PUBLIC WORKS / ENGINEERING UPDATE:
1. Scott/I-215 Bridge Demolition
2. Traffic Signal Interconnect Project to start January 2020
3. ADA ramps and countdown timer pedestrian signal project at intersections to
start February 2020
4. Sidewalk construction on McCall between Oakhurst and Junipero nearing
completion. Sidewalk completed on Newport Road near Murrieta Road.
5. Goetz Road paving and striping design nearing completion with construction
expected to start in April 2020. City of Perris is currently paving their portion
of Goetz Road.
6. Newport Road slurry and new striping west of Murrieta Road to start April
2020.
7. Other Arterials planned for slurry in April 2020 are: Scott Road east of I-215,
Briggs Road north of Scott Road, Menifee Road south of Scott Road, Leon
Road south of Scott Road, Murrieta Road between McCall Road and Rouse
Road.
8. Road reconstruction and paving planned for May 2020: Sherman Road north
of Ethanac, Ethanac between Trumble and Matthews, Matthews east to
Palomar Road.
9. Newport/Long Valley traffic signal upgrade.
10. EMWD traffic control plan for Murrieta Road.