PUBLIC WORKS / ENGINEERING UPDATE:
1. Liberty High School – Scott/Leon traffic signal and street improvements being
discussed with other agencies.
2. Active Transportation Plan – Kickoff meeting was held on May 7.
3. Traffic Signals at McCall/Hospital and Murrieta/Park City – Bid was opened on
May 2. To City Council on June 5 to award. Construction to begin July 2019.
4. Antelope improvements between Newport and Stillwater – Construction to start
in about 2-3 weeks. Lanes will be shifted on Antelope to provide a southbound
u-turn at Stillwater and keep drivers from making u-turns in residential
neighborhood. Triple southbound lefts and double northbound rights with overlap
will be included.
5. Mesa View Elementary School safety evaluation. Met with principal and County
Traffic Engineer and will be adding signage and striping to improve safety during
pick-up/drop-off times
6. SSARP Presentation to Council on June 5.
7. Reprogrammed the traffic signal near Paloma Valley High School
(Holland/Bradley) to improve safety for pedestrians by giving an advance walk
before vehicles receive green light.
8. Quail Valley area slurry project to start July 1, 2019.
9. Mira Lago neighborhood ADA ramp improvements have begun. Slurry to begin
second week of May 2019.
10. Encanto Drive neighborhood south of Ethanac a nd east of Encanto Drive street
overlay to begin June 2019.