to project approval, the following procedures shall
be followed. Unique cultural resources are defined, for this condition only, as being multiple
artifacts in close association with each other, but may include fewer artifacts if the area of the
find is determined to be of significance due to its sacred or cultural importance as determined
in consultation with the Native American Tribe(s).
All ground disturbance activities within 100 feet of the discovered cultural resources shall
be halted until a meeting is convened between the developer, the archaeologist, the tribal
representative(s) and the Community Development Director to discuss the significance of
the find.
At the meeting, the significance of the discoveries shall be discussed and after consultation
with the tribal representative(s) and the archaeologist, a decision shall be made, with the
concurrence of the Community Development Director, as to the appropriate mitigation
(documentation, recovery, avoidance, etc.) for the cultural resources.
Grading of further ground disturbance shall not resume within the area of the discovery
until an agreement has been reached by all parties as to the appropriate mitigation.
Treatment and avoidance of the newly discovered resources shall be consistent with the
Cultural Resources Treatment and Monitoring Agreements entered into with the
Planning Application No. CUP 2015-156 Page 30
appropriate tribes. This may include avoidance of the cultural resources through project
design, in-place preservation of cultural resources located in native soils and/or re-burial on
the Project property so they are not subject to further disturbance in perpetuity.
Pursuant to Calif. Pub. Res. Code § 21083.2(b) avoidance is the preferred method of
preservation for archaeological resources and cultural resources. If the landowner and the
Tribe(s) cannot agree on the significance or the mitigation for the archaeological or cultural
resources, these issues will be presented to the City Community Development Director for
decision. The City Community Development Director shall make the determination based
on the provisions of the California Environmental Quality Act with respect to archaeological
resources, recommendations of the project archeologist and shall take into account the
cultural and religious principles and practices of the Tribe. Notwithstanding any other rights
available under the law, the decision of the City Community Development Director shall be
appealable to the City Planning Commission and/or City Council.”
C-2 Archeologist Retained. Prior to issuance of a grading permit the project applicant shall retain
a Riverside County qualified archaeologist to monitor ground-disturbing activities involving
clearing and grubbing and grading in the areas of the blue line stream, detention basin, and
utility trenches in an effort to identify any unknown archaeological resources.
The Project Archaeologist and the representative(s) from the Native American Tribe (s) shall be
included in the pre-grade meetings to provide cultural/historical sensitivity training including the
establishment of set guidelines for ground disturbance in sensitive areas with the grading
contractors. The Project Archaeologist and the Tribal representative(s) shall manage and
oversee monitoring for ground-disturbing activities involving clearing and grubbing and grading
in the areas of the blue line stream, detention basin, and utility trenches. The Project
Archaeologist and the Tribal representative(s), shall have the authority to temporarily divert,
redirect or halt the ground disturbance activities to allow identification, evaluation, and potential
recovery of cultural resources in coordination with any required special interest or tribal
monitors.
The developer/permit holder shall submit a fully executed copy of the contract to the
Community Development Department to ensure compliance with this condition of approval.
Upon verification, the Community Development Department shall clear this condition.
Any newly discovered cultural resources shall be subject to an evaluation, in consultation with
the Native American Tribe(s) and which will require the development of a treatment plan and
monitoring agreement for the newly discovered resources.
C-3 Native American Monitoring (Pechanga). Tribal monitor(s) shall be required on-site during
ground-disturbing activities involving clearing and grubbing and grading in the areas of the blue
line stream, detention basin, and utility trenches. The boundaries of areas to be monitored
shall be determined by the grading superintendent, the project archaeologist and the Pechanga
Tribe based on existing field conditions. The land divider/permit holder shall retain a qualified
tribal monitor(s) from the Pechanga Band of Luiseno Indians. Prior to issuance of a grading
permit, the developer shall submit a copy of a signed contract between the above-mentioned
Tribe and the land divider/permit holder for the monitoring of the project to the Community
Development Department and to the Engineering Department. The Native American Monitor(s)
shall have the authority to temporarily divert, redirect or halt the ground-disturbance activities to
allow recovery of cultural resources, in coordination with the Project Archaeologist.
The Developer shall relinquish ownership of all cultural resources, including all archaeological
artifacts that are of Native American origin, found in the project area for proper treatment and
disposition to a curational facility that meets or exceeds Federal Curation Standards outlined in
36 CFR 79. The Applicant/Permittee shall be responsible for all curation costs.
Planning Application No. CUP 2015-156 Page 31
C-4 Native American Monitoring (Soboba). Tribal monitor(s) shall be required on-site during
ground-disturbing activities involving clearing and grubbing and grading in the areas of the blue
line stream, detention basin, and utility trenches. The boundaries of areas to be monitored shall
be determined by the grading superintendent, the project archaeologist and the Soboba Tribe
based on existing field conditions. The land divider/permit holder shall retain a qualified tribal
monitor(s) from the Soboba Band of Luiseno Indians. Prior to issuance of a grading permit, the
developer shall submit a copy of a signed contract between the above-mentioned Tribe and the
land divider/permit holder for the monitoring of the project to the Community Development
Department and to the Engineering Department. The Native American Monitor(s) shall have the
authority to temporarily divert, redirect or halt the ground-disturbance activities to allow recovery
of cultural resources, in coordination with the Project Archaeologist.
The Developer shall relinquish ownership of all cultural resources, including all archaeological
artifacts that are of Native American origin, found in the project area for proper treatment and
disposition to a curational facility that meets or exceeds Federal Curation Standards outlined in
36 CFR 79. The Applicant/Permittee shall be responsible for all curation costs.
c) Less Than Significant Impact with Mitigation Incorporated. The project site, according to the
Menifee General Plan EIR, is located in a high paleontological sensitivity area. It is possible that
potentially significant prehistoric remains could be found, since buried fossils often go undetected
during a walkover survey.
C-5 Paleontological Resources. Prior to issuance of a grading permit a Paleontological Resource
Impact Mitigation Program (PRIMP) shall be prepared and submitted to the Community
Development Department for review and approval.
d) Less Than Significant Impact with Mitigation Incorporated. Because the project site has been
previously disturbed by agricultural uses, no human remains or cemeteries are anticipated to be
disturbed by the proposed project. Nevertheless, if human remains are encountered, State Health and
Safety Code Section 7050.5 states that no further disturbance shall occur until the Riverside County
Coroner has made the necessary findings as to origin. Further, pursuant to Public Resource Code
Section 5097.98(b) remains shall be left in place and free from disturbance until a final decision as to
the treatment and disposition has been made. If the Riverside County Coroner determines the remains
to be Native American, the Native American Heritage Commission shall be contacted within the period
specified by law (24 hours). Subsequently, the Native American Heritage Commission shall identify the
"most likely descendant". The most likely descendant shall then make recommendations and engage
in consultation concerning the treatment of the remains as provided in Public Resources Code Section
5097.98. Human remains from other ethnic/cultural groups with recognized historical associations to
the project area shall also be subject to consultation between appropriate representatives from that
group and the Community Development Director. In addition to state laws referenced above, Mitigation
Measures C-6 and C-7 have been incorporated to ensure compliance with State Health and Safety
Code Section 7050.5 and 5097.98. Thus, compliance with the above-referenced state laws will reduce
impacts to less than significant levels.
Mitigation Measure
C-6 Human Remains. If human remains are encountered, State Health and Safety Code Section
7050.5 states that no further disturbance shall occur until the Riverside County Coroner has
made the necessary findings as to origin. Further, pursuant to Public Resource Code
5097.98(b), remains shall be left in place and free from disturbance until a final decision as to
the treatment and disposition has been made. If the Riverside County Coroner determines the
Planning Application No. CUP 2015-156 Page 32
remains to be Native American, the Native American Heritage Commission shall be contacted
within the period specified by law (24 hours). Subsequently, the Native American Heritage
Commission shall identify the “most likely descendant.” The most likely descendant shall then
make recommendations and engage in consultation concerning the treatment of the remains
as provided in Public Resources Code Section 5097.98. Human remains from other
ethnic/cultural groups with recognized historical associations to the project area shall also be
subject to consultation between appropriate representatives from that group and the
Community Development Director.
C-7 Non-Disclosure of Location Reburials. It is understood by all parties that unless otherwise
required by law, the site of any reburial of Native American human remains or associated grave
goods shall not be disclosed and shall not be governed by public disclosure requirements of
the California Public Records Act. The Coroner, pursuant to the specific exemption set forth in
California Government Code 6254 (r)., parties, and Lead Agencies, will be asked to withhold
public disclosure information related to such reburial, pursuant to the specific exemption set
forth in California Government Code 6254 (r).
Planning Application No. CUP 2015-156 Page 33
VI. GEOLOGY AND SOILS Potentially
Significant
Impact
Less Than
Significant with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
Would the project: a) Expose people or structures to potential
substantial adverse effects, including the
risk of loss, injury, or death involving:
i) Rupture of a known earthquake fault,
as delineated on the most recent
Alquist-Priolo Earthquake Fault Zoning
Map issued by the State Geologist for
the area or based on other substantial
evidence of a known fault? Refer to
Division of Mines and Geology Special
Publication 42.
ii) Strong seismic ground shaking?
iii) Seismic-related ground failure,
including liquefaction?
iv) Landslides?
b) Result in substantial soil erosion or the
loss of topsoil?
c) Be located on a geologic unit or soil that
is unstable, or that would become unstable
as a result of the project, and potentially
result in on- or off-site landslide, lateral
spreading, subsidence, liquefaction or
collapse?
d) Be located on expansive soil, as defined
in Table 18-1-B of the Uniform Building
Code (1997), creating substantial risks to
life or property?
e) Have soils incapable of adequately
supporting the use of septic tanks or
alternative waste water disposal systems
where sewers are not available for the
disposal of waste water?
Sources: Menifee General Plan, Exhibits S-1, “Fault Map,” S-2, “Slope Distribution,” S-3, “Liquefaction
and Landslides,” and S-4, “Geologic Map”; Riverside County General Plan Figure S-8, Wind “Erosion
Susceptibility Map,”
Applicable General Plan Policies:
Goal S-1: A community that is minimally impacted by seismic shaking and earthquake-induced or
Planning Application No. CUP 2015-156 Page 34
other geologic hazards.
Policy S-1.1: Require all new habitable buildings and structures to be designed and built to be
seismically resistant in accordance with the most recent California Building Code adopted by the
City.
Goal S-2: A community that has used engineering solutions to reduce or eliminate the potential for
injury, loss of life, property damage, and economic and social disruption caused by geologic
hazards such as slope instability; compressible, collapsible, expansive or corrosive soils; and
subsidence due to groundwater withdrawal.
Policy S-2.1: Require all new developments to mitigate the geologic hazards that have the potential
to impact habitable structures and other improvements.
Analysis of Project Effect and Determination of Significance:
a.i.) Less Than Significant Impact. Although the project site is located in seismically active Southern
California, the site is not located within an Alquist-Priolo Earthquake Fault Zone.20 No active faults have
been identified at the ground surface within City limits. The nearest active fault is the Temecula
Segment of the Elsinore Fault Zone, which is located approximately nine miles west of the project site.
Therefore, impacts are considered less than significant.
a.ii) Less Than Significant Impact. The proposed project will be subject to ground shaking impacts
should a major earthquake in the area occur in the future. Potential impacts include injury or loss of life
and property damage.
The project site is subject to strong seismic ground shaking as are virtually all properties in Southern
California. The proposed buildings are subject to the seismic design criteria of the California Building
Code (CBC). The 2013 California Building Code (California Building Code, California Code of
Regulations, Title 24, Volume 2) contains seismic safety provisions with the aim of preventing building
collapse during a design earthquake, so that occupants would be able to evacuate after the
earthquake. A design earthquake is one with a two percent chance of exceedance in 50 years, or an
average return period of 2,475 years. Adherence to these requirements will reduce the potential of the
building from collapsing during an earthquake, thereby minimizing injury and loss of life. Although
structures may be damaged during earthquakes, adherence to seismic design requirements will
minimize damage to property within the structure because the structure is designed not to collapse.
The CBC is intended to provide minimum requirements to prevent major structural failure and loss of
life. Adherence to existing regulations will reduce the risk of loss, injury, and death; impacts due to
strong ground shaking will be less than significant.
a.iii) No Impact. Liquefaction is a phenomenon that occurs when soil undergoes transformation from a
solid state to a liquefied condition due to the effects of increased pore-water pressure. This typically
occurs where susceptible soils (particularly the medium sand to silt range) are located over a high
groundwater table (within 50 feet of the surface). Affected soils lose all strength during liquefaction and
foundation failure can occur.
According to the California Department of Conservation Seismic Hazard Evaluation system, the project
the site is not located in a Zone of Required Investigation for liquefaction.21 This indicates that the area
has not been subject to historic occurrence of liquefaction, or local geological, geotechnical, and
groundwater conditions do not indicate potential for permanent ground displacement such that
mitigation as defined in Public Resources Code § 2693(c) would be required. Therefore, no impacts
due to the project site from seismically induced liquefaction will occur.
Planning Application No. CUP 2015-156 Page 35
a.iv.) No Impact. The project site is located in a suburbanized area that is relatively flat and there is no
potential for landslides on the project site. No impacts to the proposed project site from landslides will
occur.
b) Less Than Significant Impact. Topsoil is used to cover surface areas for the establishment and
maintenance of vegetation due to its high concentrations of organic matter and microorganisms. The
topsoil on the project site has been disturbed by past agricultural use. The project has the potential to
expose surficial soils to wind and water erosion during construction activities. Wind erosion will be
minimized through soil stabilization measures required by South Coast Air Quality Management District
(SCAQMD) Rule 403 (Fugitive Dust), such as daily watering. Water erosion will be prevented through
the City’s standard erosion control practices required pursuant to the California Building Code and the
National Pollution Discharge Elimination System (NPDES), such as silt fencing, fiber rolls, or
sandbags. Following project construction, the site will be covered completely by paving, structures, and
landscaping. Impacts related to soil erosion will be less than significant with implementation of existing
regulations.
c) Less Than Significant Impact. Impacts related to liquefaction and landslides are discussed above.
Lateral spreading is the downslope movement of surface sediment due to liquefaction in a subsurface
layer. The downslope movement is due to gravity and earthquake shaking combined. Such movement
can occur on slope gradients of as little as one degree. Lateral spreading typically damages pipelines,
utilities, bridges, and structures.
Lateral spreading of the ground surface during a seismic activity usually occurs along the weak shear
zones within a liquefiable soil layer and has been observed to generally take place toward a free face
(i.e. retaining wall, slope, or channel) and to lesser extent on ground surfaces with a very gentle slope.
As such, the soils report includes preliminary design recommendations for footings and building floor
slabs. Furthermore, the project is required to be constructed in accordance with the CBC. Therefore,
with the project’s compliance with CBC requirements, impacts arising from unstable soils will be
reduced to less than significant.
d) Less than Significant Impact. The CBC requires special design considerations for foundations of
structures built on soils with expansion indices greater than 20. With the project’s adherence to CBC
design considerations, impacts related to expansive soils will be considered less than significant.
e) No Impact. The proposed project includes the development of self-storage facilities, and will not
generate any wastewater that requires conveyance through a municipal sewage or septic system. No
impact will occur.
Planning Application No. CUP 2015-156 Page 36
VII. GREENHOUSE GAS EMISSIONS Potentially
Significant
Impact
Less Than
Significant with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact Would the project: a) Generate greenhouse gas emissions,
either directly or indirectly, that may have a
significant impact on the environment?
b) Conflict with any applicable plan, policy
or regulation of an agency adopted for the
purpose of reducing the emissions of
greenhouse gases?
Source: OPR’s Technical Advisory.
Applicable General Plan Policies:
Goal OSC-4: Efficient and environmentally appropriate use and management of energy and mineral
resources to ensure their availability for future generations.
Policy OSC-4.1: Apply energy efficiency and conservation practices in land use, transportation
demand management, and subdivision and building design.
Policy OSC-4.2: Evaluate public and private efforts to develop and operate alternative systems of
energy production, including solar, wind, and fuel cell.
Goal OSC-10: An environmentally aware community that is responsive to changing climate
conditions and actively seeks to reduce local greenhouse gas emissions.
Policy OSC-10.1: Align the City's local GHG reduction targets to be consistent with the statewide
GHG reduction target of AB 32.
Policy OSC-10.2: Align the City's long-term GHG reduction goal consistent with the statewide GHG
reduction goal of Executive Order S-03-05.
Policy OSC-10.3: Participate in regional greenhouse gas emission reduction initiatives.
Policy OSC-10.4: Consider impacts to climate change as a factor in evaluation of policies,
strategies, and projects.
Existing Setting:
Global Warming and Greenhouse Gases
Global climate change refers to changes in average climatic conditions on earth as a whole, including
temperature, wind patterns, precipitation and storms. Global warming, a related concept, is the
observed increase in average temperature of the earth’s surface and atmosphere. The six major
greenhouse gases (GHGs) identified by the Kyoto Protocol are carbon dioxide (CO2), methane (CH4),
nitrous oxide (N20), sulfur hexafluoride (SF6), hydrofluorocarbons (HFCs), and perfluorocarbons
(PFCs). GHGs absorb longwave radiant energy reflected by the earth, which warms the atmosphere.
GHGs also radiate long wave radiation both upward to space and back down toward the surface of the
earth. The downward part of this longwave radiation absorbed by the atmosphere is known as the
“greenhouse effect.” The potential effects of global climate change may include rising surface
temperatures, loss in snow pack, sea level rise, more extreme heat days per year, and more drought
Planning Application No. CUP 2015-156 Page 37
years.
CO2 is an odorless, colorless natural GHG. Natural sources include the following: decomposition of
dead organic matter; respiration of bacteria, plants, animals, and fungus; evaporation from oceans;
and volcanic outgassing. Anthropogenic (human caused) sources of CO2 are from burning coal, oil,
natural gas, wood, butane, propane, etc. CH4 is a flammable gas and is the main component of natural
gas. N20, also known as laughing gas, is a colorless GHG. Some industrial processes (fossil fuel-fired
power plants, nylon production, nitric acid production, and vehicle emissions) also contribute to the
atmospheric load of GHGs. HFCs are synthetic man-made chemicals that are used as a substitute for
chlorofluorocarbons (whose production was stopped as required by the Montreal Protocol) for
automobile air conditioners and refrigerants. The two main sources of PFCs are primary aluminum
production and semiconductor manufacture. SF6 is an inorganic, odorless, colorless, nontoxic,
nonflammable gas. SF6 is used for insulation in electric power transmission and distribution equipment,
in the magnesium industry, in semiconductor manufacturing, and as a tracer gas for leak detection.
Events and activities, such as the industrial revolution and the increased combustion of fossil fuels
(e.g., gasoline, diesel, coal, etc.), have heavily contributed to the increase in atmospheric levels of
GHGs. An air quality analysis of GHGs is a much different analysis than the analysis of criteria
pollutants for the following reasons. For criteria pollutants significance thresholds are based on daily
emissions because attainment or non-attainment is based on daily exceedances of applicable ambient
air quality standards. Further, several ambient air quality standards are based on relatively short-term
exposure effects on human health, e.g., one-hour and eight-hour. Since the half-life of CO2 in the
atmosphere is approximately 100 years, for example, the effects of GHGs are longer-term, affecting
global climate over a relatively long time frame. As a result, the SCAQMD’s current position is to
evaluate GHG effects over a longer timeframe than a single day.
In its CEQA & Climate Change document (January 2008), the California Air Pollution Control Officers
Association (CAPCOA) identifies many potential GHG significance threshold options. The CAPCOA
document indicates that establishing quantitative thresholds is a balance between setting the level low
enough to capture a substantial portion of future residential and non-residential development, while
also setting a threshold high enough to exclude small development projects that will contribute a
relatively small fraction of the cumulative statewide GHG emissions. Two potential significance
thresholds were 10,000 metric tons per year and 25,000 metric tons per year.
Finally, another approach to determining significance is to estimate what percentage of the total
inventory of GHG emissions are represented by emissions from a single project. If emissions are a
relatively small percentage of the total inventory, it is possible that the project will have little or no effect
on global climate change. According to available information, the statewide inventory of CO2 equivalent
emissions is as follows: 1990 GHG emissions were estimated to equal 427 million metric tons of CO2
equivalent, and 2020 GHG emissions are projected to equal 600 million metric tons of CO2 equivalent,
under a business as usual scenario. Interpolating an inventory for the year 2011 results in an
estimated inventory of approximately 121 million metric tons of CO2 equivalent. Interpolating an
inventory for the year 2012 results in an estimated inventory of approximately 127 million metric tons of
CO2 equivalent. These amounts assume that between 1990 and 2020 there is an average increase of
5.76 million tons per year of GHG.
Analysis of Project Effect and Determination of Significance:
a) Less Than Significant Impact. GHG emissions for the project were analyzed in the project
Greenhouse Gas Emissions Analysis Report to determine if the project could have a cumulatively
considerable impact related to greenhouse gas emissions (See Appendix A). The emissions inventory
accounts for GHG emissions from construction and operational activities.
Operational emissions associated with the proposed project would include GHG emissions from mobile
Planning Application No. CUP 2015-156 Page 38
sources (transportation), energy, water use and treatment, waste disposal, and area sources. GHG
emissions from electricity use are indirect GHG emissions from the energy (purchased energy) that is
produced offsite. Area sources are owned or controlled by the project (e.g., natural gas combustion,
boilers, and furnaces) and produced onsite. Construction activities are short term and cease to emit
greenhouse gases upon completion, unlike operational emissions that are continuous year after year
until operation of the use ceases. Because of this difference, SCAQMD recommends amortizing
construction emissions over a 30-year operational lifetime. This normalizes construction emissions so
that they can be grouped with operational emissions in order to generate a precise project-based GHG
inventory.
A numerical threshold for determining the significance of greenhouse gas emissions in the Basin has
not officially been adopted by the SCAQMD. As an interim threshold based on guidance provided in
the CAPCOA CEQA and Climate Change white paper, a non-zero threshold based on Approach 2 of
the handbook will be used.22 Threshold 2.5 (Unit-Based Thresholds Based on Market Capture)
establishes a numerical threshold based on capture of approximately 90 percent of emissions from
future development. The latest threshold developed by SCAQMD using this method is 3,000 metric
tons carbon dioxide equivalent (MTCO2E) per year for residential and commercial projects.23 This
threshold is based on the review of 711 CEQA projects. It should also be noted that the city of Menifee
does not yet have an adopted GHG inventory or an adopted GHG reduction plan (such as a Climate
Action Plan). The City also has not adopted a quantitative threshold of significance for GHGs. The city
will accept the interim threshold recommended in SCAQMD’s Interim Thresholds document for
commercial, residential, and mixed-use projects.24 Thus, and based on guidance from the City of
Menifee and SCAQMD, if a residential or commercial project would emit GHGs less than 3,000 metric
tons of carbon dioxide equivalent (MTCO2e) per year, the project is not considered a substantial GHG
emitter and the GHG impact would be less than significant.
Annual GHG emissions are summarized in Table 7 (Greenhouse Gas Emission Inventory) below.
Greenhouse gas emissions associated with the proposed project will not exceed the 3,000 MTCO2E
threshold; therefore, impacts will be less than significant.
Table 7
Greenhouse Gas Emissions Inventory
Source CO2E (MT/YR)
Construction (amortized) 24.5
Operational 906.3
Total 930.8
Threshold 3,000
Exceeds? No
Source: MIG, 2016
b) No Impact. The City of Menifee has not yet adopted a qualified GHG reduction plan.25 The City of
Menifee General Plan includes policies and measures (shown in General Plan Draft EIR GHG section
Table 5.7-9) for the City to implement in support of achieving the reduction target of AB 32 and the
statewide GHG reduction goal of Executive Order S-03-05. The City has adopted the 2013 edition of
the California Building Code (Title 24), including the California Green Building Standards Code
(pursuant to Menifee Municipal Code Chapter 8.06). The project will be subject to the California Green
Building Standards Code, which requires new buildings to reduce water consumption, employ building
commissioning to increase building system efficiencies for large buildings, divert construction waste
from landfills, and install low pollutant-emitting finish materials. The project does not include any
feature (i.e. substantially alter energy demands) that will interfere with implementation of these state
and City codes and plans. The proposed project will not conflict with any applicable plan, policy or
regulation of an agency adopted for the purpose of reducing the emissions of greenhouse gases; no
impact will occur.
Planning Application No. CUP 2015-156 Page 39
VIII. HAZARDS AND HAZARDOUS
MATERIALS Potentially
Significant
Impact
Less Than
Significant with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
Would the project: a) Create a significant hazard to the public
or the environment through the routine
transport, use, or disposal of hazardous
materials?
b) Create a significant hazard to the public
or the environment through reasonably
foreseeable upset and accident conditions
involving the release of hazardous
materials into the environment?
c) Emit hazardous emissions or handle
hazardous or acutely hazardous materials,
substances, or waste within one-quarter
mile of an existing or proposed school?
d) Be located on a site which is included on
a list of hazardous materials sites compiled
pursuant to Government Code Section
65962.5 and, as a result, would it create a
significant hazard to the public or the
environment?
e) For a project located within an airport
land use plan or, where such a plan has
not been adopted, within two miles of a
public airport or public use airport, would
the project result in a safety hazard for
people residing or working in the project
area?
f) For a project within the vicinity of a
private airstrip, would the project result in a
safety hazard for people residing or
working in the project area?
g) Impair implementation of or physically
interfere with an adopted emergency
response plan or emergency evacuation
plan?
h) Expose people or structures to a
significant risk of loss, injury or death
involving wildland fires, including where
wildlands are adjacent to urbanized areas
or where residences are intermixed with
wildlands?
Sources: Menifee General Plan, Exhibit S-6, “High Fire Hazard Areas,” and Exhibit S-7, “Critical
Facilities;” State of California, Department of Toxics Substances Control, EnviroStor database; State of
California, Department of Toxics Substances Control, Cortese list of Hazardous Waste and
Planning Application No. CUP 2015-156 Page 40
Substances Sites database; State of California, Water Resources Control Board, Geotracker, All
Hazards Site Search; United States, Environmental Protection Agency, Comprehensive Environmental
Response, Compensation, and Liability Information System (CERCLIS) database; Priority 1
Environmental, Phase 1 Environmental Site Assessment, August 31, 2015
Applicable General Plan Policies:
Goal S-5: A community that has reduced the potential for hazardous materials contamination.
Policy S-5.1: Locate facilities involved in the production, use, storage, transport, or disposal of
hazardous materials away from land uses that may be adversely impacted by such activities and
areas susceptible to impacts or damage from a natural disaster.
Policy S-5.2: Ensure that the fire department can continue to respond safely and effectively to a
hazardous materials incident in the City, whether it is a spill at a permitted facility, or the result of an
accident along a section of the freeway or railroads that extend across the City.
Policy S-5.4: Ensure that all facilities that handle hazardous materials comply with federal and state
laws pertaining to the management of hazardous wastes and materials.
Policy S-5.5: Require facilities that handle hazardous materials to implement mitigation measures
that reduce the risks associated with hazardous material production, storage, and disposal.
Goal S-6: A City that responds and recovers in an effective and timely manner from natural
disasters such as flooding, fire, and earthquakes, and as a result is not impacted by civil unrest that
may occur following a natural disaster.
Policy S-6.1: Continuously review, update, and implement emergency preparedness, response,
and recovery plans that make the best use of the City- and county-specific emergency
management resources available.
Analysis of Project Effect and Determination of Significance:
a) Less Than Significant Impact. The proposed project could result in a significant hazard to the
public if the project includes the routine transport, use, or disposal of hazardous materials or places
housing near a facility which routinely transports, uses, or disposes of hazardous materials. The
proposed project is located within an industrially zoned area that is primarily vacant. The proposed
project does not place housing near any hazardous materials facilities. The routine use, transport, or
disposal of hazardous materials is primarily associated with industrial uses that require such materials
for manufacturing operations or produce hazardous wastes as by-products of production applications.
The proposed project does not propose or facilitate any activity involving significant use, routine
transport, or disposal of hazardous substances as part of a self-storage use.
During construction, there would be a minor level of transport, use, and disposal of hazardous
materials and wastes that are typical of construction projects. This would include fuels and lubricants
for construction machinery, coating materials, etc. Routine construction control measures and best
management practices for hazardous materials storage, application, waste disposal, accident
prevention and clean-up, etc. would be sufficient to reduce potential impacts to a less than significant
level.
With regard to project operation, widely used hazardous materials common at self-storage uses
include cleaners, pesticides, and food waste. The remnants of these and other products are disposed
of as household hazardous waste that are prohibited or discouraged from being disposed of at local
landfills. Regular operation and cleaning of facility would not result in significant impacts involving use,
Planning Application No. CUP 2015-156 Page 41
storage, transport or disposal of hazardous wastes and substances. Use of common household
hazardous materials and their disposal does not present a substantial health risk to the community.
Impacts associated with the routine transport and use of hazardous materials or wastes would be less
than significant.
b) Less Than Significant. There are no open leaking underground storage tank (LUST) cases on or
near the proposed project site.26 According to the Phase I Site Assessment (Appendix E), pesticides
are likely to be found in sub surface soils due to the past use of the site as a wheat field. The proposed
project consists of the expansion of the existing All Star Storage to the north. Past agricultural use and
the potential presence of pesticides is not considered a Recognized Environmental Condition (REC).
Impacts will be less than significant. Therefore, there will be no impact related to the release of
hazardous materials into the environment as a result of the proposed project.
The project site is primarily vacant thus there will be no impacts related to structures with asbestos
containing materials or lead-based paint. With adherence to existing regulations, the proposed project
will not create a significant hazard to the public or the environment through reasonably foreseeable
upset and accident conditions involving the release of hazardous materials into the environment;
impacts will be less than significant.
c) No Impact. There are no schools within ¼ mile of the project site. Therefore, no impact regarding
hazardous material transportation, storage, and use will occur.
d) No Impact. The proposed project is not located on a site listed on the state Cortese List, a
compilation of various sites throughout the state that have been compromised due to soil or
groundwater contamination from past uses.27
Based upon review of the Cortese List, the project site is not:
listed as a hazardous waste and substance site by the Department of Toxic Substances
Control (DTSC),28
listed as a leaking underground storage tank (LUST) site by the State Water Resources
Control Board (SWRCB),29
listed as a hazardous solid waste disposal site by the SWRCB,30
currently subject to a Cease and Desist Order (CDO) or a Cleanup and Abatement Order
(CAO) as issued by the SWRCB,31 or
developed with a hazardous waste facility subject to corrective action by the DTSC.32
e-f) No Impact. There are no public airports or private airstrips within two miles of the project site. No
impact will occur.
g) Less Than Significant Impact. The proposed project consists of the expansion of an existing self-
storage facility. All project elements, including landscaping, will be sited with sufficient clearance from
the proposed buildings so as not to interfere with emergency access to and evacuation from the site.
The proposed project is required to comply with the California Fire Code as adopted by the Menifee
Municipal Code. Primary and secondary access to the project site will be provided via driveways off of
Haun Road.
The project will not impair implementation of or physically interfere with an adopted emergency
response plan or evacuation plan because no permanent public street or lane closures are proposed.
Construction work in the street associated with the project will be limited to minor roadway
improvements that will be limited to nominal potential traffic diversion. Project impacts will be less than
significant.
h) No Impact. The proposed project site is not located within a fire hazard zone, as identified on the
Planning Application No. CUP 2015-156 Page 42
latest Fire Hazard Severity Zone (FHSZ) maps prepared by the California Department of Forestry and
Fire Protection (CALFIRE).33 There are no wildland conditions in the suburbanized area where the
project site is located. No impact will occur.
Planning Application No. CUP 2015-156 Page 43
IX. HYDROLOGY AND WATER QUALITY Potentially
Significant
Impact
Less Than
Significant with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
Would the project: a) Violate any water quality standards or
waste discharge requirements?
b) Substantially deplete groundwater
supplies or interfere substantially with
groundwater recharge such that there
would be a net deficit in aquifer volume or
a lowering of the local groundwater table
level (e.g., the production rate of pre-
existing nearby wells would drop to a level
which would not support existing land uses
or planned uses for which permits have
been granted)?
c) Substantially alter the existing drainage
pattern of the site or area, including
through the alteration of the course of a
stream or river, in a manner which would
result in substantial erosion or siltation on-
or off-site?
d) Substantially alter the existing drainage
pattern of the site or area, including
through the alteration of the course of a
stream or river, or substantially increase
the rate or amount of surface runoff in a
manner which would result in flooding on-
or off-site?
e) Create or contribute runoff water which
would exceed the capacity of existing or
planned stormwater drainage systems or
provide substantial additional sources of
polluted runoff?
f) Otherwise substantially degrade water
quality?
g) Place housing within a 100-year flood
hazard area as mapped on a federal Flood
Hazard Boundary or Flood Insurance Rate
Map or other flood hazard delineation
map?
h) Place within a 100-year flood hazard
area structures which would impede or
redirect flood flows?
Planning Application No. CUP 2015-156 Page 44
i) Expose people or structures to a
significant risk of loss, injury or death
involving flooding, including flooding as a
result of the failure of a levee or dam?
j) Inundation by seiche or mudflow?
Sources: Menifee General Plan, Safety Element Exhibit S-5, “Flood Hazards”; Riverside County
General Plan Figure S-9, “100- and 500-Year Flood Hazard Zones,” and Figure S-10 “Dam Failure
Inundation Zone”; Blaine A. Womer Civil Engineering, Project Specific Water Quality Management
Plan, July 2, 2015; Blaine A. Womer Civil Engineering, Preliminary Hydrology Study for All Star Super
Storage, July 1, 2015.
Applicable General Plan Policies:
Goal S-3: A community that is minimally disrupted by flooding and inundation hazards.
Policy S-3.1: Require that all new developments and redevelopments in areas susceptible to
flooding (such as the 100-year floodplain and areas known to the City to flood during intense or
prolonged rainfall events) incorporate mitigation measures designed to mitigate flood hazards.
Policy S-3.2: Reduce flood hazards in developed areas known to flood.
Policy OSC-7.8: Protect groundwater quality by decommissioning existing septic systems and
establishing connections to sanitary sewer infrastructure.
Policy OSC-7.9: Ensure that high quality potable water resources continue to be available by
managing stormwater runoff, wellhead protection, and other sources of pollutants.
Policy OSC-7.10: Preserve natural floodplains, including Salt Creek, Ethanac Wash, Paloma Wash,
and Warm Springs Creek, to facilitate water percolation, replenishment of the natural aquifer,
proper drainage, and prevention of flood damage.
Analysis of Project Effect and Determination of Significance:
a) Less Than Significant Impact. A project normally would have an impact on surface water quality if
discharges associated with the project would create pollution, contamination, or nuisance as defined in
Water Code Section 13050, or that cause regulatory standards to be violated as defined in the
applicable National Pollutant Discharge Elimination System (NPDES) stormwater permit or Water
Quality Control Plan for a receiving water body. For the purpose of this specific issue, a significant
impact could occur if the project would discharge water that does not meet the quality standards of the
agencies which regulate surface water quality and water discharge into stormwater drainage systems.
Significant impacts could also occur if the project does not comply with all applicable regulations with
regard to surface water quality as governed by the State Water Resources Control Board (SWRCB).
These regulations include preparation of a Water Quality Management Plan (WQMP) to reduce
potential post-construction water quality impacts.
Construction Impacts
Three general sources of potential short-term, construction-related stormwater pollution associated
with the proposed project include: 1) the handling, storage, and disposal of construction materials
containing pollutants; 2) the maintenance and operation of construction equipment; and 3) earth-
moving activities which, when not controlled, may generate soil erosion via storm runoff or mechanical
equipment. The proposed project will disturb approximately 9.85 acres of land and therefore will be
subject to NPDES permit requirements during construction activities. Pursuant to the Menifee
Municipal Code § 15.01.015, new development or redevelopment projects shall control stormwater
Planning Application No. CUP 2015-156 Page 45
runoff so as to prevent any deterioration of water quality that will impair subsequent or competing uses
of the water. The Department of Public Works and Engineering will review and approve Best
Management Practices (BMPs) contained in the project applicant’s submitted Stormwater Pollution
Prevention Plan (SWPPP) to be implemented to reduce the discharge of pollutants during construction.
The project applicant’s SWPPP shall identify erosion control BMPs to minimize pollutant discharges
during construction activities. These identified BMPs will include stabilized construction entrances,
sand bagging, designated concrete washout, tire wash racks, silt fencing, and curb cut/inlet protection.
Impacts will be less than significant with implementation of existing regulations.
Operational Impacts
Proposed construction of the storage facility will increase impervious areas by replacing the vacant
property with 15 storage buildings and associated paving and landscaping. Landscaping is proposed
as part of project design along the west, south, and east boundaries of the site. Although the amount of
impervious surfaces will be greater than existing conditions, all on-site runoff will drain towards the east
of the property into a water quality detention basin. According to the Preliminary Hydrology Study
(Appendix F), the detention basin has been sized in accordance with the Riverside County Flood
Control and Water Conservation District criteria and that outflow from the basin is significantly lower
than the outflow under existing conditions. According to the Water Quality Management Plan
(Appendix G) prepared for the proposed project, the detention basin and the following source control
BMPs would fully address drainage management areas and no alternative compliance measures are
required for the project.
Permanent Structural Source Control BMPs
Mark all inlets “only rain in the drain”.
Landscaping design to minimize irrigation and runoff. Specify plants tolerant to saturated
soil conditions for self-retaining areas.
Provide a means to drain fire sprinkler water to the sanitary sewer.
Operational Source Control BMPs
Maintain stencil.
Maintain landscaping using minimum or no pesticides.
Sweep sidewalks, parking lots and drive aisles regularly to prevent accumulation of litter
and debris.
Compliance with existing federal, state and local regulations related to water quality, including
implementation of BMP’s included in the project construction SWPPP will result in impacts to water
quality being less than significant.
The proposed development will not generate hazardous wastewater that will require any special waste
discharge permits. All wastewater associated with the project’s interior plumbing systems will be
discharged into the local sewer system for treatment at the regional wastewater treatment plant.
Impacts will be less than significant with implementation of existing regulations.
b) Less Than Significant Impact. If the project removes an existing groundwater recharge area or
substantially reduces runoff that results in groundwater recharge such that existing wells will no longer
be able to operate, a potentially significant impact could occur. The project site is located in the
Menifee Hydrologic Subarea (HSA) within the Perris Hydrologic Area of the San Jacinto Valley
Hydraulic Unit.34 According to the General Plan EIR, there are no percolation basins or other areas in
the City used for intentional recharge of groundwater basins. Therefore, the increase in impermeable
surfaces will not interfere with intentional groundwater recharge. Further, all on-site runoff will drain
towards the east of the property into a water quality detention basin. Impacts will be less than
significant.
c) Less Than Significant Impact. Potentially significant impacts to the existing drainage pattern of the
Planning Application No. CUP 2015-156 Page 46
site or area could occur if development of the project results in substantial on- or off-site erosion or
siltation. The project will collect and convey off-site run-off from upstream areas and convey these
flows to a water quality detention basin located in the eastern portion of the site. A site drainage plan is
required by the City of Menifee and will be reviewed by the City Engineer. The final grading and
drainage plan will be approved by the City Department of Public Works and Engineering during plan
check review. Erosion and siltation reduction measure BMPs contained in the required SWPPP will be
implemented during construction. At the completion of construction, the project will consist of
impervious surfaces, landscaping, a water quality detention basin, and therefore the development will
not be subject to substantial erosion. The proposed project will not alter the course of Drainage A,
which traverses the southeastern portion of the project site; thus, the project will not alter any stream
course. Impacts will be less than significant.
d-e) Less Than Significant Impact. One drainage course that is a Blue Line stream (Drainage A)
traverses the southeastern portion of the project site. Drainage A originates offsite and flow through the
plant nursery south of the project site. Prior to entering the project site, flows from Drainage A are
diverted into a constructed side channel on the nursery property. This side channel runs parallel to the
southern boundary of the project site and ties into the flood control channel located immediately east of
the site. Flows within Drainage A that overtop the constructed side channel enter the site from the
south and sheet flow across the disked and plowed field in a northeastern direction, eventually exiting
the site along the eastern boundary over a concrete spillway and directly into the Caltrans channel that
runs parallel to I-215. The drainage course has been diverted to run along the southern portion of the
project site.
During construction, the project applicant will be required to comply with drainage and runoff guidelines
pursuant to City of Menifee guidelines.
With regard to project operation, construction of the proposed project will increase the net area of
impermeable surfaces on the site because the site is currently primarily vacant. Project implementation
will not result in alteration of the existing drainage course; however, the project proposes to turn
Drainage A into a concrete channel. The proposed water quality detention basin will be located at the
eastern portion of the site, which will continue to collect any excess flows from Drainage A. Permits to
connect to the existing storm drainage system will be obtained prior to construction. Therefore, the
increase in discharges will not impact local storm drain capacity. The project will not result in
substantial pollutant loading such that treatment control BMPs will be required to protect downstream
water quality. With implementation of the BMPs as noted in Section IX.a, other impacts from polluted
runoff, such as from oil and other pollutants from parking areas, will be reduced to acceptable levels.
Impacts will be less than significant.
f) No Impact. The project does not propose any uses that will have the potential to otherwise degrade
water quality beyond those issues discussed in Section IX herein. No impacts will occur.
g) No Impact. The proposed project consists of 15 self-storage buildings totaling 225,324 square feet
on 9.85 acres. According to flood maps prepared by the Federal Emergency Management Agency, the
proposed project site is not located in an area subject to inundation by the 1-percent-annual-chance
flood event.35 No impact will occur.
h) No Impact. According to flood maps prepared by the Federal Emergency Management Agency, the
proposed project site is not located in an area subject to inundation by the 1-percent-annual-chance
flood event.36 No impact will occur.
i) Less Than Significant Impact. Parts of the City of Menifee are within existing dam inundation
areas for three dams at Diamond Valley Lake, two dams at Canyon Lake, and one at Lake Perris
Reservoir. Diamond Valley Lake is located approximately 6.3 miles east of the project site, Canyon
Lake is located approximately 6.0 miles west of the project site, and Perris Reservoir is located
Planning Application No. CUP 2015-156 Page 47
approximately 13.1 miles north of the project site. The design and construction of the dams for
earthquake resistance, in combination with monitoring of the dams, reduce risks of dam failure due to
earthquakes. Dam inundation impacts will be less than significant.
j) No Impact. The project site is not subject to tsunami due to its elevation and distance (over 40 miles)
from the ocean. There are several reservoirs in the City of Menifee associated with Menifee Lakes
Country Club (north of the proposed project site). There is no possibility of a seiche from these
reservoirs affecting the project site given the project’s location being approximately 2.0 miles from the
nearest reservoir to the north. As noted in Section VI, the project site has not been identified as being
in an area susceptible to landslides, thus the potential for mudflow is relatively low because the project
does not lie in a landslide hazard zone and no natural rivers or streams are located in the project
vicinity. No impact will occur.
Planning Application No. CUP 2015-156 Page 48
X. LAND USE AND PLANNING Potentially
Significant
Impact
Less Than
Significant with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
Would the project: a) Physically divide an established
community?
b) Conflict with any applicable land use
plan, policy, or regulation of an agency with
jurisdiction over the project (including, but
not limited to the general plan, specific
plan, local coastal program, or zoning
ordinance) adopted for the purpose of
avoiding or mitigating an environmental
effect?
c) Conflict with any applicable habitat
conservation plan or natural community
conservation plan?
Sources: Menifee General Plan, Exhibit LU-2, “Land Use Map”; Menifee Zoning Map;
Applicable General Plan Policies:
Goal LU-1: Land uses and building types that result in a community where residents at all stages of
life, employers, workers, and visitors have a diversity of options of where they can live, work, shop,
and recreate within Menifee.
Policy LU-1.1: Concentrate growth in strategic locations to help preserve rural areas, create place
and identity, provide infrastructure efficiently, and foster the use of transit options.
Policy LU-1.4: Preserve, protect, and enhance established rural, estate, and residential
neighborhoods by providing sensitive and well-designed transitions (building design, landscape,
etc.) between these neighborhoods and adjoining areas.
Policy LU-1.5: Support development and land use patterns, where appropriate, that reduce reliance
on the automobile and capitalize on multimodal transportation opportunities.
Policy LU-1.6: Coordinate land use, infrastructure, and transportation planning and analysis with
regional, county, and other local agencies to further regional and subregional goals for jobs-housing
balance.
Policy LU-1.8: Ensure new development is carefully designed to avoid or incorporate natural
features, including washes, creeks, and hillsides.
Policy LU-1.9: Allow for flexible development standards provided that the potential benefits and
merit of projects can be balanced with potential impacts.
Policy LU-1.10: Buffer sensitive land uses, such as residences, schools, care facilities, and
recreation areas from major air pollutant emission sources, including freeways, manufacturing,
Planning Application No. CUP 2015-156 Page 49
hazardous materials storage, wastewater treatment, and similar uses.
Goal LU-2: Thriving Economic Development Corridors that accommodate a mix of nonresidential
and residential uses that generate activity and economic vitality in the City.
Policy LU-2.1: Promote infill development that complements existing neighborhoods and
surrounding areas. Infill development and future growth in Menifee is strongly encouraged to locate
within EDC areas to preserve the rural character of rural, estate, and small estate residential uses.
Goal ED-1: A diverse and robust local economy capable of providing employment for all residents
desiring to work in the City.
Policy ED-1.2: Diversify the local economy and create a balance of employment opportunities
across skill and education levels, wages and salaries, and industries and occupations.
Goal ED-2: A variety of retail shopping areas distributed strategically throughout the City and
regional retail, dining, and entertainment destinations in key locations with freeway access.
Policy ED-2.1: Promote retail development by locating needed goods and services in proximity to
where residents live to improve quality of life, retain taxable spending by Menifee residents, and
attract residents from outside the City to shop in Menifee.
• Locate businesses providing convenience goods and services in retail centers that are on
arterials adjacent to neighborhoods and communities throughout the City but not in rural
residential areas.
• Encourage comparison goods businesses to locate in larger retail centers located on major
arterials near freeway interchanges, because businesses that provide comparison goods
tend to draw customers from larger areas.
Policy ED-2.2: Require regional retail districts to provide entertainment and dining in addition to
retail sales and services to create destinations prepared to withstand e-commerce's increasing
capture of retail spending. These districts should create a pedestrian-friendly human-scale
atmosphere with street furniture, shading, and gathering spaces that enhance the experience of
shopping and socializing.
Local retail centers (primarily intended to serve Menifee residents) need not necessarily provide
dining and entertainment but shall provide street furniture, shading, pedestrian-circulation, and
gathering spaces that enhance the experience of shopping.
Goal ED-3: A mix of land uses that generates a fiscal balance to support and enhance the
community's quality of life.
Policy ED-3.1: Incorporate short-term and long-term economic and fiscal implications of proposed
actions into decision making.
Analysis of Project Effect and Determination of Significance:
a) No Impact. The proposed project is within a suburbanized area comprised of residential, industrial,
vacant land, and surface street features. To the north of the project site is the All Star Super Storage
facility of which the proposed project will be an expansion of and to the south of the site is a plant
nursery. Vacant land is located to the west of the project site and the I-215 is located to the east. The
proposed project is consistent and compatible with the surrounding land uses and will not divide an
Planning Application No. CUP 2015-156 Page 50
established community. The project does not propose construction of any roadway, flood control
channel, or other structure that will physically divide any portion of the community. Therefore, no
impact will occur.
b) Less Than Significant. The project site is designated as Economic Development Corridor (EDC) in
the City’s General Plan and is zoned EDC- Southern Gateway. According to the General Plan Land
Use Element, the areas designated EDC are envisioned to develop primarily as nonresidential uses,
with residential uses playing a supporting role. The EDC designation is primarily intended for uses
along corridors such as I-215. The City of Menifee has adopted the Economic Development Corridor
District Ordinance. According to the Ordinance Public Self-Storage facilities are conditionally permitted
within the EDC- Southern Gateway zone. The proposed project will comply with all development
standards set forth in. The project will also be consistent with the City’s General Plan, including policies
intended to mitigate environmental impacts as noted in other sections of this initial study. Impacts will
be less than significant.
c) Less Than Significant Impact. As discussed in Section IV above, the proposed project site is
within the planning area of the Western Riverside Multiple Species Habitat Conservation Plan
(NCCP/HCP) and complies with the provisions of that plan. Moreover, implementation of Mitigation
Measure BIO-1 will ensure that potential impacts to burrowing owls are reduced to less than significant
levels. Less than significant impacts will occur.
Planning Application No. CUP 2015-156 Page 51
XI. MINERAL RESOURCES Potentially
Significant
Impact
Less Than
Significant with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
Would the project: a) Result in the loss of availability of a
known mineral resource that would be of
value to the region and the residents of the
state?
b) Result in the loss of availability of a
locally-important mineral resource recovery
site delineated on a local general plan,
specific plan or other land use plan?
Sources: Menifee General Plan Draft EIR, Figure 5.11-1, “Mineral Resource Zones”;
Applicable General Plan Policies:
Goal OSC-4: Efficient and environmentally appropriate use and management of energy and mineral
resources to ensure their availability for future generations.
Policy OSC-4.4: Require that any future mining activities be in compliance with the State Mining
Reclamation Act, federal and state environmental regulations, and local ordinances.
Policy OSC-4.5: Limit the impacts of mining operations on the City's natural open space, biological
and scenic resources, and any adjacent land uses.
Analysis of Project Effect and Determination of Significance:
a-b) No Impact. The proposed project site is located in suburbanized area. There are no mineral
extraction or process facilities on or near the site. No mineral resources are known to exist within the
vicinity. According to the General Plan Draft EIR, no known significant mineral resources have been
designated in the City of Menifee.37 Thus, the project will not impact mineral resources.
Planning Application No. CUP 2015-156 Page 52
XII. NOISE Potentially
Significant
Impact
Less Than
Significant with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
Would the project result in: a) Exposure of persons to or generation of
noise levels in excess of standards
established in the local general plan or
noise ordinance, or applicable standards of
other agencies?
b) Exposure of persons to or generation of
excessive groundborne vibration or
groundborne noise levels?
c) A substantial permanent increase in
ambient noise levels in the project vicinity
above levels existing without the project?
d) A substantial temporary or periodic
increase in ambient noise levels in the
project vicinity above levels existing
without the project?
e) For a project located within an airport
land use plan or, where such a plan has
not been adopted, within two miles of a
public airport or public use airport, would
the project expose people residing or
working in the project area to excessive
noise levels?
f) For a project within the vicinity of a
private airstrip, would the project expose
people residing or working in the project
area to excessive noise levels?
Sources: Menifee General Plan, Noise Element; Menifee General Plan, Noise Element Exhibit N-1;
Menifee General Plan Draft EIR, Figure 5.12-3, “Airport Noise Contours”; Menifee Municipal Code;
Applicable General Plan Policies:
Goal N-1: Noise-sensitive land uses are protected from excessive noise and vibration exposure.
Policy N-1.1: Assess the compatibility of proposed land uses with the noise environment when
preparing, revising, or reviewing development project applications.
Policy N-1.2: Require new projects to comply with the noise standards of local, regional, and state
building code regulations, including but not limited to the City's Municipal Code, Title 24 of the
California Code of Regulations, the California Green Building Code, and subdivision and
development codes.
Policy N-1.3: Require noise abatement measures to enforce compliance with any applicable
regulatory mechanisms, including building codes and subdivision and zoning regulations, and
Planning Application No. CUP 2015-156 Page 53
ensure that the recommended mitigation measures are implemented.
Policy N-1.7: Mitigate exterior and interior noises to the levels listed in the table below to the extent
feasible, for stationary sources adjacent to sensitive receptors:
Table N-1
Stationary Source Noise Standards
Land Use Interior Standards Exterior Standards
Residential
10:00 p.m. to 7:00 a.m.
7:00 a.m. to 10:00 p.m.
40 Leq (10 minute)
55 Leq (10 minute)
45 Leq (10 minute)
65 Leq (10 minute)
Policy N-1.8 Locate new development in areas where noise levels are appropriate for the proposed
uses. Consider federal, state, and City noise standards and guidelines as a part of new
development review.
Policy N-1.9: Limit the development of new noise-producing uses adjacent to noise-sensitive
receptors and require that new noise-producing land be are designed with adequate noise
abatement measures.
Policy N-1.10: Guide noise-tolerant land uses into areas irrevocably committed to land uses that
are noise-producing, such as transportation corridors adjacent to the I-215 or within the projected
noise contours of any adjacent airports.
Policy N-1.11: Discourage the siting of noise-sensitive uses in areas in excess of 65 dBA CNEL
without appropriate mitigation.
Policy N-1.13: Require new development to minimize vibration impacts to adjacent uses during
demolition and construction.
Goal N-2: Minimal Noise Spillover. Minimal noise spillover from noise-generating uses, such as
agriculture, commercial, and industrial uses into adjoining noise-sensitive uses.
Fundamentals of Sound and Environmental Noise
Noise can be defined as unwanted sound. Sound (and therefore noise) consists of energy waves that
people receive and interpret. Sound pressure levels are described in logarithmic units of ratios of
sound pressures to a reference pressure, squared. These units are called bels. In order to provide a
finer description of sound, a bel is subdivided into ten decibels, abbreviated dB. To account for the
range of sound that human hearing perceives, a modified scale is utilized known as the A-weighted
decibel (dBA). Since decibels are logarithmic units, sound pressure levels cannot be added or
subtracted by ordinary arithmetic means. For example, if one automobile produces a sound pressure
level of 70 dBA when it passes an observer, two cars passing simultaneously would not produce 140
dBA. In fact, they would combine to produce 73 dBA. This same principle can be applied to other traffic
quantities as well. In other words, doubling the traffic volume on a street or the speed of the traffic will
increase the traffic noise level by 3 dBA. Conversely, halving the traffic volume or speed will reduce the
traffic noise level by 3 dBA. A 3 dBA change in sound is the beginning at which humans generally
notice a barely perceptible change in sound and a 5 dBA change is generally readily perceptible.38
Noise consists of pitch, loudness, and duration; therefore, a variety of methods for measuring noise
have been developed. According to the California General Plan Guidelines for Noise Elements, the
following are common metrics for measuring noise:39
LEQ (Equivalent Energy Noise Level): The sound level corresponding to a steady-state sound level
containing the same total energy as a time-varying signal over given sample periods. LEQ is typically
Planning Application No. CUP 2015-156 Page 54
computed over 1-, 8-, and 24-hour sample periods.
CNEL (Community Noise Equivalent Level): The average equivalent A-weighted sound level during
a 24-hour day, obtained after addition of five decibels to sound levels in the evening from 7:00pm to
10:00pm and after addition of ten decibels to sound levels in the night from 10:00pm to 7:00am.
LDN (Day-Night Average Level): The average equivalent A-weighted sound level during a 24- hour
day, obtained after the addition of ten decibels to sound levels in the night after 10:00pm and before
7:00am.
CNEL and LDN are utilized for describing ambient noise levels because they account for all noise
sources over an extended period of time and account for the heightened sensitivity of people to noise
during the night. LEQ is better utilized for describing specific and consistent sources because of the
shorter reference period.
Existing Noise Environment
The proposed project is located within a suburbanized area comprised of residential, industrial use,
vacant land, and surface street features. Existing noise conditions are representative of this
environment. Traffic noise from the I-215 Freeway, Haun Road, Wickerd Road, and Garbani Road are
the greatest contributors to ambient noise levels near the project site. There are no discernible,
substantial stationary noise sources within the area, as surrounding areas of development consists of
residential, industrial use, and vacant land.
Analysis of Project Effect and Determination of Significance:
a, d) Less Than Significant with Mitigation Incorporated. The City of Menifee Municipal Code
Section 9.09.050 (Noise Control Regulations) establishes the permissible noise level that may intrude
into a neighbor’s property. The Municipal Code establishes the exterior noise level criteria for
residential properties affected by stationary noise sources. For residential properties the exterior noise
level shall not exceed 65 dBA Leq during daytime hours (7:00 a.m. to 10:00 p.m.) and shall not exceed
45 dBA Leq during the nighttime hours (10:00 p.m. to 7:00 a.m.). In addition, the City’s General Plan
references the state Land Use Compatibility for Community Noise Environments that indicates noise
levels at residential uses are normally acceptable up to 60 dBA CNEL and conditionally acceptable up
to 70 dBA CNEL, at school uses are normally acceptable up to 70 dBA CNEL and conditionally
acceptable up to 70 dBA CNEL, and at commercial uses are normally acceptable up to 70 dBA CNEL
and conditionally acceptable up to 77.5 dBA CNEL.
Temporary Construction Noise
The project will result in temporary construction-related noise increases during on-site ground
disturbing and construction activities. Construction noise levels vary, depending on the type and
intensity of construction activity, equipment type and duration of use, and the distance between the
noise sources and the receiver.
The project consists of three separate construction phases. Phase 1 will consist of the construction of
the five western buildings (Buildings AA, BB, CC, DD, and EE) and the detention basin. Phase 2 will
consist of the construction of the four central buildings (Buildings FF, GG, HH, and II) on the site.
Phase 3 will consist of construction of the six eastern buildings (Buildings JJ, KK, LL, MM, NN, and
OO).
To provide a worst case analysis, the Roadway Construction Noise Model (RCNM) was run assuming
that all proposed buildings will be constructed as part of one phase. The proposed project will be
completed in six phases: 1) demolition, 2) site preparation, 3) grading, 4) facility construction, 5)
paving, and 6) application of architectural coatings. According to the model, the demolition phase of
construction produces the loudest noise levels. Demolition activity to occur at the southwest corner of
the storage use to the north of the site would likely require the use of a concrete saw, dozer, tractor,
Planning Application No. CUP 2015-156 Page 55
and backhoe. Operation of this equipment will also include the use of warning horns.
According to RCNM (Appendix H), noise levels due to project construction activity are expected to
range from 51.6 to 69.6 dBA Lmax at nearby industrial receiver locations and will therefore not result in
significant impacts to neighboring industrial uses. The nearest land uses that are considered sensitive
receptors are existing single-family residential dwelling units located approximately 0.15 miles south of
the project site. Section 9.09.030(B) of the City’s Municipal Code indicates that private construction
projects located within one quarter mile of an occupied residence are considered exempt from
Municipal Code noise standards if they occur within the permitted hours of 6:00 AM and 6:00 PM
during the months of June through September and between the hours of 7:00 AM and 6:00 PM during
the months of October through May, with no activity allowed on Sundays and nationally recognized
holidays. Mitigation Measures N-1 has been implemented to restrict hours of construction for the
proposed project to the hours permitted in the City’s Municipal Code. With adherence to these
construction hours, impacts related to project construction will be less than significant.
Mitigation Measures
NOI-1 Limit construction activities to the hours of between 6:00 AM to 6:00 PM during the months of
June through September and between the hours of 7:00 AM and 6:00 PM during the months of
October through May. All plans submitted to the City shall have the above noted on plans prior
issuance of grading or issuance of building permits.
On-Site Operational Noise
The proposed project is expected to create transportation noise sources typical of self-storage facilities
(cars coming and going, people talking, landscape maintenance equipment). These activities can
generate noise levels between 49 dBA (tire squeals) at 50 feet but are not expected to last for more
than a few minutes at a time and therefore are not likely to violate the City’s noise ordinance ten-
minute Leq noise level standards. Property maintenance equipment (between the hours of 7:00 AM
and 8:00 PM), safety and alarm devices, and motor vehicles are exempt from the City’s noise
standards. Project operations will not exceed City of Menifee noise standards and are not expected to
be readily audible over existing traffic noise associated with Haun Road and I-215, and therefore,
would not result in a permanent substantial increase in ambient noise levels. Impacts will be less than
significant.
Traffic Noise
A substantial increase in ambient noise is an increase that is barely perceptible (3 dBA). The Existing
and Existing Plus Project traffic noise levels at 50 feet from the roadway centerline were calculated
using TNM Version 2.5 (see Appendix H) based on average daily traffic volumes presented in the
traffic impact analysis. The Existing and Existing Plus Project traffic noise levels are summarized in
Table 8 (Existing Roadway Noise Levels). As shown in Table 8, increase in traffic noise due to the
proposed project will not result in perceptible increases in noise. Impacts will be less than significant.
Table 8
Existing Roadway Noise Levels
Roadway Segment
Existing
Existing
Plus Project
Difference Significant?
Noise Level at 100 ft from
Centerline (dBA CNEL)
Haun Road
between Garbani Rd & Project Site 70.2 70.5 +0.3 No
between Project Site & Scott Rd 70.3 70.6 +0.3 No
Scott Road
west of Haun Rd 70.5 70.7 +0.2 No
between Haun Rd & I-215 SB Ramps 72.7 73.0 +0.3 No
Planning Application No. CUP 2015-156 Page 56
It is expected that the primary source of noise impacts to the project site will be traffic noise from the I-
215 Freeway and Haun Road. The proposed self-storage use is not considered a noise-sensitive land
use. The City’s General Plan references the state Land Use Compatibility for Community Noise
Environments that indicates noise levels at industrial uses are normally acceptable up to 75 dBA CNEL
and conditionally acceptable up to 85 dBA CNEL. According to Exhibit N-1 (Future Noise Contours) of
the General Plan Noise Element, the site would be exposed to noise levels of 65 to 70 dBA CNEL on
the western portion of the site and greater than 70 dBA CNEL at the eastern portion, adjacent to the I-
215. The proposed project includes a detention basin at the eastern boundary of the site with the
eastern buildings set back approximately 150 feet from the I-215. The manager’s office for the facility is
already existing and operating as part of the existing storage facility to the north. The expansion of the
facility would not include additional offices that would expose managers to traffic noise. Expansion of
the self-storage use along the I-215 would not result in the exposure employees or residents to noise
exceeding normally or conditionally acceptable levels on a regular basis. Impacts will be less than
significant.
b) Less Than Significant Impact. Vibration is the movement of mass over time. It is described in
terms of frequency and amplitude, and unlike sound there is no standard way of measuring and
reporting amplitude. Groundborne vibration can be described in terms of displacement, velocity, or
acceleration. Each of these measures can be further described in terms of frequency and amplitude.
Displacement is the easiest descriptor to understand; it is simply the distance that a vibrating point
moves from its static position. The velocity describes the instantaneous speed of the movement and
acceleration is the instantaneous rate of change of the speed.
Although displacement is fundamentally easier to understand than velocity or acceleration, it is rarely
used for describing groundborne vibration, for the following reasons: 1) human response to
groundborne vibration correlates more accurately with velocity or acceleration; 2) the effect on
buildings and sensitive equipment is more accurately described using velocity or acceleration; and, 3)
most transducers used in the measurement of groundborne vibration actually measure either velocity
or acceleration. For this study velocity is the fundamental measure used to evaluate the effects of
groundborne vibration.
Common sources of vibration within communities include construction activities and railroads. Vibration
can impact people, structures, and sensitive equipment. The primary concern related to vibration and
people is the potential to annoy those working and residing in the area. Groundborne vibration can also
disrupt the use of sensitive medical and scientific instruments such as electron microscopes. Vibration
with high enough amplitudes can also damage structures (such as crack plaster or destroy windows).
Structural damage is generally only of concern where large construction equipment is necessary to
complete a development project (e.g. large bulldozers, vibratory pile drivers), where blasting is
required, or where very old buildings are involved (e.g. ancient ruins). Groundborne vibration
generated by construction projects is generally highest during pile driving or rock blasting. Next to pile
driving, grading activity has some potential for structural vibration impacts if large bulldozers, large
trucks, or other heavy equipment are used where very old structures are present. Construction of the
project does not require rock blasting or pile driving. Project site grading activities will require heavy
construction equipment.
Operation of the proposed project does not include uses that cause vibration. Furthermore, the project
does not require pile driving or blasting to complete, there are no ancient structures in the project
vicinity, and no research medical facilities in the vicinity that could be using sensitive medical or
scientific equipment. Potential impacts related to temporary construction activities are discussed below.
The most vibration-causing piece of equipment that will likely be used onsite as part of the proposed
Planning Application No. CUP 2015-156 Page 57
project is a vibratory roller (for paving purposes). This machine can cause vibration levels of up to 0.02
PPV at 25 feet. The nearest land uses that are considered sensitive receptors are existing single-family
residential dwelling units located approximately 0.15 miles south of the project site. Annoyance related
impacts would be short term and would only occur during site grading and preparation activities. Based
on California Department of Transportation data, haul trucks would not be anticipated to exceed 0.10
in./sec. peak particle velocity (ppv) at 10 feet.40 Based on reference vibration levels provided by the
Federal Transit Administration (FTA), the proposed project will not include or require equipment,
facilities, or activities that would result in barely perceptible human response (annoyance) for
infrequent events. Further vibration levels at the site of the closest sensitive receptor are unlikely to be
sustained during the entire construction period, but will occur rather only during the times that heavy
construction equipment is operating simultaneously at a distance of 100 feet from the project site
perimeter. Moreover, construction at the project site will be restricted to daytime hours consistent with
City requirement thereby eliminating potential vibration impacts during the sensitive nighttime hours.
Impacts related to groundborne vibration and groundborne noise levels will be less than significant.
c) Less Than Significant Impact. As discussed in Section XII a. above, operational noise impacts
associated with day-to-day use of the proposed storage facility would not exceed the City’s noise
ordinance ten-minute Leq noise level standards. As such, long-term operational noise impacts will be
less than significant.
e-f) No Impact. No airport land use plans apply to the area, and the proposed project site is not
located within two miles of an airport. No impacts related to airport land use plans or airports could
occur. There are also no private airstrips in the project vicinity; there will be no impacts related to
excessive noise near a private airstrip.
Planning Application No. CUP 2015-156 Page 58
XIII. POPULATION AND HOUSING Potentially
Significant
Impact
Less Than
Significant with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
Would the project: a) Induce substantial population growth in
an area, either directly (for example, by
proposing new homes and businesses) or
indirectly (for example, through extension
of roads or other infrastructure)?
b) Displace substantial numbers of existing
housing, necessitating the construction of
replacement housing elsewhere?
c) Displace substantial numbers of people,
necessitating the construction of
replacement housing elsewhere?
Sources: U.S. Census Bureau, Annual Estimates of the Resident Population for Incorporated Places
over 50,000; Southern California Association of Governments (SCAG) Adopted 2012 RTP Growth
Forecast.
Analysis of Project Effect and Determination of Significance:
a) Less Than Significant Impact. The proposed project would result in the expansion of a self-
storage facility; therefore, the project would not result in direct population increases. Expansion of this
self-storage facility would not generate any new employees. Management and maintenance of the
facility will be handled by the existing management and maintenance staff. The proposed project will
not generate significant amounts of new employment in the city because self-storage facilities either
require no employment or generate only a few employees. There will be no impact related to
population growth.
b) No Impact. The proposed project site is located on a primarily vacant, previously disturbed site west
of I-215, within a suburbanized area comprised of residential, industrial uses, vacant land, as well as
surface street features. The proposed project will not displace existing housing necessitating the
construction of replacement housing elsewhere. No impacts will occur.
c) No Impact. The proposed project site is located on a primarily vacant, previously disturbed site west
of I-215, within a suburbanized area comprised of residential, industrial uses, vacant land, as well as
surface street features. The proposed project will not displace any people necessitating the
construction of replacement housing elsewhere. No impacts will occur.
Planning Application No. CUP 2015-156 Page 59
XIV. PUBLIC SERVICES Potentially
Significant
Impact
Less Than
Significant with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
Would the project result in substantial adverse physical impacts associated with the provision of new or
physically altered governmental facilities, need for new or physically altered governmental facilities, the
construction of which could cause significant environmental impacts, in order to maintain acceptable
service ratios, response times or other performance objectives for any of the public services:
a) Fire protection?
b) Police protection?
c) Schools?
d) Parks?
e) Other public facilities?
Sources: Menifee General Plan Safety Element; Menifee Union School District, Perris Union High
School District and Romoland School District websites.
Applicable General Plan Policies:
Goal S-4: A community that has effective fire mitigation and response measures in place, and as a
result is minimally impacted by wildland and structure fires.
Policy S-4.1: Require fire-resistant building construction materials, the use of vegetation control
methods, and other construction and fire prevention features to reduce the hazard of wildland fire.
Policy S-4.2: Ensure, to the maximum extent possible, that fire services, such as firefighting
equipment and personnel, infrastructure, and response times, are adequate for all sections of the
City.
Policy S-4.4: Review development proposals for impacts to fire facilities and compatibility with fire
areas or mitigate.
Goal OSC-1: A comprehensive system of high quality parks and recreation programs that meets
the diverse needs of the community.
Policy OSC-1.7: Ensure that parks and recreational facilities are well-maintained by the responsible
agency.
Analysis of Project Effect and Determination of Significance:
a) Less Than Significant Impact. The Riverside County Fire Department provides fire protection and
emergency medical response services in the City of Menifee. Station No. 68 is located approximately
1.7 miles west of the proposed project site at 26020 Wickerd Road. The Riverside County Fire
Department in cooperation with the California Department of Forestry and Fire Protection serves more
than 1,360,000 residents and employs nearly 1,700 career and volunteer fire fighters and 240
administrative support personnel.41
Planning Application No. CUP 2015-156 Page 60
The project will not have a significant impact on fire response times because the project is located
within the existing service area of the Riverside County Fire Department. No new or expanded fire
protection facilities will be required as a result of this project. Impacts related to expansion of fire
protection services will be less than significant.
b) Less Than Significant Impact. The City of Menifee contracts with the Riverside County Sheriff to
provide police service for the City. The Menifee Police Department is located at 137 N. Perris
Boulevard in Perris, California approximately 9.9 miles northwest of the proposed project site. In
January 2013 the Perris Station was staffed with 138 sworn deputies and 30 classified employees,
including 33 patrol and traffic officers assigned to patrol in the City of Menifee. Average RCSD
response time to emergency calls is 7.28 minutes, and average response time for nonemergency calls
is 49.58 minutes.42
The sheriff’s department provides a crime prevention program to the City of Menifee, consisting of
support to the Neighborhood Watch program in the City and officer visits to schools and churches with
presentations on topics including drug education and personal safety.
The proposed development will not result in any unique or more extensive crime problems that cannot
be handled with the existing level of police resources. The proposed project is located within the
Riverside County Sheriff service area. No new or expanded police facilities will need to be constructed
as a result of this project. Impacts related to expansion of police protection services will be less than
significant.
c) Less Than Significant Impact. The proposed storage facility is located within the Menifee Union
School District and Perris Union High School District. The proposed project is subject to development
fees for school facilities pursuant to Senate Bill 50 (SB 50). With the payment of these development
fees, less than significant impacts will occur.
d) No Impact. Demand for park and recreational facilities are generally the direct result of residential
development. The proposed development does not include any residential development and is not a
use that will create additional demand for parkland. No impact will result.
e) No Impact. The proposed expansion of the self-storage facility will not result in new employment or
population that would create demand for additional public services. No impact will occur.
Planning Application No. CUP 2015-156 Page 61
XV. RECREATION Potentially
Significant
Impact
Less Than
Significant with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
a) Would the project increase the use of
existing neighborhood and regional parks
or other recreational facilities such that
substantial physical deterioration of the
facility would occur or be accelerated?
b) Does the project include recreational
facilities or require the construction or
expansion of recreational facilities which
might have an adverse physical effect on
the environment?
Sources: Menifee General Plan Draft EIR;
Applicable General Plan Policies:
Goal OSC-1: A comprehensive system of high quality parks and recreation programs that meets
the diverse needs of the community.
Policy OSC-1.1: Provide parks and recreational programs to meet the varied needs of community
residents, including children, youth, adults, seniors, and persons with disabilities, and make these
facilities and services easily accessible and affordable to all users.
a-b) No Impact. The proposed project includes the expansion of a storage facility. Demand for park
and recreational facilities are generally the direct result of residential development. The proposed
project, therefore, will not generate any additional demand for new or expanded park facilities which
might have an adverse physical effect on the environment. No impact will occur.
Planning Application No. CUP 2015-156 Page 62
XVI. TRANSPORTATION/TRAFFIC Potentially
Significant
Impact
Less Than
Significant with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
Would the project: a) Conflict with an applicable plan,
ordinance or policy establishing measures
of effectiveness for the performance of the
circulation system, taking into account all
modes of transportation including mass
transit and non-motorized travel and
relevant components of the circulation
system, including but not limited to
intersections, streets, highways and
freeways, pedestrian and bicycle paths,
and mass transit?
b) Conflict with an applicable congestion
management program, including, but not
limited to level of service standards and
travel demand measures, or other
standards established by the county
congestion management agency for
designated roads or highways?
c) Result in a change in air traffic patterns,
including either an increase in traffic levels
or a change in location that results in
substantial safety risks?
d) Substantially increase hazards due to a
design feature (e.g., sharp curves or
dangerous intersections) or incompatible
uses (e.g., farm equipment)?
e) Result in inadequate emergency
access?
f) Conflict with adopted policies, plans, or
programs regarding public transit, bicycle,
or pedestrian facilities, or otherwise
decrease the performance or safety of
such facilities?
Sources: Menifee General Plan Circulation Element; Riverside County Transportation Commission,
2010 Riverside County Congestion Management Program adopted March 10, 2010; Riverside Transit
Agency. 2010 Annual Report, Ride Guides and System Map; TJW Engineering, Inc., All Star Super
Storage Traffic Impact Analysis, October 19, 2015.
Applicable General Plan Policies:
Goal C-1: A roadway network that meets the circulation needs of all residents, employees, and
visitors to the City of Menifee.
Planning Application No. CUP 2015-156 Page 63
Policy C-1.1: Require roadways to:
• Comply with federal, state and local design and safety standards.
• Meet the needs of multiple transportation modes and users.
• Be compatible with the streetscape and surrounding land uses.
• Be maintained in accordance with best practices.
Policy C-1.2: Require development to mitigate its traffic impacts and achieve a peak hour Level of
Service (LOS) D or better at intersections, except at constrained intersections at close proximity to
the I-215 where LOS E may be permitted.
Policy C-1.5: Minimize idling times and vehicle miles traveled to conserve resources, protect air
quality, and limit greenhouse gas emissions.
Goal C-2: A bikeway and community pedestrian network that facilitates and encourages
nonmotorized travel throughout the City of Menifee.
Policy C-2.1: Require on- and off-street pathways to:
• Comply with federal, state and local design and safety standards.
• Meet the needs of multiple types of users (families, commuters, recreational beginners,
exercise experts) and meet ADA standards and guidelines.
• Be compatible with the streetscape and surrounding land uses.
• Be maintained in accordance with best practices.
Policy C-2.2: Provide off-street multipurpose trails and on-street bike lanes as our primary paths of
citywide travel, and explore the shared use of low speed roadways for connectivity wherever it is
safe to do so.
Policy C-2.3: Require walkways that promote safe and convenient travel between residential areas,
businesses, schools, parks, recreation areas, transit facilities, and other key destination points.
Policy C-2.4: Explore opportunities to expand the pedestrian and bicycle networks; this includes
consideration of utility easements, drainage corridors, road rights-of-way and other potential
options.
Goal C-3: A public transit system that is a viable alternative to automobile travel and meets basic
transportation needs of the transit dependent.
Policy C-3.2: Require new development to provide transit facilities, such as bus shelters, transit
bays, and turnouts, as necessary.
Goal C-4: Diversified local transportation options that include neighborhood electric vehicles and
golf carts.
Policy C-4.1: Encourage the use of neighborhood electric vehicles and golf carts instead of
Planning Application No. CUP 2015-156 Page 64
automobiles for local trips.
Goal C-5: An efficient flow of goods through the City that maximizes economic benefits and
minimizes negative impacts.
Policy C-5.3: Support efforts to reduce/eliminate the negative environmental impacts of goods
movement.
Analysis of Project Effect and Determination of Significance:
a) Less Than Significant Impact with Mitigation Incorporated. A Traffic Impact Analysis was
prepared by TJW Engineering, Inc. (Appendix I) to assess project related impacts.43 The purpose of
this TIA was to evaluate the potential circulation system deficiencies that may result from the
development of the proposed project, and recommend improvements to achieve acceptable circulation
system operational conditions. The TIA was prepared in accordance with the City of Menifee Planning
Department Traffic Impact Analysis Guidelines (August 2015).
Per the City of Menifee’s traffic study guidelines, a “significant” direct traffic impact under CEQA occurs
when the addition of projected project traffic is defined by the existing plus project scenario causes an
intersection that operates at an acceptable level of service under existing conditions to operate at an
unacceptable level of service for existing plus project conditions. Therefore, existing plus project
conditions are compared to existing conditions to identify significant, direct, project related traffic
impacts according to the following criteria:
If an intersection operating at an acceptable level of service (LOS D or better) under existing
conditions and the addition of projected project traffic causes the intersection to operate at an
unacceptable level of service (LOS E or F).
If an intersection is operating at an unacceptable level of service (LOS E or F) under existing
conditions and the addition of projected project traffic at the intersection is 50 or more peak
hour trips.
A significant cumulative impact is identified when a facility is projected to operate at an unacceptable
LOS (LOS E or F) due to cumulative future traffic and project related traffic. Cumulative traffic impacts
are the result of a combination of the proposed project and other future developments contributing to
the overall traffic impact at an intersection.
Existing Circulation Network
The characteristics of the roadway system in the vicinity of the project site are described below:
Haun Road is a two- to four-lane north-south undivided roadway. Haun Road is classified as a
four-lane divided major roadway with a 118-foot cross section in the City of Menifee General
Plan Circulation Element.
Holland Road is a two-lane east-west undivided roadway. Holland Road is classified as a four-
lane divided major roadway with a 118-foot cross section in the City of Menifee General Plan
Circulation Element. In the City of Menifee’s Capital Improvement Program (CIP), construction
of the Holland Road overcrossing of the I-215 is expected to commence construction in 2016
with a completion date in 2017. This improvement will construct Holland Road as a four-lane
major-roadway between Haun Road and Antelope Road and is expected to relieve traffic
congestion currently experienced on Newport Road and Scott Road.
Garbani Road is a two-lane undivided east-west roadway west of Haun Road. East of Haun
Road, Garbani Road is a dirt road providing access to land uses between Haun Road and I-
215. Garbani Road, in the study area, is classified as a four-lane divided major roadway with a
118-foot cross section in the City of Menifee General Plan Circulation Element.
Planning Application No. CUP 2015-156 Page 65
Scott Road is a two- to four-lane east-west roadway. Scott Road is classified as a six-lane
divided urban arterial roadway with a 152-foot cross section in the City of Menifee General Plan
Circulation Element. West of Haun Road, Scott Road is a two-lane undivided roadway; between
Haun Road and the I-215 Ramps, Scott Road is a three-lane undivided roadway with two lanes
in the westbound direction and one lane in the eastbound direction. In the City’s CIP, major
improvements are planned at the Scott Road/I-215 interchange including a major widening of
the interchange. This project is expected to commence in 2017 with a completion date in 2019.
The traffic impact analysis evaluated three intersections and four roadway segments in the vicinity of
the project site:
Haun Road at Holland Road
Haun Road at Garbani Road
Haun Road at Scott Road
Haun Road between Garbani Road and Project Site
Haun Road between Project Site and Scott Road
Scott Road west of Haun Road
Scott Road between Haun Road and I-215
The Traffic Impact Analysis analyzes the following study scenarios:
Existing Conditions
Existing Plus Project Conditions
Cumulative Plus Project Conditions.
Traffic operations are evaluated for the following time periods:
Weekday AM Peak Hour occurring between 7:00 AM and 9:00 AM
Weekday PM Peak Hour occurring between 4:00 PM and 6:00 PM
Existing Plus Project Conditions
Existing Plus Project volumes include background traffic plus the addition of project-generated traffic.
Because the proposed project is expected to be operational in 2017, Existing Plus Project volumes
include an ambient growth rate of three percent per year for two years, applied to existing traffic
volumes.
Intersection Analysis
Existing Plus Project conditions AM and PM peak hour intersection analysis is shown in Table 9
(Intersection Analysis – Existing Plus Project Conditions). Based on the thresholds of significance for
existing plus project conditions, the addition of project-generated trips will not have a significant impact
at any of the study intersections because (1) Haun Road at Garbani Road operates at a deficient LOS
pre-project, and (2) the proposed project is projected to generate less than 50 peak hour trips at the
intersection. Impacts to study area intersections under Existing Plus Project conditions will be less than
significant.
Planning Application No. CUP 2015-156 Page 66
Table 9
Intersection Analysis – Existing Plus Project Conditions
Intersection
Control
Type
Existing (2015) Existing Plus Project (2017)
Delay1 LOS Delay1 LOS
Haun Rd/Holland Rd AWSC 23.9 20.4 C C 30.4 27.5 D D
Haun Rd/Garbani Rd TWSC 170.6 23.2 F C 265.4 25.7 F D
Haun Rd/North Drwy TWSC 23.6 17.9 C C 26.1 19.3 D C
Haun Rd/Middle Drwy TWSC N/A 26/6 19.4 D C
Haun Rd/Scott Rd Signal 41.5 36.9 D D 46.3 37.8 D D
Note: AWSC = All Way Stop Control; TWSC= One- or Two-Way Stop Control; Delay shown in seconds per vehicle 1 = Per the 2010 HCM, overall average delay and LOS are shown for signalized and wall-way stop-controlled intersections. For
intersections with one- or two-way stop-control, the delay and LOS for the worst individual movement is shown.
Source: TJW Engineering, Inc., All Star Super Storage Traffic Impact Analysis, October 19, 2015
Roadway Segment Analysis
Table 10 (Roadway Segment Analysis – Existing Plus Project Conditions) summarizes the roadway
segment analysis based on the LOS E capacities provided in the Menifee General Plan Circulation
Element. As shown in Table 10, study area roadway segments operate at unacceptable LOS. The
addition of project-generated trips will not have a significant impact because roadway segments are
projected to operate at LOS E or F without the proposed project. Impacts to study area roadway
segments under Existing Plus Project conditions will be less than significant.
Table 10
Roadway Segment Analysis – Existing Plus Project Conditions
Roadway Segment
LOS E
Capacity
Existing Existing Plus Project
Project
Contribution
ADT V/C LOS ADT V/C LOS ADT V/C
Haun Rd btwn Garbani & Site 13,000 11,587 0.891 D 12,405 0.954 E 112 0.009
Haun Rd btwn Site & Scott 13,000 11,776 0.906 E 12,717 0.978 E 224 0.017
Scott Rd w/o Haun Rd 13,000 13,044 1.003 F 13,889 1.068 F 51 0.004
Scott Rd btwn Haun & I-215
SB Ramps
19,500 21,746 1.115 F 23,243 1.192 F 173 0.009
Source: TJW Engineering, Inc., All Star Super Storage Traffic Impact Analysis, October 19, 2015
Signal Warrant Analysis
Traffic signal warrants were met at the intersections of Haun Road at Holland Road and Haun Road at
Garbani Road under Existing Conditions and will continue to be met under Existing Plus Project
Conditions. Impacts will be less than significant.
Cumulative Plus Project Conditions
Under Cumulative conditions, lane configurations and traffic controls assumed to be in place under
Existing Plus Project conditions apply with the exception of project driveways and other facilities
assumed to be constructed by the proposed project to provide site access. Additionally, the Holland
Road overcrossing is assumed to be built; although no intersection improvements at the Haun
Road/Holland Road intersection are assumed.
Cumulative Plus Project volumes include background traffic plus the addition of project-generated
traffic and traffic projected to be generated by cumulative developments in the vicinity of the proposed
project which are in various stages of planning, entitlement, and construction. Since the proposed
project is projected to be operational in 2017, Cumulative Plus Project volumes include an ambient
growth rate of three percent per year for two years, applied to existing volumes.
Intersection Analysis
Cumulative Plus Project conditions AM and PM peak hour intersection analysis is shown in Table 11
(Intersection Analysis – Cumulative Plus Project Conditions). Based on the thresholds of significance
for cumulative plus project conditions, the addition of project-generated trips at the intersections of
Planning Application No. CUP 2015-156 Page 67
Haun Road/Holland Road, Haun Road/Garbani Road, and Haun Road/Scott Road will result in
cumulative impacts. In order to reduce cumulative impacts to less-than-significant levels, Mitigation
Measure TIA-1, requiring participation in the funding and/or construction of off-site improvements, has
been implemented. Within implementation of Mitigation Measure TIA-1, impacts will be less than
significant.
Table 11
Intersection Analysis – Cumulative Plus Project Conditions
Intersection
Control
Type
Cumulative Plus Project (2017)
Delay1 LOS
Haun Rd/Holland Rd AWSC 78.2 75.8 F F
Haun Rd/Garbani Rd TWSC 265.4 509.9 F F
Haun Rd/North Drwy TWSC 26.1 31.6 D D
Haun Rd/Middle Drwy TWSC 26.6 25.4 D D
Haun Rd/Scott Rd Signal 78.9 93.4 E F
Note: AWSC = All Way Stop Control; TWSC= One- or Two-Way Stop Control; Delay shown in seconds per vehicle
1 = Per the 2010 HCM, overall average delay and LOS are shown for signalized and wall-way stop-controlled
intersections. For intersections with one- or two-way stop-control, the delay and LOS for the worst individual
movement is shown.
Source: TJW Engineering, Inc., All Star Super Storage Traffic Impact Analysis, October 19, 2015
Roadway Segment Analysis
Table 12 (Roadway Segment Analysis –Cumulative Plus Project Conditions) summarizes the roadway
segment analysis based on the LOS E capacities provided in the Menifee General Plan Circulation
Element. As shown in Table 12, study area roadway segments are projected to operate at
unacceptable LOS. The addition of project-generated trips will result in cumulative impacts. In order to
reduce cumulative impacts to less-than-significant levels, Mitigation Measure TIA-1, requiring
participation in the funding and/or construction of off-site improvements, has been implemented. Within
implementation of Mitigation Measure TIA-1, impacts will be less than significant.
Table 12
Roadway Segment Analysis – Cumulative Plus Project Conditions
Roadway Segment
LOS E
Capacity
Cumulative Plus Project
ADT V/C LOS
Haun Rd btwn Garbani & Site 13,000 15,717 1.209 F
Haun Rd btwn Site & Scott 13,000 15,605 1.200 F
Scott Rd w/o Haun Rd 13,000 19,909 1.531 F
Scott Rd btwn Haun & I-215 SB Ramps 19,500 28,081 1.440 F
Signal Warrant Analysis
Traffic signal warrants were met at the intersections of Haun Road at Holland Road and Haun Road at
Garbani Road under Existing Conditions and will continue to be met under Cumulative Plus Project
Conditions. Impacts will be less than significant.
Mitigation Measure
TIA-1 The applicant shall participate in the funding or construction of off-site improvements, including
traffic signals that are needed to serve cumulative traffic conditions through the payment of the
Transportation Uniform Mitigation Fees (TUMF), City of Menifee Development Impact Fees
(DIF), and Scott Road and Bridge Benefit District Fees (Scott RBBD) or a fair share
contribution as directed by the City.
b) Less Than Significant Impact. The Congestion Management Program (CMP) in effect in Riverside
County was approved by the Riverside County Transportation Commission (RCTC) in 2010. All
freeways and selected arterial roadways in the County are designated elements of the CMP system of
Planning Application No. CUP 2015-156 Page 68
highways and roadways. There are two CMP system roadways in the City, I-215 and SR-74. RCTC
has adopted a minimum Level of Service threshold of LOS “E” for CMP facilities. Although, the CMP
indicates that I-215 in the Menifee area had a LOS “D” in 2011, the Riverside County Congestion
Management Program indicates that I-215 is "exempt" from CMP requirements in accordance with
CMP Statutes because this facility (roadway segments or intersections) had an LOS "F" in 1991.
The proposed development is located immediately west of I-215; however, project-related traffic is not
expected to significantly impact this facility with payment towards recommended roadway
improvements. Impacts to CMP facilities will be less than significant.
c) No Impact. The project site is over seven miles from Perris Valley Airport. The project site is not
located within any airport influence area. No impact will occur.
d) Less Than Significant Impact. The TIA prepared for the project includes recommendations for on-
site roadway and site access improvements to ensure that project driveway intersections and internal
circulation are safe, with adequate sight distance, driveway widths and stop signs where necessary for
entering and exiting the site. Implementation of these recommendations will prevent any project
impacts due to a design feature. The project site is bordered by an existing storage facility to the north,
vacant land to the west, a plant nursery to the south, and I-215 to the east and will not create hazards
due to incompatible uses. Impacts will be less than significant
e) No Impact. The proposed project is required to comply with Fire Department requirements for
adequate access. Project site access and circulation will provide adequate access and turning radius
for emergency vehicles, consistent with the Fire Department’s requirements. Emergency access to the
site will be maintained during construction. No impact will occur.
f) Less Than Significant Impact. The proposed project will not conflict with adopted policies, plans,
or programs regarding public transit, bicycle, or pedestrian facilities, or otherwise decrease the
performance or safety of such facilities. There are no striped Class II bicycle lanes in the study area.
Sidewalks along roadways and curb ramps at intersections are present in some locations and are
generally provided along roadway segments and at intersection corners where development has
occurred. Sidewalks are present adjacent to the existing All Star Super Storage site to the north as well
as the project’s frontage. There are no transit routes directly serving the project site, and no transit
routes within an acceptable walking distance. Additionally, the proposed self-storage use does not lend
itself to transit use by customers due to the nature of the business. The project will not decrease the
performance or safety of existing pedestrian facilities. Impacts will be less than significant.
Planning Application No. CUP 2015-156 Page 69
XVII. UTILITIES AND SERVICE
SYSTEMS Potentially
Significant
Impact
Less Than
Significant with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
Would the project: a) Exceed wastewater treatment
requirements of the applicable Regional
Water Quality Control Board?
b) Require or result in the construction of
new water or wastewater treatment
facilities or expansion of existing facilities,
the construction of which could cause
significant environmental effects?
c) Require or result in the construction of
new storm water drainage facilities or
expansion of existing facilities, the
construction of which could cause
significant environmental effects?
d) Have sufficient water supplies available
to serve the project from existing
entitlements and resources, or are new or
expanded entitlements needed?
e) Result in a determination by the
wastewater treatment provider which
serves or may serve the project that it has
adequate capacity to serve the project’s
projected demand in addition to the
provider’s existing commitments?
f) Be served by a landfill with sufficient
permitted capacity to accommodate the
project’s solid waste disposal needs?
g) Comply with federal, state, and local
statutes and regulations related to solid
waste?
Sources: Menifee General Plan;
Applicable General Plan Policies:
Goal LU-3: A full range of public utilities and related services that provide for the immediate and
long-term needs of the community.
Policy LU-3.1: Work with utility providers in the planning, designing, and siting of distribution
and support facilities to comply with the standards of the General Plan and Development Code.
Policy LU-3.2: Work with utility provides to increase service capacity as demand increases.
Policy LU-3.3: Coordinate public infrastructure improvements through the City's Capital
Planning Application No. CUP 2015-156 Page 70
Improvement Program.
Policy LU-3.4: Require that approval of new development be contingent upon the project's
ability to secure appropriate infrastructure services.
Policy LU-3.5: Facilitate the shared use of right-of-way, transmission corridors, and other
appropriate measures to minimize the visual impact of utilities infrastructure throughout
Menifee.
Goal OSC-7: A reliable and safe water supply that effectively meets current and future user
demands.
Policy OSC-7.2: Encourage water conservation as a means of preserving water resources.
Policy OSC-7.4: Encourage the use of reclaimed water for the irrigation of parks, golf courses,
public landscaped areas, and other feasible applications as service becomes available from the
Eastern Municipal Water District.
Policy OSC-7.5: Utilize a wastewater collection, treatment, and disposal system that adequately
serves the existing and long-term needs of the community.
Policy OSC-7.7: Maintain and improve existing level of sewer service by improving
infrastructure and repairing existing deficiencies.
Analysis of Project Effect and Determination of Significance:
a) Less Than Significant Impacts. The proposed project could affect Regional Water Quality Control
Board (RWQCB) treatment standards by increasing wastewater production such that expansion of
existing facilities or construction of new facilities will be required. Exceeding the RWQCB treatment
standards could result in contamination of surface or groundwater with pollutants such as pathogens
and nitrates. New development in the City is required to install wastewater infrastructure concurrent
with project development. Wastewater service within the City of Menifee is provided by Eastern
Municipal Water District.
Open drainage channels and underground storm drains larger than 36 inches in diameter are operated
and maintained by the Riverside County Flood Control and Water Conservation District (RCFCWCD);
smaller underground storm drains are operated and maintained by the City of Menifee Public Works
Department. EMWD provides wastewater treatment to the City of Menifee. Wastewater from most of
Menifee – except the north and south ends of the City – are collected at the Sun City Regional
Wastewater Reclamation Facility (RWRF) and sent to the Perris Valley RWRF for treatment.
All wastewater generated by the interior plumbing system of the proposed project will be discharged
into the local sewer system and conveyed for treatment at the Perris Valley RWRF.44 Wastewater flows
will consist of typical commercial wastewater discharges and will not require new methods or
equipment for treatment that are not currently permitted for the facility. The Perris Valley RWRF has a
capacity of treating 22 million gallons per day (mgd). Minimal wastewater flows associated with the
proposed storage facility will consist of the same kinds of substances typically generated by
maintenance of commercial uses and no modifications to any existing wastewater treatment systems
or construction of any new ones will be needed to treat this project’s wastewater. The project will have
a less than significant impact on the ability of the Perris Valley RWRF to operate within its established
wastewater treatment requirements, which are enforced via the facility’s NPDES permit authorized by
the Santa Ana Regional Water Quality Control Board (SARWQCB). Therefore, the project will have a
less than significant impact related to wastewater treatment requirements of the SARWQCB.
b) Less Than Significant Impact. The Eastern Municipal Water District (EMWD) provides water
Planning Application No. CUP 2015-156 Page 71
service to the City of Menifee. EMWD has three sources of water supply: imported water from the
Metropolitan Water District of Southern California (MWD), local groundwater, and recycled water.
Roughly 75 percent of EMWD’s potable water demand is supplied by imported water from MWD
through its Colorado River Aqueduct and connections to the State Water Project. EMWD forecasts that
it will provide water for future growth in its service area through imported water from MWD. EMWD
procures water from MWD that has been treated at MWD’s Skinner Filtration Plant in Winchester and
Mills Filtration Plant in Riverside. In 2010 EMWD obtained 75,000 acre-feet (af) of MWD water treated
at MWD filtration plants before delivery, and 16,600 af of raw MWD water treated at EMWD water
filtration plants. EMWD has two water filtration plants, one in Hemet and one in San Jacinto, with total
existing capacity of 32 million gallons per day or about 35,840 af per year. About 25 percent of
EMWD’s potable water demand is supplied by EMWD groundwater wells in the San Jacinto
Groundwater Basin. EMWD’s estimated production of potable groundwater in 2010 was 18,800 af.
EMWD’s production of desalinated groundwater in 2010 was 5,800 af. EMWD’s recycled water
production in 2010 was 41,500 af. EMWD’s territory is divided into four subareas. Parts of the City of
Menifee are in two service areas: most of the City is in Sub-Area 41, but the southeast corner is in
Sub-Area 43. Potable water sources for Sub-Area 41 are 1) Imported MWD water treated at MWD’s
Mills Filtration Plant in the City of Riverside, 2) Imported MWD water treated at EMWD’s Perris Water
Filtration Plant, 3) Local potable groundwater, and 4) Local groundwater treated at EMWD’s Menifee
Desalter.
According to the City of Menifee General Plan EIR, the projected net increase in water demands by
buildout of the General Plan – about 15mgd, or 16,800 acre-feet per year (afy) - is within EMWD
forecasts of increases in its water supplies over the 2015-2035 period. EMWD forecasts that its total
water supplies will increase by 88,300 afy over that period. The proposed project is not anticipated to
generate indoor water demand as the project consists of storage units and no restroom facilities. The
project is anticipated to demand approximately 1,270,673 gallons (3.9 afy) of water per year for
landscaping. This demand is well within the anticipated increase in water supply. There are adequate
forecast water supplies in the region for the proposed project and General Plan buildout, and no
additional water supplies will be needed. Less than significant impacts will occur.
Regarding wastewater facilities, as discussed in the preceding response, wastewater generated at the
project site is treated at the Perris Valley RWRF. The proposed project will generate minimal
wastewater to be conveyed to the Perris Valley RWRF and will be well within the existing remaining
treatment capacity of the Perris Valley RWRF.
Connections to local water and sewer mains will involve temporary and less than significant
construction impacts that will occur in conjunction with other on-site improvements. No additional
improvements are needed to either sewer lines or treatment facilities to serve the proposed project.
Standard connection fees will address any incremental impacts of the proposed project. Therefore, the
project will result in less than significant impacts as a result of new or expanded wastewater treatment
facilities.
c) Less Than Significant Impact. Potentially significant impacts could occur as a result of this project
if storm water runoff was increased to a level that would require construction of new storm drainage
facilities. As discussed in the Hydrology section, the proposed project will not generate any increased
runoff from the site that will require construction of new storm drainage facilities. All drainage will be
directed to a water quality detention basin proposed along the eastern edge of the site. A NPDES
permit will be required for the proposed project, and pursuant to the Menifee Municipal Code 15.01.015
all construction projects shall apply Best Management Practices (BMPs) to be contained in the project
applicant’s submitted Stormwater Pollution Prevention Plan (SWPPP). According to the Preliminary
Hydrology Study (Appendix F), the detention basin has been sized in accordance with the Riverside
County Flood Control and Water Conservation District criteria and that outflow from the basin is
significantly lower than the outflow under existing conditions. According to the Water Quality
Management Plan (Appendix G) prepared for the proposed project, the detention basin and the
Planning Application No. CUP 2015-156 Page 72
following source control BMPs would fully address drainage management areas and no alternative
compliance measures are required for the project.
Permanent Structural Source Control BMPs
Mark all inlets “only rain in the drain”.
Landscaping design to minimize irrigation and runoff. Specify plants tolerant to saturated
soil conditions for self-retaining areas.
Provide a means to drain fire sprinkler water to the sanitary sewer.
Operational Source Control BMPs
Maintain stencil.
Maintain landscaping using minimum or no pesticides.
Sweep sidewalks, parking lots and drive aisles regularly to prevent accumulation of litter
and debris.
Impacts will be less than significant with implementation of existing regulations and BMP’s.
d) Less Than Significant Impact. The project could result in significant impacts if the project required
additional water supplies than are currently entitled. The proposed project is not anticipated to
generate indoor water demand as the project consists of storage units and no restroom facilities. The
project is anticipated to demand approximately 1,270,673 gallons (3.9 afy) of water per year for
landscaping. According to the City of Menifee General Plan EIR, the projected net increase in water
demands by buildout of the General Plan – about 15.0 mgd, or 16,800 acre-feet per year - is within
EMWD forecasts of increases in its water supplies over the 2015-2035 period. EMWD forecasts that its
total water supplies will increase by 88,300 acre-feet per year over that period. There are adequate
forecast water supplies in the region for the proposed project, and no additional water supplies will be
needed. Less than significant impacts will occur.
e) Less Than Significant Impact. As detailed in Sections XVII.a and XVII.b, the proposed project will
be adequately served by existing facilities. Therefore, less than significant impacts will occur.
f) Less Than Significant Impact. Significant impacts could occur if the proposed project will exceed
the existing permitted landfill capacity or violates federal, state, and local statutes and regulations.
Solid waste from Menifee is collected by Waste Management, Inc. (WMI).
The proposed project’s additional solid waste stream will have a less than significant impact on
regional landfill capacity. During 2014, the City of Menifee utilized four landfills: Badlands Sanitary
Landfill, El Sobrante Landfill, Lamb Canyon Sanitary Landfill, Mid-Valley Sanitary Landfill, and Simi
Valley Landfill and Recycling Center.45 Badlands Sanitary Landfill has a maximum daily capacity of
4,000 tons per day and a maximum capacity of 33,560,993 cubic yards. The remaining capacity is
14,730,025 cubic yards and it is scheduled to cease operation in January 2024. El Sobrante Sanitary
Landfill has a maximum daily capacity of 16,054 tons per day and a maximum capacity of 184,930,000
tons. The remaining capacity is 145,530,000 tons and it is scheduled to cease operation in January
2045. Lamb Canyon Landfill has a maximum daily capacity of 3,000 tons per day and a maximum
capacity of 34,292,000 cubic yards. The remaining capacity is 18,955,000 cubic yards and it is
scheduled to cease operation in April 2021. Mid-Valley Sanitary Landfill has a maximum daily capacity
of 7,500 tons per day and a maximum capacity of 101,300,000 cubic yards. The remaining capacity is
67,520,000 cubic yards and it is scheduled to cease operation in April 2033. Simi Valley Landfill and
Recycling Center has a maximum daily capacity of 9,250 tons per day and a maximum capacity of
119,600,000 cubic yards. The remaining capacity is 119,600,000 cubic yards and it is scheduled to
cease operation in January 2052.46
Considering the availability of landfill capacity and the relatively nominal amount of solid waste
generation from the proposed project, project solid waste disposal needs can be adequately met
Planning Application No. CUP 2015-156 Page 73
without a significant impact on the capacity of the nearest and optional, more distant, landfills.
Therefore, it is not expected that the proposed project will impact the City’s compliance with state-
mandated (AB 939) waste diversion requirements. Impacts will be less than significant.
g) No Impact. The proposed project is required to comply with all applicable federal, state, County,
and City statutes and regulations related to solid waste as a standard project condition of approval.
Therefore, no impact will occur.
Planning Application No. CUP 2015-156 Page 74
XVIII. MANDATORY FINDINGS OF
SIGNIFICANCE Potentially
Significant
Impact
Less Than
Significant with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
a) Does the project have the potential to
degrade the quality of the environment,
substantially reduce the habitat of a fish or
wildlife species, cause a fish or wildlife
population to drop below self-sustaining
levels, threaten to eliminate a plant or
animal community, reduce the number or
restrict the range of a rare or endangered
plant or animal or eliminate important
examples of the major periods of California
history or prehistory?
b) Does the project have impacts that are
individually limited, but cumulatively
considerable? ("Cumulatively
considerable" means that the incremental
effects of a project are considerable when
viewed in connection with the effects of
past projects, the effects of other current
projects, and the effects of probable future
projects)?
c) Does the project have environmental
effects which will cause substantial
adverse effects on human beings, either
directly or indirectly?
a) Less Than Significant with Mitigation Incorporated. The proposed project will not substantially
impact any scenic vistas, scenic resources, or the visual character of the area, as discussed in Section
I and will not result in excessive light or glare. The project site is located within an urbanized area with
little-to-no natural habitat. However, there is potential for burrowing owls to occur on site. As such,
Mitigation Measure B-1 will reduce potential impacts to burrowing owls in the project area to less than
significant levels. Mitigation Measure B-2 will ensure that impacts to nesting birds will be less than
significant. Adverse impacts to historic, paleontological resources, or human remains will not occur.
Construction-phase procedures will be implemented in the event any important archaeological or
paleontological resources are discovered during grading, consistent with Mitigation Measures C-1
through C-7. This site is not known to have any association with an important example of California’s
history or prehistory. The environmental analysis provided in Section III concludes that impacts related
to emissions of criteria pollutants and other air quality impacts will be less than significant with
implementation of Mitigation Measure AQ-1. Sections VII and IX conclude that impacts related to
climate change and hydrology and water quality will be less than significant. Based on the preceding
analysis of potential impacts in the responses to items I thru XVII, no evidence is presented that this
project will degrade the quality of the environment. The City hereby finds that impacts related to
degradation of the environment and cultural resources will be less than significant with mitigation
incorporation.
b) Less Than Significant with Mitigation Incorporated. Cumulative impacts can result from the
interactions of environmental changes resulting from one proposed project with changes resulting from
Planning Application No. CUP 2015-156 Page 75
other past, present, and future projects that affect the same resources, utilities and infrastructure
systems, public services, transportation network elements, air basin, watershed, or other physical
conditions. Such impacts could be short-term and temporary, usually consisting of overlapping
construction impacts, as well as long term, due to the permanent land use changes and operational
characteristics involved with the project.
Section 15130(b)(1) of the CEQA Guidelines identifies two methods to determine the scope of related
projects for cumulative impact analysis:
List-of-Projects Method: a list of past, present, and probable future projects producing related or
cumulative impacts, including, if necessary, those projects outside the control of the agency.
Summary-of-Projections Method: a summary of projections contained in an adopted general plan or
related planning document or in a prior environmental document that has been adopted or certified,
which described or evaluated regional or area wide conditions contributing to the cumulative impact.
Any such planning document shall be referenced and made available to the public at a location
specified by the lead agency. The proposed project is consistent with the City of Menifee General Plan,
AQMP, and the CMP. Therefore, cumulative impacts will be less than significant
Non-Cumulative Impacts
Impacts related to geology and soils, and airport hazards at the project-level have no potential for
cumulative impacts because impacts are limited to on-site conditions and include no component that
could result in similar impacts over time or space. Therefore, no cumulative impacts related to these
topics will occur.
Local Impacts
Projects can contribute considerably to cumulative impacts in context of the local environment. Local
cumulative impacts are limited to agricultural and forestry resources, air quality, biological resources,
cultural resources, hazardous materials, groundwater levels, drainage and water quality, land use and
planning, mineral resources, noise, population and housing, public services, recreation, transportation
and traffic, and utilities and service systems. A general discussion of potentially significant cumulative
impacts in the local context is summarized below.
The analysis provided in Section XV found that no individual impacts will occur; therefore, the project
will not contribute considerably to recreation impacts. The analysis also found that no impacts to
mineral resources would occur. The analyses related to aesthetics, agricultural resources, geology and
soils, hazards and hazardous materials, hydrology and water quality, land use and planning,
population and housing, public services, recreation, and utilities and services systems found that
impacts will be less than significant; therefore, while the project will contribute to localized cumulative
impacts, the project contribution will not be considerable.
Impacts related to air quality, biological resources, cultural resources, noise, and traffic and
transportation were found to be potentially significant and require mitigation to reduce to less than
significant levels; therefore, the project could contribute considerably to significant regional cumulative
impacts in these topical areas. These topics are discussed in detail below.
Air Quality. The context for assessing cumulative air quality impacts to the area is the extent to which
project related emissions will contribute to a net increase of any criteria pollutant for which the project
region is in non-attainment. The proposed project requires implementation of Mitigation Measure AQ-1
to reduce emissions of VOC during construction. Impacts will be mitigated to less than significant
levels; therefore, the project will have no cumulative contribution to local air quality impacts.
Biological Resources. The context for assessing local cumulative biological resources impacts is the
extent to which project related construction will contribute to or result on the disturbance of habitat
Planning Application No. CUP 2015-156 Page 76
critical to endangered and/or protected species. To protect against significant impacts to burrowing
owls, the project will implement Mitigation Measure B-1, which requires a 30-day preconstruction
survey for burrowing owl as required by the Western Riverside County Multiple Species Habitat
Conservation Plan (MSHCP). If burrowing owls are discovered during pre-construction surveys, buffers
will be erected to reduce impacts to less than significant levels. Mitigation Measure B-2 requires
nesting bird surveys prior to removal of vegetation on the project site to ensure that impacts to nesting
birds are less than significant. Implementation of Mitigation Measures B-1 and B-2 will eliminate any
destruction of critical habitat in the immediate area; therefore, the project will have no cumulative
contribution to local biological resource impacts.
Cultural Resources. The context for assessing cumulative impacts to local archeological knowledge of
our past is the geographical extent of regional and statewide historic and prehistoric knowledge. Loss
of on-site archaeological resources could reduce or eliminate important information relevant to the San
Jacinto Basin and the State of California. Mitigation Measures C-1 through C-5 have been incorporated
requiring construction monitoring and evaluation of any discovered potential archaeological or
paleontological resources, the uniqueness of the archaeological or paleontological sample or ancestry
of the remains, and appropriate steps to preserve or curate the artifact or remains. Mitigation Measures
C-1 through C-5 will eliminate any potential loss of important regional archaeological or paleontological
information that may be buried under the project site; therefore, the project will have no contribution to
a cumulative loss of important local archaeological knowledge. Mitigation Measures C-6 and C-7 have
been incorporated to ensure compliance with State Health and Safety Codes in regards to buried
human remains and associated grave goods.
Noise. The context for assessing local cumulative noise impacts is the extent to which temporary or
permanent noise generating sources exist in the area. Noise generating sources can create
annoyance to residents and can cause vibration impacts. Mitigation Measure N-1 has been
incorporated requiring construction activities to be limited to between the hours of 6:00 AM to 6:00 PM
during the months of June through September and between the hours of 7:00 AM and 6:00 PM during
the months of October through May. This will eliminate any noise impacts resulting from construction of
the proposed project site; therefore, the project will have no local contribution to cumulative noise
impacts.
Traffic and Transportation. The context for assessing cumulative impacts on the regional transportation
system is the extent to which project-generated trips will pass through regional transportation facilities
such as freeway on and off ramps and Congestion Management Program (CMP) intersections or
roadway segments. The analysis provided in Section XVI.A found that the project would contribute
considerably to traffic impacts. Therefore, Mitigation Measure T-1 has been incorporated to require the
applicant to participate in the funding of off-site improvements, including intersections that are needed
to serve cumulative traffic conditions through the payment of Western Riverside County TUMF, City of
Menifee Development Impact Fees (DIF), or RBBD fees, as directed by the City. These fees are
collected as part of a funding mechanism aimed at ensuring that regional highways and arterial
expansions keep pace with the projected population increases. Lastly, Section XVI.B found that no
CMP facilities will be impacted by the project.
Regional Impacts
Projects can contribute considerably to cumulative impacts in context of the regional environment.
Regional cumulative impacts are limited to air quality, biological resources, cultural resources,
hazardous materials, wildfires, groundwater levels, drainage and water quality, flooding, land use and
planning, mineral resources, noise, transportation and traffic, and utilities and service systems. A
general discussion of potentially significant cumulative impacts in the regional context is summarized
below.
No impacts related to mineral resources were identified. The analysis provided related to aesthetics,
agricultural and forest resources, geology and soils, hazards and hazardous materials, wildfires,
Planning Application No. CUP 2015-156 Page 77
groundwater levels, drainage and water quality, flooding, land use and planning, population and
housing, public services, recreation, and utilities and services systems found that impacts will be less
than significant; therefore, while the project will contribute to regional cumulative impacts, the project
contribution will not be considerable.
Impacts related to air quality, biological resources, cultural resources, noise, and traffic and
transportation were found to be potentially significant and require mitigation to reduce to less than
significant levels; therefore, the project could contribute considerably to significant regional cumulative
impacts in these topical areas. These topics are discussed in detail below.
Air Quality. The context for assessing cumulative air quality impacts to the area is the extent to which
project related emissions will contribute to a net increase of any criteria pollutant for which the project
region is in non-attainment. The proposed project requires implementation of Mitigation Measure AQ-1
to reduce emissions of VOC during construction. Impacts will be mitigated to less than significant
levels; therefore, the project will have no cumulative contribution to regional air quality impacts.
Biological Resources. The context for assessing cumulative biological resources impacts in the region
is the extent to which project related construction will contribute to or result on the disturbance of
habitat critical to endangered and/or protected species. To protect against significant impacts to
burrowing owls, the project will implement Mitigation Measure B-1, which requires a 30-day
preconstruction survey for burrowing owl as required by the Western Riverside County Multiple
Species Habitat Conservation Plan (MSHCP). If burrowing owls are discovered during pre-construction
surveys, buffers will be erected to reduce impacts to less than significant levels. Mitigation Measure B-
2 requires nesting bird surveys prior to removal of vegetation on the project site to ensure that impacts
to nesting birds are less than significant. Implementation of Mitigation Measures B-1 and B-2 will
eliminate any destruction of critical habitat in the region; therefore, the project will have no cumulative
contribution to regional biological resource impacts.
Cultural Resources. The context for assessing cumulative impacts to regional archeological knowledge
of our past is the geographical extent of regional and statewide historic and prehistoric knowledge.
Loss of on-site archaeological resources could reduce or eliminate important information relevant to
the San Jacinto Basin and the State of California. Mitigation Measures C-1 through C-5 have been
incorporated requiring construction monitoring and evaluation of any discovered potential
archaeological or paleontological resources, the uniqueness of the archaeological or paleontological
sample or ancestry of the remains, and appropriate steps to preserve or curate the artifact or remains.
Mitigation Measures C-1 through C-5 will eliminate any potential loss of important regional
archaeological or paleontological information that may be buried under the project site; therefore, the
project will have no contribution to a cumulative loss of important regional archaeological or
paleontological knowledge. Mitigation Measures C-6 and C-7 have been incorporated to ensure
compliance with State Health and Safety Codes in regards to buried human remains and associated
grave goods.
Noise. The context for assessing cumulative noise impacts in the region is the extent to which
temporary or permanent noise generating sources exist in the area. Noise generating sources can
create annoyance to residents and can cause vibration impacts. Mitigation Measure N-1 has been
incorporated requiring construction activities to be limited to between the hours of 6:00 AM to 6:00 PM
during the months of June through September and between the hours of 7:00 AM and 6:00 PM during
the months of October through May. This will eliminate any noise impacts resulting from construction of
the proposed project site. The proposed project will not result in permanent increase in traffic noise;
therefore, the project will have no local contribution to cumulative noise impacts.
Traffic and Transportation. The context for assessing cumulative impacts on the regional transportation
system is the extent to which project-generated trips will pass through regional transportation facilities
such as freeway on and off ramps and Congestion Management Program (CMP) intersections or
Planning Application No. CUP 2015-156 Page 78
roadway segments. The analysis provided in Section XVI.A found that the project would contribute
considerably to traffic impacts. Therefore, Mitigation Measure T-1 has been incorporated to require the
applicant to participate in the funding of off-site improvements, including intersections that are needed
to serve cumulative traffic conditions through the payment of Western Riverside County TUMF, City of
Menifee Development Impact Fees (DIF), or RBBD fees, as directed by the City. These fees are
collected as part of a funding mechanism aimed at ensuring that regional highways and arterial
expansions keep pace with the projected population increases. Lastly, Section XVI.B found that no
CMP facilities will be impacted by the project.
Global Impacts
One topic of global concern is climate change. As discussed in Section VII, climate change is the result
of numerous, cumulative sources of greenhouse gas emissions all over the world. The project will not
contribute considerably to global climate change.
Based on the above analysis concerning the local, regional, and global impacts of the project in
consideration of past, current, and future projects, the City hereby finds that the contribution of the
proposed project to cumulative impacts will be less than significant with mitigation incorporation.
c) Less Than Significant with Mitigation Incorporation. Based on the analysis of the project’s
impacts in the responses to items I thru XVII, there is no indication that this project will result in
substantial adverse effects on human beings. While there will be a variety of temporary adverse effects
during construction related to air quality and noise, these will be reduced to less than significant levels
through mitigation. Long-term effects include increased vehicular traffic, traffic related noise, and
emissions of criteria pollutants. The analysis herein concludes that direct and indirect environmental
effects will at worst require mitigation to reduce to less than significant levels. Generally, environmental
effects will result in less than significant impacts. Based on the analysis in this Initial Study, the City
finds that direct and indirect impacts to human beings will be less than significant with mitigation
incorporation.
XIX. EARLIER ANALYSES
Earlier analyses may be used where, pursuant to the tiering, program EIR, or other CEQA process, an effect
has been adequately analyzed in an earlier EIR or negative declaration as per California Code of
Regulations, Section 15063 (c) (3) (D).
XX. REFERENCES
1 California Department of Transportation. California Scenic Highway Program. Riverside County.
http://www.dot.ca.gov/hq/LandArch/16_livability/scenic_highways/index.htm [Accessed March 17, 2016].
2 City of Menifee General Plan. Community Design Element. Exhibit CD-2: Enhanced Landscape
Corridors and Scenic Corridors. 2013.
3 California Department of Transportation. California Scenic Highway Program. Riverside County.
http://www.dot.ca.gov/hq/LandArch/scenic_highways/index.htm [Accessed January 28, 2016].
4 City of Menifee General Plan. Community Design Element. Exhibit C-8: Scenic Highways. 2012.
5 California Department of Conservation. Riverside County Important Farmland Map Sheet 1 of 3. 2012.
6 California Department of Conservation. Riverside County Important Farmland Map Sheet 1 of 3. 2012.
7 City of Menifee General Plan Draft EIR. Agricultural Resources. Page 5.2-13.
8 California Department of Conservation. Williamson Act Program. Riverside County Williamson Act FY
2008/2009 Sheet 1 of 3.
9 City of Menifee General Plan Draft EIR. Agricultural Resources. Page 5.2-13.
10 South Coast Air Quality Management District. CEQA Air Quality Handbook. 1993.
11 TJW Engineering, Inc. All Star Super Storage Traffic Impact Analysis: City of Menifee, California Project
#2015-156. March 16, 2016.
12 U.S. Fish and Wildlife Service. Critical Habitat Portal. http://ecos.fws.gov/crithab/ [Accessed March 18,
2016].
Planning Application No. CUP 2015-156 Page 79
13 California Department of Fish and Wildlife. Natural Community Conservation Planning (NCCP) Summary
Table. https://www.wildlife.ca.gov/Conservation/Planning/NCCP [Accessed March 23, 2016].
14 Glenn Lukos Associates, Inc. Biological Technical Report for the All Star Super Storage Project 2015-
156. September 22, 2015.
15 U.S. Fish & Wildlife Service. National Wetland Inventory.
https://www.fws.gov/wetlands/Data/Mapper.html [August 2016]
16 National Park Service. National Register of Historic Places. http://www.cr.nps.gov/nr/research/ [Accessed
March 24, 2016].
17 California State Parks Office of Historic Preservation. California Historical Resources: Riverside County.
http://ohp.parks.ca.gov/listedresources/ [Accessed March 24, 2016].
18 Scientific Resource Surveys, Inc. Phase 1 Cultural Resources/Archaeological Study: All Star Super
Storage. October 1, 2015
19 Scientific Resource Surveys, Inc. Phase 1 Cultural Resources/Archaeological Study: All Star Super
Storage. October 1, 2015
20 California Department of Conservation. Alquist-Priolo Maps.
http://www.quake.ca.gov/gmaps/WH/regulatorymaps.htm [Accessed March 17, 2016].
21 California Department of Conservation. http://www.quake.ca.gov/gmaps/WH/regulatorymaps.htm
[Accessed March 17, 2016].
22 California Air Pollution Control Officers Association. CEQA and Climate Change. January 2008
23 South Coast Air Quality Management District. CEQA Significance Thresholds Working Group. Meeting
# 15, Main Presentation. September 28, 2010
24 California Air Pollution Control Officers Association. CEQA and Climate Change. January 2008.
25 City of Menifee General Plan Draft EIR. Section 5.7 Greenhouse Gas Emissions. p. 5.7-23.
26 California Water Resources Control Board. GeoTracker. http://geotracker.waterboards.ca.gov/
[Accessed March 24, 2016].
27 California Environmental Protection Agency. Cortese List Data Resources.
http://www.calepa.ca.gov/sitecleanup/corteselist/ [Accessed March 24, 2016].
28 California Environmental Protection Agency. DTSC’s Hazardous Waste and Substances Site List
(Cortese List). http://www.dtsc.ca.gov/SiteCleanup/Cortese_List.cfm [Accessed March 24, 2016].
29 California Water Resources Control Board. Geotracker. https://geotracker.waterboards.ca.gov/
[Accessed March 24, 2016].
30 California Water Resources Control Board. List of Solid Waste Disposal Sites.
http://www.calepa.ca.gov/sitecleanup/corteselist/CurrentList.pdf [Accessed March 24, 2016].
31 California Environmental Protection Agency. List of Active CDO and CAO.
http://www.calepa.ca.gov/sitecleanup/corteselist/ [Accessed March 24, 2016].
32 California Environmental Protection Agency. List of Hazardous Waste Facilities Subject to Corrective
Action Pursuant to Section 25187.5 of the Health and Safety Code.
http://www.calepa.ca.gov/sitecleanup/corteselist/SectionA.htm#Facilities [Accessed March 24, 2016].
33 California Department of Forestry and Fire Protection (CAL FIRE). Riverside County City Fire Hazard
Severity Zone Maps. http://www.fire.ca.gov/fire_prevention/fhsz_maps_riverside_city_maps.php
[Accessed March 24, 2016].
34 City of Menifee. City of Menifee General Plan Draft EIR. Figure 5.9-2 (Groundwater Basins).
35 Federal Emergency Management Agency. Flood Insurance Rate Maps. FIRM Panel 06065C2070H.
August 18, 2008.
36 Federal Emergency Management Agency. Flood Insurance Rate Maps. FIRM Panel 06065C2070H.
August 18, 2008.
37 City of Menifee General Plan Draft EIR. Figure 5.11-1 Mineral Resource Zones. September 2013.
38 California Department of Transportation. Basics of Highway Noise: Technical Noise Supplement.
November 2009.
39 California Governor’s Office of Planning and Research. General Plan Guidelines. 2003.
40 California Department of Transportation. Division of Environmental Analysis. Technical Noise
Supplement. November 2009.
41 Riverside County Fire Department in Cooperation with CAL Fire. 2014 Annual Report.
Planning Application No. CUP 2015-156 Page 80
42 City of Menifee General Plan Draft EIR. Public Services. September 2013.
43 TJW Engineering, Inc. All Star Super Storage Traffic Impact Analysis: City of Menifee, California Project
#2015-156. March 16, 2016.
44 City of Menifee General Plan Draft EIR. Utilities and Service Systems. September 2013.
45 CalRecycle. Jurisdiction Disposal by Facility. Disposal during 2012 for Menifee.
http://www.calrecycle.ca.gov/lgcentral/Reports/DRS/Destination/JurDspFa.aspx [Accessed February 2,
2016].
46 CalRecycle. Detailed Facility Search. http://www.calrecycle.ca.gov/FacIT/facility/search.aspx [Accessed
February 2, 2016].