California Professional Engineering, Inc.PRELIMINARY NOTICE CALIFORNIA City of Menifee
USE PROOF OF SERVICE AFFIDAVIT OF CALIFORNIA 20-DAY PRELIMINARY NOTI2ty Clerk
(PRIVATE AND PUBLIC WORK)
CONSTRUCTION LENDER
(Or Reputed Construction Lender, if Any)
Construction loan no. (if known)
OWNER Or PUBLIC AGENCY AND
Or Reputed Owner DISBURSING OFFICER
(On Private Work) (On Public Work)
CITY OF MENIFEE
29844 HAUN ROAD
MENIFEE, CA 92586
DIRECT CONTRACTOR
(Or Reputed Direct Contractor)
California Professional Engineering Inc
929 Otterbein Ave, Unit E
La Puente, CA 91748
SUBCONTRACTOR
(Or Reputed Subcontractor)
SUB -SUBCONTRACTOR
(Or Reputed Sub -Subcontractor)
SUB -SUB -SUBCONTRACTOR
(Or Reputed Sub -Sub -Subcontractor)
BOND COMPANY
THE BOND EXCHANGE
24800 CHRISANTA DRIVE, SUITE 160
Mission Viejo, CA 92691
* * * * Joint Check Requested * * * *
An estimate of the total price of the labor, services,
equipment or materials furnished or to be furnished is:
$88,600.00
Statement or estimate of the Claimant's demand for sums
currently due after deducting all just credits and offsets:
$0.00
8202 AND 9300-9303 CALIFORNIA CIVIL CODE
YOU ARE HEREBY NOTIFIED THAT...
McCain, Inc.
2365 Oak Ridge Way R e c e € w: 4'
Vista, CA 92081
(Ms. Linh Trinh
Telephone: (760) 734-5009; Email: ltrinh@mccain-inc.com)
(name and address of person or firm — sender)
has furnished or will furnish materials of the following general
description:
Traffic Signals and related material
for the building, structure or other work of improvement located at:
Job #1958 ORD #4515081,4515083 Traffic Signals at McCall
Blvd and Oakhurst Ave and Murrieta Rd and Park City
CIP 19-04 & CIP 19-05
McCall Blvd/Oakhurst Ave/Murrieta Rd/ and Park City
Menifee, CA
The name of the person or firm who contracted for the purchase
of such labor, services equipment or materials:
California Professional Engineering Inc
NOTICE TO PROPERTY OWNER
EVEN THOUGH YOU HAVE PAID YOUR CONTRACTOR IN FULL,
if the person or firm that has given you this notice is not paid in full for
labor, service, equipment, or material provided or to be provided to your
construction project, a lien may be placed on your property. Foreclosure of
the lien may lead to loss of all or part of your property. You may wish to
protect yourself against this by (1) requiring your contractor to provide a
signed release by the person or firm that has given you this notice before
making payment to your contractor, or (2) any other method that is
appropriate under the circumstances.
This notice is required by law to be served by the undersigned as a
statement of your legal rights. This notice is not intended to reflect upon
the financial condition of the contractor or the person employed by you on
the construction project.
If you record a notice of cessation or completion of your construction
project, you must within 10 days after recording, send a copy of the notice
of completion to your contractor and the person or firm that has given you
this notice. The notice must be sent by registered or certified mail. Failure
to send the notice will extend the deadline to record a claim of lien. You are
not required to send the notice if you are a residential homeowner of a
dwelling containing four or fewer units.
Claimant's Notice of unpaid compensation & employer g to
laborers & entities (described in Civil C ]): The names and
addresses of the laborer(s) and t Fund to whom compensation and
employer payments is' and payable are:
( 'ames)
(Addffi-ws)
Mailed this date: September 11, 2019