RIC Construction - Fire Station 7 Bradley RdPRELIMINARY 20-DAY NOTICE
IN ACCORDANCE WITH SECTIONS 8200 et seq. AND 9300 et seq., CALIFORNIA CIVIL CODE,
THIS IS NOT A REFLECTION OF THE INTEGRITY OF ANY CONTRACTOR OR SUBCONTRACTOR.
NOTICE TO:
(Identify Name & Address of Party)
PROPERTY OWNER
City of Menifee
29714 Haun Rd
Menifee, Ca 92586
PRIME CONTRACTOR
R I C Construction Co Inc
10675 E Ave
Hesperia, Ca 92345
CONSTRUCTION LENDER
NOTICE FROM ("CLAIMANT"):
(Identify Name & Address & Phone)
Valley Industrial Mechanical
PO Box 3457
Victorville, Ca 92393
(760) 963-2598
NOTICE TO PROPERTY OWNER
YOU ARE HEREBY NOTIFIED THAT the CLAIMANT, has
furnished or will be furnishing labor, services, equipment,
or materials, of the following general description:
(Identify Work/Materials Provided by Claimant)
Plumbing and site utilities
These services have been contracted for by:
(Identify Name & Address of Party Who Hired Claimant)
R I C Construction Co Inc, 10675 E Ave, Hesperia, Ca 92345
An estimate of the total price of the labor, services,
equipment or material furnished or to be furnished is
$ 118,604.97
Property Address where labor, services, equipment or
materials is furnished or to be furnished:
(Identify Name & Address of Party Who Hired Claimant)
Fire Station #7, 28349 Bradley Rd, Menifee, Ca 92586
EVEN THOUGH YOU HAVE PAID YOUR CONTRACTOR IN FULL, if the person or firm that
has given you this notice is not paid in full for labor, service, equipment, or material
provided or to be provided to your construction project, a lien may lead to loss of all or
part of your property. You may wish to protect yourself against this by (1) requiring
your contractor to provide a signed release by the person or firm that has given you this
notice before making payment to your contractor, or (2) any other method that is
appropriate under the circumstances.
This notice is required by law to be served by the undersigned as a statement of your
legal rights. This notice is not intended to reflect upon the financial condition of the
contractor or the person employed by you on the construction project.
If you record a notice of cessation or completion of your construction project, you must
within 10 days after recording, send a copy of the notice of completion to your
contractor and the person or firm that has given you this notice. The notice must be
sent by registered or certified mail. Failure to send the notice will extend the deadline
to record a claim of lien. You are not required to send the notice if you are a residential
homeowner of a dwelling containing four or fewer units."�-
Dated: 11 day of Sept. 2017
Valley Ind. Mech. Agent for CLAIMANT
Signed by: Raymond J Rivera