L C Paving & Sealing IncSUPERIOR READY MIX CALIFORNIA
1508 W MISSION RD
ESCONDIDO CA 92029
PRELIMINARY
7136 0615 0661 1127 6283 NOTICE
811959 87
THIS IS NOT A LIEN. THIS NOTICE IS GIVEN PURSUANT TO
City of Menifee SECTIONS 8034(a), 8102, 8200 et seq, CALIFORNIA CIVIL
City Clerk CODE. THIS IS NOT A REFLECTION ON THE INTEGRITY OF
ANY CONTRACTOR OR SUBCONTRACTOR.
CITY OF MENIFEE UUN $ O 2018
29714 HAUN ROAD YOU ARE HEREBY NOTIFIED THAT....
MENIFEE CA 92586- Received
SUPERIOR READY MIX CONCRETE L.P.
1508 W MISSION RD
ESCONDIDO CA 92029
OWNER or Reputed Owner (on private work) 02
or PUBLIC AGENCY (on public work)
CITY OF MENIFEE
29714 HAUN ROAD
MENIFEE CA, 92586-
CONSTRUCTION LENDER/Surety or
Reputed Construction Lender/Surety, If any.
B B & T INSURANCE SERVICES
750 B STREET S# 2400
SAN DIEGO CA, 92101-
DIRECT CONTRACTOR or
Reputed Contractor, if any 03
L C PAVING & SEALING INC
330 RANCHEROS DRIVE STE 208
SAN MARCOS CA, 92069-
SUB CONTRACTOR/person or firm who contracted for the
purchase of such labor, services, equipment or materials is:
L C PAVING & SEALING INC
330 RANCHEROS DRIVE STE 208
SAN MARCOS CA, 92069
OTHER INFORMATION, if any.
Owner Copy
has furnished or will famish labor, services, equipment or
materials of the following general description:
READY MIX CONCRETE,
SAND AND/OR ROCK
for the building, structure or other work of Improvement
located at:
NEWPORT RD. & MENIFEE ST. IMPROVEMENTS
NEWPORT RD. & MENIFEE RD.
MENIFEE
An estimate of the total price of labor, services, equipment
or materials furnished or to be furnished is:
$50,000.00
By Prelim Manager Dated: 06/18/2018
(Signature) (Title)
NOTICE TO PROPERTY OWNER
EVEN THOUGH YOU HAVE PAID YOUR CONTRACTOR IN FULL, if the person
or firm that has given you this notice is not paid in full for labor, service,
equipment, or material provided or to be provided to your construction
project, a lien may be placed on your property. Foreclosure of the lien may
lead to loss of all or part of your property. You may wish to protect yourself
against this by (1) requiring your contractor to provide a signed release by
the person or firm that has given you this notice before making payment to
your contractor, or (2) any other method that is appropriate under the
circumstances. This notice is required by law to be served by the
undersigned as a statement of your legal rights. This notice is not intended
to reflect upon the financial condition of the contractor or the person
employed by you on the construction project. If you record a notice of
cessation or completion of your construction project, you must within 10
days after recording, send a copy of the notice of completion to your
contractor and the person or firm that has given you this notice. The notice
must be sent by registered or certified mail. Failure to send the notice will
extend the deadline to record a claim of lien. You are not required to send the
notice if you are a residential homeowner of a dwelling containing four or
fewer units.
PROOF OF SERVICE BY MAIL AFFIDAVIT
I, Jesie Walker, declare that I served copies of the above PRELIMINARY NOTICE by First Class Certified, postage prepaid, addressed to each of
the parties at the addresses shown above on 06118/2018. 1 declare under penalty of perjury under the laws of the State of California that the
foregoing is true and correct.
BY: lJ Jesie Walker, Agent
Executed at ESCONDIDO, California on 06/18/2018